WEBVTT

00:00:00.322 --> 00:00:08.008
- I call to order tonight's meeting of the Board of Public Works for March 24th, 2026. First on our agenda

00:00:08.008 --> 00:00:15.401
- is opening of bids. I assume we have no bids to open. Okay. Next is messages from board members. Any

00:00:15.401 --> 00:00:18.622
- messages from the board tonight? All right.

00:00:18.818 --> 00:00:27.886
- Moving along, we will go to agenda item number three, which is appeals. And we have requests for appeal

00:00:27.886 --> 00:00:36.605
- of notice of violation issued to Wells and Wells on September 20th, 2025. From engineering. So just

00:00:36.605 --> 00:00:44.190
- to give some background on this, it will be appeal. So the summary of this would read,

00:00:44.450 --> 00:00:50.825
- Engineering staff finds that Wells and Wells had both an approved extension and advanced written notice

00:00:50.825 --> 00:00:57.078
- of the deadline of potential enforcement action as it relates to this NOV or notice of violation. The

00:00:57.078 --> 00:01:03.760
- roadway restoration work was not completed within the permitted timeframe and staff does recommend upholding

00:01:03.760 --> 00:01:07.070
- the notice of violation and the associated penalties.

00:01:07.298 --> 00:01:14.501
- So the right-of-way permit associated with this work was approved by the board on May 20th of 2025,

00:01:14.501 --> 00:01:21.704
- and then issued June 5th of 2025 for roadway and utility work along East 19th Street, North Lincoln

00:01:21.704 --> 00:01:29.267
- Street, and North Washington Street, all associated with the Hub 2 project. The permit included a phased

00:01:29.267 --> 00:01:37.118
- schedule for roadway closures and restoration work with a scheduled completion date of September 19th, 2025.

00:01:37.698 --> 00:01:46.327
- At the request of the contractor the board approved an extension. I'm sorry, that was a September August

00:01:46.327 --> 00:01:55.285
- 12 for the first one, and then requested an extension to September 19, giving the final date for restoration

00:01:55.285 --> 00:01:58.654
- to be completed of September 19 of 2025.

00:01:58.914 --> 00:02:04.400
- Prior to the extended deadline, engineering staff notified the contractor on September 12th, 2025 that

00:02:04.400 --> 00:02:09.887
- the failure to reopen the affected streets and restore the roadway surfaces by the approved date could

00:02:09.887 --> 00:02:15.533
- result in an enforcement action. Despite the notification, roadways weren't restored within the permitted

00:02:15.533 --> 00:02:21.073
- timeframe. Documentation photographs associated with the notice of violation show that the base asphalt

00:02:21.073 --> 00:02:26.559
- did not occur, paving did not occur until September 20th through 24th of 2025, days after the approved

00:02:26.559 --> 00:02:27.678
- completion deadline.

00:02:28.386 --> 00:02:36.512
- With those thoughts in mind we support upholding the notice of violation Yes, I believe we

00:02:36.512 --> 00:02:45.799
- have representative of Wells and Wells here if you'd like to make a statement to the board or now would

00:02:45.799 --> 00:02:55.086
- be your time Yeah, Jesse Graber with Wells and Wells construction representing Wells and Wells and core

00:02:55.086 --> 00:02:56.158
- development

00:02:56.578 --> 00:03:05.582
- the owners. So first of all, I do actually want to thank Kyle and Zach and Maria and the entire

00:03:05.582 --> 00:03:15.805
- transportation board for working with us so diligently on the project. It has been difficult. We acknowledge

00:03:15.805 --> 00:03:25.278
- and do not dispute the fact that the project for the basically the public improvements of that block

00:03:25.442 --> 00:03:33.785
- through private development did to go past our permitted timeframe. I'm not going to take a lot of your

00:03:33.785 --> 00:03:42.289
- time. I just have a few bullet points here that I would like for the board to consider and transportation

00:03:42.289 --> 00:03:47.102
- to consider. We applied for a grading permit in the fall of

00:03:47.234 --> 00:04:16.190
- to the community that you know this road work was

00:04:16.866 --> 00:04:25.119
- I do just want to comment, and this is not negativity or criticism, but at no point in time during the

00:04:25.119 --> 00:04:33.452
- entire planning process was a restriction that this work had to be completed during a summer break ever

00:04:33.452 --> 00:04:41.464
- made known until we applied for the road permit. Had we known that the work being required over the

00:04:41.464 --> 00:04:44.990
- summer break was going to be a requirement,

00:04:45.698 --> 00:04:53.603
- we could have phased the initial project differently, but by that point in time, it was far too late

00:04:53.603 --> 00:05:01.430
- in the planning and process. So the road work being completed during summer break was a requirement

00:05:01.430 --> 00:05:09.414
- that came up when we applied for the road work permit. We acknowledged that our contractors agreed to

00:05:09.414 --> 00:05:14.110
- it, but what we did not anticipate was that IDEM would take

00:05:14.210 --> 00:05:21.991
- the full three months to approve the sewer permit. What we did not anticipate was the amount of rock

00:05:21.991 --> 00:05:29.849
- that was in the street. We beat out about $500,000 worth of rock to put those public improvements in.

00:05:29.849 --> 00:05:37.861
- And what we did not anticipate was the six days that the site was shut down to gas line leaks that both

00:05:37.861 --> 00:05:43.870
- the fire department and Centerpoint Energy responded to with emergency calls.

00:05:44.706 --> 00:05:59.903
- We would ask the board's consideration that the dollar amount of the fine be applied towards the improvement

00:05:59.903 --> 00:06:13.566
- of Washington Street from 19th along the west side of Washington Street that is not a part of our

00:06:14.210 --> 00:06:24.024
- Work-in-process or approved plans, but we recognize as a developer and contractor that the west side

00:06:24.024 --> 00:06:34.032
- of that street is not in a finished state Probably was not fully addressed by by Plan by our plans and

00:06:34.032 --> 00:06:37.822
- by the design of the project fines are

00:06:38.530 --> 00:06:47.485
- punitive to our subcontractors. And Crider and Crider, the subcontractor on this, worked six to seven

00:06:47.485 --> 00:06:56.703
- days a week, 80 to 90 hours a week trying to achieve this goal. It was not achievable by reasons outside

00:06:56.703 --> 00:07:03.902
- of their control. We recognize as a developer that we did impact the community as

00:07:04.258 --> 00:07:13.571
- As a compensation, we would like to use the money to improve towards an improvement of Washington Street

00:07:13.571 --> 00:07:22.528
- that has been brought up by transportation and by Maria and Kyle. If that is agreeable to the board,

00:07:22.528 --> 00:07:31.486
- we would be happy to buy that offsetting the fine amount towards capital improvement of that street.

00:07:32.578 --> 00:07:38.821
- I'll jump in here. You know, we wouldn't be able to just negotiate that on the floor of a board meeting

00:07:38.821 --> 00:07:44.824
- at this point in time, having no prior requests of that type. Does the board mind if I ask a couple

00:07:44.824 --> 00:07:49.086
- questions of the petitioner? Is that okay? So of the appellant, sorry.

00:07:49.378 --> 00:07:54.822
- You're stating that the holdups were with IDEM and others, and this will impact the subcontractors who

00:07:54.822 --> 00:08:00.529
- are working so hard at this. What I'm confused about is that we were working directly, that the engineering

00:08:00.529 --> 00:08:05.920
- staff was working directly with you and Wells and Wells to set the timelines for the extensions. They

00:08:05.920 --> 00:08:11.311
- let you know when the deadlines would need to be met. You know, how does that fall to a subcontractor

00:08:11.311 --> 00:08:15.486
- to be at fault? Why would Crider and Crider be at fault at that point in time?

00:08:16.386 --> 00:08:23.621
- They were present at the very initial meeting with transportation provided and agreed to the dates.

00:08:23.621 --> 00:08:30.929
- In hindsight, we would have asked that Crider and Crider pull the permit, but historically Wells and

00:08:30.929 --> 00:08:38.236
- Wells construction as the general contractor pulls the permit. They say that businesses pay no taxes

00:08:38.236 --> 00:08:43.518
- and businesses pay no tariffs. General contractors don't really ever pay

00:08:43.618 --> 00:08:52.314
- fines either, you know, these do flow down to the subcontractors that that's impacted. And we do,

00:08:52.314 --> 00:09:01.365
- you know, we're cognizant of the fact that, you know, they they put in the effort, they had agreed to

00:09:01.365 --> 00:09:10.239
- dates that were not achievable, but they were not achievable because of conditions that were hidden

00:09:10.239 --> 00:09:12.990
- and unknown at the time. Okay.

00:09:15.458 --> 00:09:20.557
- We've had construction projects come to this board in my 12 years that have known time and time again

00:09:20.557 --> 00:09:25.805
- that this community has rock under every road and that you're gonna have to beat it out and you're gonna

00:09:25.805 --> 00:09:31.204
- have to do these things as part of these developments. Based on what's been, what I know is the engineering

00:09:31.204 --> 00:09:36.302
- staff is working with Wells and Wells to try to set dates that could be achievable. We were certainly

00:09:36.302 --> 00:09:41.401
- hopeful this work would have been happening before the students return. Then we got into the football

00:09:41.401 --> 00:09:44.350
- season, kept trying to work with you folks to get it done.

00:09:44.482 --> 00:09:51.176
- quick fashion. Based on what I've heard, I don't know that we would recommend anything other than upholding

00:09:51.176 --> 00:09:57.621
- the fine as has been presented by the engineering department. I don't think this is one where we could,

00:09:57.621 --> 00:10:03.819
- given the timelines and everything else, start considering other types of, you know, trying to make

00:10:03.819 --> 00:10:10.141
- other public improvements and things. You know, I just don't see how that could be negotiated at this

00:10:10.141 --> 00:10:12.062
- point in time, given that it's

00:10:12.162 --> 00:10:18.884
- eight months after when these fines were issued and such. So we did the eight months past was not our

00:10:18.884 --> 00:10:25.738
- timeline. I'm saying since October, November, December, January, February, March, six months later from

00:10:25.738 --> 00:10:32.328
- when these fines were issued to start trying to think about other negotiated improvements and such.

00:10:32.328 --> 00:10:39.050
- I don't think that's a route that we well, that was that was an offer that was made to transportation

00:10:39.050 --> 00:10:41.950
- prior to the fines even being issued. Okay.

00:10:42.050 --> 00:10:51.605
- And the fact that it's six months later, we appealed as soon as we were notified of the fines. It was

00:10:51.605 --> 00:11:01.253
- initially denied. We requested again for the appeal. It was then reconsidered. And we're here at your,

00:11:01.253 --> 00:11:10.620
- we understand that we're asking for your grace in this situation, but had we not had gas leaks from

00:11:10.620 --> 00:11:11.838
- Centerpoint,

00:11:11.938 --> 00:11:21.141
- You know that did shut the site down for six days. We wouldn't be standing here. You know today we would

00:11:21.141 --> 00:11:30.168
- be within our time frames. And I certainly don't want to drag other city departments into this but you

00:11:30.168 --> 00:11:39.195
- know city Bloomington utilities was working in the streets while we were supposed to be paving. I mean

00:11:39.195 --> 00:11:40.510
- it truly was a

00:11:41.122 --> 00:11:51.644
- difficult Project with many unforeseen circumstances some very last-minute changes that was requested

00:11:51.644 --> 00:12:02.063
- by CBU Gas leaks that shut us down You know late permits by the state they all came together and you

00:12:02.063 --> 00:12:04.126
- know, my team did a

00:12:04.802 --> 00:12:10.628
- do everything that they could possibly do during those home football games to provide safe passage for

00:12:10.628 --> 00:12:16.341
- the students on the sidewalks, you know, all the way to the extent of snow fencing around the entire

00:12:16.341 --> 00:12:22.280
- site and providing, you know, safe passage on the sidewalks. And those sorts of things would be required

00:12:22.280 --> 00:12:27.993
- from any major development. I mean, that's beside the fact. You know, that's required as part of any

00:12:27.993 --> 00:12:33.310
- major development. You know, where I'm struggling with trying to make any sense of it is that

00:12:33.410 --> 00:12:40.558
- The petitioner was the one asking for the extensions the extensions got granted. Those were they agreed

00:12:40.558 --> 00:12:47.430
- upon dates You know the the gas mains and other things those are I don't understand how if if those

00:12:47.430 --> 00:12:54.990
- timelines are agreed to what different I'm just struggling to understand how that impacts what the contractor

00:12:54.990 --> 00:12:59.870
- Wells and Wells agreed to to have this road restored well if we have a

00:13:00.546 --> 00:13:09.352
- We did not have work durations. We had deadlines, which we acknowledge. We acknowledge. There's no question

00:13:09.352 --> 00:13:17.669
- about the fact that we had deadlines. Had we had those six days back from the site being shut down by

00:13:17.669 --> 00:13:26.067
- services, again, we would have met the deadline and beat the durations. Can I ask a relevant question?

00:13:26.067 --> 00:13:28.350
- What were the dates of that

00:13:28.770 --> 00:13:35.720
- and the associated shutdown? I would have to check, I don't have those dates with me, but I know there

00:13:35.720 --> 00:13:42.670
- was three separate occurrences with the fire department and CenterPoint for repairing gas leaks in the

00:13:42.670 --> 00:13:49.484
- road. Were they prior to the first extension request? That's what I was getting at. One was prior to

00:13:49.484 --> 00:13:55.422
- the first extension request, two were after. And what were the causes of the gas leaks?

00:13:55.906 --> 00:14:04.963
- The gas line in the street is one of the original old cast iron gas lines. It's extremely close to the

00:14:04.963 --> 00:14:13.932
- surface of the road. And as construction took place, any vibrations, we don't have a direct knowledge

00:14:13.932 --> 00:14:21.758
- of what caused them. They were not hits. They were not utility strikes. It was gas line.

00:14:22.690 --> 00:14:35.088
- the gas line itself leaked through deterioration of the existing line. I have a couple of questions

00:14:35.088 --> 00:14:48.478
- for staff, if I may. One question about the fine table. And if I'm reading this correctly, the fines starts

00:14:50.914 --> 00:14:57.286
- at the original amount, in this case $100, then it goes twice, then twice again. The fine table we show,

00:14:57.286 --> 00:15:03.719
- or we have, shows Lincoln $100 and then it goes to 400 instead of just up to 200, which would be doubling

00:15:03.719 --> 00:15:10.091
- the 100 amount. Why is it going up four times instead of twice? I did print out the Notice of Violation,

00:15:10.091 --> 00:15:16.766
- but unfortunately it's the wrong violation, so I don't have a direct answer without that in front of me here.

00:15:16.930 --> 00:15:26.181
- I can say that the process for those is an evaluation of an occurrence on a per day basis on a per block

00:15:26.181 --> 00:15:35.081
- phase. So if we start at $100, we should move to 200, 400, et cetera. This is a complicated site, as

00:15:35.081 --> 00:15:44.420
- Jesse mentioned. So for this NOV, thank you. Sorry, it's going from the top down. Yeah, so the formatting

00:15:44.420 --> 00:15:45.918
- we worked around

00:15:46.050 --> 00:15:53.649
- Obviously, it's not super clear. So yeah, those are violations of the same day, different locations

00:15:53.649 --> 00:16:01.476
- associated with the same project and the same violation type. Then it doubles the second day, correct?

00:16:01.476 --> 00:16:09.151
- Correct. And does this not quadruple? Or am I reading this totally incorrectly? It's every violation

00:16:09.151 --> 00:16:15.838
- by the permit holder. And so there were two violations on the 20th. So 100, it doubled.

00:16:16.002 --> 00:16:23.713
- 200, next violation is a doubling of 400. So on 921, it became 400. Oh, it's not the 100 that gets doubled

00:16:23.713 --> 00:16:31.137
- to two and the 200 that gets. Right, so I just started with Lincoln as the first location for the next

00:16:31.137 --> 00:16:39.064
- following day there. So every violation doubles across the days. Is that, like, there are multiple violations

00:16:39.064 --> 00:16:45.118
- happening. It says the quick violations are twice the previous fine of two minutes.

00:16:47.778 --> 00:16:53.497
- Yeah, in code it dictates whenever we're looking at a closure request, it's per block phase. So those

00:16:53.497 --> 00:16:59.160
- are two separate occurrences on the same day for separate locations assigned to the same contractor,

00:16:59.160 --> 00:17:05.047
- if that makes sense. Okay, and I was reading it across, and then the Washington would be a second. Okay,

00:17:05.047 --> 00:17:10.991
- I understand now, thank you. My second question is the notice of violation was September 20th. The appeal

00:17:10.991 --> 00:17:16.990
- was written on December 11th, which is still longer than the seven days. Can you talk us through just the,

00:17:17.314 --> 00:17:25.346
- The appeal was initially denied. It's getting to us late. Correct. So there were a series of NOVs and

00:17:25.346 --> 00:17:33.614
- subsequent appeals that all came in in the same time frame. This was the first one of those four appeals

00:17:33.614 --> 00:17:41.568
- that had gone through. The dating was scant to support not hearing it. And once we got that reviewed

00:17:41.568 --> 00:17:46.686
- by legal, they brought it back to our attention. They said, hey,

00:17:46.818 --> 00:17:53.305
- what we would like to hear this. At the same time, as we were working through these multiple NOVs for

00:17:53.305 --> 00:17:59.793
- this particular site, we were realizing that we needed to improve some of our internal process on how

00:17:59.793 --> 00:18:06.153
- those are communicated to the developers and who and when and how decisions of the board on appeals

00:18:06.153 --> 00:18:12.958
- are then communicate. So not only how we communicate when they're heard and how they need to be submitted,

00:18:13.058 --> 00:18:19.167
- whether it's engineering staff or public work staff that take those in. So we've been working on our

00:18:19.167 --> 00:18:25.275
- internal process for this. So when, and Miranda might have to jump in to correct me when I say this,

00:18:25.275 --> 00:18:31.384
- when a notice of violation is issued, it gets sent directly to the parties that are being issued the

00:18:31.384 --> 00:18:36.222
- NOV. From there, the appeal says it should come to the public works department.

00:18:36.290 --> 00:18:41.641
- Sometimes the appeals at that point in time were going to engineering because the developers or the

00:18:41.641 --> 00:18:47.206
- permit holders were working very closely with engineering. Engineering issued it, and so there was just

00:18:47.206 --> 00:18:52.878
- some confusion on the dates and times of when each one was communicated about, and so we did just decide,

00:18:52.878 --> 00:18:58.443
- hey, we're gonna hear the appeal. It might not have met our deadlines, but given some of that confusion

00:18:58.443 --> 00:19:04.062
- since then, we've come up with an internal process of who communicates what when, including the decision

00:19:04.062 --> 00:19:06.256
- of the board when the appeals are heard,

00:19:06.256 --> 00:19:14.821
- how that official communication goes back to the appellants and such. So, yes. Yeah, it was a situation

00:19:14.821 --> 00:19:23.056
- where a letter was mailed to our office in Champaign, but it was over obviously Thanksgiving break.

00:19:23.056 --> 00:19:31.373
- So it literally was not opened. The letter wasn't even opened and received by our office until after

00:19:31.373 --> 00:19:35.326
- the appeal deadline had passed. And that's when

00:19:35.458 --> 00:19:43.399
- you know, we had reached out to Kyle and his team and and started that process basically the first of

00:19:43.399 --> 00:19:51.339
- December, which leads us here to today. So I have a question just about generally some of the factors

00:19:51.339 --> 00:19:59.280
- that caused your delays, because there are several things issued here about the delays that have been

00:19:59.280 --> 00:20:04.574
- caused. Were any of these items, did any of these items take place?

00:20:04.866 --> 00:20:13.840
- between the August 12th and September 19th time of the permit extension Yes, and which ones took place

00:20:13.840 --> 00:20:23.163
- during that time two of the gas leaks the city Bloomington utility work on Lincoln which was an excavation

00:20:23.163 --> 00:20:31.877
- of the street and then And it's not an unknown. I 100% agree. It's not an unknown but the continued

00:20:31.877 --> 00:20:34.142
- rock excavation that just

00:20:34.242 --> 00:20:42.736
- Was far beyond the borings that we if you recall we had a hearing for an approval to do 10 borings on

00:20:42.736 --> 00:20:51.897
- the street and you know, we had 10 borings on basically eight acres and it was not it was just not indicative

00:20:51.897 --> 00:20:56.894
- of the quantity or the height of the rock in those areas it

00:20:56.962 --> 00:21:04.144
- Even, yes, we've worked in Bloomington. I busted out $2 million worth of Rocket Hub 1. We know it's

00:21:04.144 --> 00:21:11.541
- here. You know where it's not? Under the garage where I spent a million dollars trying to find it, so.

00:21:11.541 --> 00:21:18.867
- You know Bloomington. It is, if you take 10 borings on an eight acre site, you don't know what's down

00:21:18.867 --> 00:21:23.966
- there. But you can't dig up the street to explore it either, you know.

00:21:24.706 --> 00:21:34.972
- So it was those three factors between the permit and the extension, but the extenuating circumstance

00:21:34.972 --> 00:21:45.137
- of the IDEM state permit being issued on July, which allowed us to begin utilities, was the driving

00:21:45.137 --> 00:21:52.862
- factor to the situation. I follow up question to... Manicure. The CBU work,

00:21:53.122 --> 00:22:01.549
- that took place between the 12th and the 19th. Were you aware that it was going to happen before the

00:22:01.549 --> 00:22:10.059
- 12th? No. You thought all the CBE work was done? We weren't aware it was happening at all. They don't

00:22:10.059 --> 00:22:19.070
- ask us, so. It was work that was not associated with the project? No, it was not. So obviously these things

00:22:19.202 --> 00:22:29.586
- happen, you know, surprising elements happen. When engineering had the conversation on September 12th,

00:22:29.586 --> 00:22:39.970
- so this was a week prior to the expiration of the permit, my sense is engineering had a sense that the

00:22:39.970 --> 00:22:45.918
- project was not going to wrap up in time for the deadline.

00:22:46.370 --> 00:22:55.308
- What was that conversation like in the sense of, was there a discussion about a permit extension?

00:22:55.308 --> 00:23:04.519
- And if so, what was the result of that conversation? We had asked, we were told that it wasn't, that

00:23:04.519 --> 00:23:11.998
- an extension of an extension was not allowed. So while there was cooperation and,

00:23:12.450 --> 00:23:21.004
- And what we felt and still feel was an understanding of the conditions of the situation. I also understand

00:23:21.004 --> 00:23:28.918
- that, you know, if an extension of an extension is simply not something that's able to be written,

00:23:28.918 --> 00:23:37.632
- everybody's hands at that point in time were kind of bound. You know, I do, you know, just want to readdress

00:23:37.632 --> 00:23:40.190
- that, I mean, we poured asphalt

00:23:40.770 --> 00:23:50.179
- In in the rain. I mean we we kept the plants open for this project. The crews and the superintendents

00:23:50.179 --> 00:23:58.942
- involved in this did everything they could possibly do and and I I mean I live in Bloomington.

00:23:58.942 --> 00:24:02.078
- I live here. I'm on the job site.

00:24:02.242 --> 00:24:10.363
- every single day and there's nothing as the project director and the liaison directly back to the owner

00:24:10.363 --> 00:24:18.407
- in Chicago. I mean, there's nothing that I know of that could have been done that could have prevented

00:24:18.407 --> 00:24:26.528
- this situation. So, you know, we're not here to fault anybody. We're just asking for your consideration

00:24:26.528 --> 00:24:27.934
- in the situation.

00:24:28.770 --> 00:24:36.123
- I have a follow-up to a follow-up, I think. The CBU work, if it was not related to the project, do we

00:24:36.123 --> 00:24:43.115
- know if it happened prior to that conversation on September 12th, between the 12th and the 20th?

00:24:43.115 --> 00:24:50.612
- It did, and we were in conversation with Kyle and Maria about that as well. And I am not going, we have

00:24:50.612 --> 00:24:57.893
- a great working relationship with every department here. I'm not going to blame CBU for the reasons,

00:24:57.893 --> 00:24:58.686
- it's just,

00:24:58.914 --> 00:25:11.116
- Those are all of the reasons. I think it's questions for Kyle. Setting and negotiating timelines and

00:25:11.116 --> 00:25:24.406
- deadlines. There's been a lot of discussion about that late item permits. When a developer, when a contractor

00:25:24.406 --> 00:25:28.030
- permit holder comes and says,

00:25:28.194 --> 00:25:38.100
- This is my anticipated schedule. Do you say, great, we're gonna hold you to that? Or is there discussion,

00:25:38.100 --> 00:25:47.538
- negotiation? If there are extenuating circumstances, a late state permit, do they ever come back and

00:25:47.538 --> 00:25:52.958
- say, we need to reevaluate the timeline that we gave you?

00:25:53.634 --> 00:26:00.132
- Sure, I would say first and foremost, it's completely context-based. The approval of the original permit

00:26:00.132 --> 00:26:06.321
- was under the basis that we would be able to get it completed prior to the IU school year starting.

00:26:06.321 --> 00:26:12.819
- We saw the initial push to September from that August date and thought, you know, we can make this work.

00:26:12.819 --> 00:26:19.070
- And if I can be frank, this was a situation where we really just needed to rein the project back in.

00:26:19.202 --> 00:26:25.502
- the state of the road and I completely understanding there's not much space to operate there with, but

00:26:25.502 --> 00:26:31.924
- we essentially had what amounted to gravel roads on Lincoln, Washington and 19th before the intermediate

00:26:31.924 --> 00:26:38.102
- layer of asphalt was laid. And that's why we don't see 19th Street listed in the notice of violation

00:26:38.102 --> 00:26:44.830
- because we did have that intermediate layer of asphalt to make it at least passable for the traveling public.

00:26:53.602 --> 00:27:02.566
- I do not believe you were a part of the very original meeting that we had with transportation, okay.

00:27:02.566 --> 00:27:11.441
- These dates were not the dates we came and asked for. We were told no, it was dead in the water. We

00:27:11.441 --> 00:27:20.404
- asked for three months. We were given eight weeks. And that's not atypical for projects. Understand,

00:27:20.404 --> 00:27:23.422
- understand. But to your question,

00:27:23.938 --> 00:27:32.872
- It was, but we didn't have a choice because the sewer line and the storm line ran directly through the

00:27:32.872 --> 00:27:41.892
- project. The project was dead in the water without the reroute. And that goes back to one of my opening

00:27:41.892 --> 00:27:50.566
- statements. It's just an unfortunate confluence of situations, but the entire project was dependent

00:27:50.566 --> 00:27:52.734
- upon rerouting the storm

00:27:53.346 --> 00:28:03.621
- in the sewer around the street that ran through the project. And it was at our permit application that

00:28:03.621 --> 00:28:13.996
- the limitation of constructing all of that infrastructure during the school break was first made aware.

00:28:13.996 --> 00:28:22.974
- As a developer, we had no choice but to accept those constraints or the project was dead.

00:28:23.714 --> 00:28:31.335
- And we have no choice here either, but to abide by your decision. But again, without repeating, those

00:28:31.335 --> 00:28:38.956
- are all the factors that went into. And yes, it was a gravel street, but every single night and every

00:28:38.956 --> 00:28:45.980
- single morning and every single time a resident needed to get to their residence, it may have

00:28:45.980 --> 00:28:49.342
- been inconvenienced, I get it, construction,

00:28:49.666 --> 00:28:58.926
- tends to do that, but at no point in time was a resident ever denied to the point that we rented, bought

00:28:58.926 --> 00:29:08.097
- 10 parking passes at the home two suites and gave them to a certain address of individuals that created

00:29:08.097 --> 00:29:14.270
- some cause for concern and paid that out of pocket for their parking.

00:29:14.370 --> 00:29:20.940
- parking and again, did everything that we could possibly do to make it as small of an inconvenience

00:29:20.940 --> 00:29:27.642
- as possible while it was a gravel street. I have a question for staff. This is a question I feel like

00:29:27.642 --> 00:29:34.278
- I should know the answer to, but I don't fully understand the nuances of the fee schedule. Are there

00:29:34.278 --> 00:29:41.176
- fees associated with this permit, like the issuance of this permit, any costs associated with the permit

00:29:41.176 --> 00:29:43.870
- for the contractor or the permit holder?

00:29:44.034 --> 00:29:51.341
- Yes, absolutely. So there is a cost associated with any excavation within the right of way based on

00:29:51.341 --> 00:29:58.647
- paved or unpaid surface that is going to be disturbed. There's a cost for every week of a sidewalk,

00:29:58.647 --> 00:30:06.100
- lane, street closure. So all of those are based on the timeline that's given to us by contractors. Do

00:30:06.100 --> 00:30:13.918
- you happen to know, and it's OK if you don't, this was not asked at any point prior, what the cost of this

00:30:14.082 --> 00:30:21.490
- permit was, like even roughly, but it's okay if you don't have that number. If you promise not to quote

00:30:21.490 --> 00:30:28.898
- me. I believe lane closures are $200 a week. Permit fees $100 for the review of said permit. I couldn't

00:30:28.898 --> 00:30:32.958
- even make a guess as to what the actual disturbance was.

00:30:33.058 --> 00:30:38.945
- I can say that, you know, once this extension came in and, you know, we were reviewing everything and

00:30:38.945 --> 00:30:44.890
- trying to play catch up to make sure that everything was driving from our internal systems. We did ask

00:30:44.890 --> 00:30:50.892
- that Wells and Wells, you know, paid for the extension and the time they went past on all that to which

00:30:50.892 --> 00:30:53.374
- they have done since then to their credit.

00:30:53.762 --> 00:31:03.191
- I do, yes. The original permit fee was somewhere in the $4,200 range. Since then, we have paid an additional

00:31:03.191 --> 00:31:12.014
- $10,000 in permitting for the use of the street during construction. So we're about right at roughly,

00:31:12.014 --> 00:31:20.924
- if you don't quote me, roughly $15,000 in permitting directly attributed to the streets and the street

00:31:20.924 --> 00:31:22.654
- use and work there.

00:31:23.170 --> 00:31:33.144
- And that was for the permitting for the dates of, let's see, June 5th through what ultimately was September

00:31:33.144 --> 00:31:42.842
- 19th? In fairness, it's permits for the duration of the project. So it extends, it includes this period,

00:31:42.842 --> 00:31:49.214
- but extends past it, yes. Okay. Additional questions from the board?

00:31:54.178 --> 00:32:01.904
- All right, I'll make a suggestion and knowing that staff has approached wells and wells about the possibility

00:32:01.904 --> 00:32:06.750
- of investing this fine amount into other improvements near the site.

00:32:07.010 --> 00:32:12.747
- and knowing Mr. Graber is local. If it's okay with Mr. Graber, we'll table this for right now. And it's

00:32:12.747 --> 00:32:18.539
- not to say that it won't come back and come to the board for the same exact decision we would be seeking

00:32:18.539 --> 00:32:24.277
- tonight. But I'll give it the two week. I think we can give it the two weeks for engineering to discuss

00:32:24.277 --> 00:32:29.848
- and determine if that amount being invested in the west side of the road makes sense for us. I don't

00:32:29.848 --> 00:32:35.806
- know that it does. I'm not sure where things stand there. That's the first we've heard of it at this level.

00:32:36.258 --> 00:32:42.465
- I think if we can just do that for two weeks. If two weeks from today you could agree to be here again

00:32:42.465 --> 00:32:48.793
- and maybe at that point in time we can have this all figured out in terms of how to do that. But I guess

00:32:48.793 --> 00:32:55.120
- I'd ask you to table it for now and then we'll come back in two weeks with either an update to the board

00:32:55.120 --> 00:33:01.388
- on what took place or was agreed to or if we would ask for a final decision on the appeal at that time.

00:33:01.388 --> 00:33:04.702
- So just a motion to table. Is there a motion to table?

00:33:05.282 --> 00:33:13.388
- I move that we table the request for appeal of notice of violation issued to Wells and Wells on September

00:33:13.388 --> 00:33:21.034
- 20th, 2025. Second. Hearing a second, I'll take the roll. Cox-Deckard? Aye. Roach? Aye. Caron? Aye.

00:33:21.034 --> 00:33:26.846
- Motion to table passes. Thank you. Thank you very much. Thanks. You betcha.

00:33:28.514 --> 00:33:38.090
- Next on our agenda is petitions and remonstrances. This is time for the public to make comment on anything

00:33:38.090 --> 00:33:47.039
- that is not on our agenda. Seeing no one in council chambers, if there is anyone on Zoom, feel free

00:33:47.039 --> 00:33:56.257
- to use the raise hand function or chat. All right, moving along to the consent agenda, we have minutes

00:33:56.257 --> 00:33:58.494
- from January 13th, 2026.

00:33:58.626 --> 00:34:05.053
- Minutes from January 27, 2026, Resolution 2026-014, Mobile Vendor Travel and Tom's Coffee, Right of

00:34:05.053 --> 00:34:11.738
- Way Special Event for the Tuesday Farmer's Market, Right of Way Special Event for the Saturday Farmer's

00:34:11.738 --> 00:34:18.616
- Market, Right of Way Special Event for the Bloomington Handmade Market, Outdoor Lighting Service Agreement

00:34:18.616 --> 00:34:25.172
- with Duke Energy for South Southern Pines Court, Public Improvement Bond Estimate and Street Lighting

00:34:25.172 --> 00:34:27.614
- Plan Waiver for Oakstead Subdivision,

00:34:27.778 --> 00:34:34.929
- Supplemental number three to construction contract with Crossroads Engineering for Beeline Extension

00:34:34.929 --> 00:34:42.151
- Project. On-call service agreement with Blood, So, Rigort, Cooper, and James for engineering services

00:34:42.151 --> 00:34:49.515
- and payroll. Is there anything that needs to be removed from the consent agenda tonight? Does the board

00:34:49.515 --> 00:34:57.374
- have any questions on tonight's consent agenda? Is there public comment on the consent agenda? Anyone on Zoom?

00:34:58.434 --> 00:35:07.568
- All right, is there a motion? I move that we approve the consent agenda for this meeting on March 24th

00:35:07.568 --> 00:35:16.613
- of 2026. Second. I will call the roll. Cox-Deckard? Aye. Roach? Aye. Caron? Aye. Motion passes. First

00:35:16.613 --> 00:35:25.570
- on the new business agenda is the Pete Ellis discovery transfer with NDOT. Good evening, Neil Popper

00:35:25.570 --> 00:35:27.166
- with Engineering.

00:35:27.394 --> 00:35:34.179
- This is an Indiana Department of Transportation project. It's on State Route 45. It includes the intersection

00:35:34.179 --> 00:35:40.408
- with Pete Ellis and Discovery Parkway, which is the city's infrastructure. The project dates back to

00:35:40.408 --> 00:35:46.823
- before the hospital relocation and identification of some safety concerns in that area. This memorandum

00:35:46.823 --> 00:35:52.991
- of agreement would temporarily transfer portions of Pete Ellis Drive and Discovery Parkway from the

00:35:52.991 --> 00:35:53.854
- city to NDOT.

00:35:53.954 --> 00:35:59.463
- for construction and then after project completion those roadways would transfer back to the city. The

00:35:59.463 --> 00:36:04.811
- memorandum of agreement also clarifies the city's maintenance responsibilities for the sidewalk and

00:36:04.811 --> 00:36:07.806
- multi-use paths that are being constructed in the area.

00:36:08.418 --> 00:36:16.037
- An aspect of this project that has gotten a lot of public attention is the plan to remove 15 mature

00:36:16.037 --> 00:36:23.733
- oak trees on the south side of SR 45 on Pete Ellis. We've had significant coordination with NDOT and

00:36:23.733 --> 00:36:31.504
- we are going to be able to save eight of those 15 trees. This transfer agreement wouldn't normally be

00:36:31.504 --> 00:36:36.990
- required to approve the tree removal that has been discussed a lot, but

00:36:37.090 --> 00:36:42.925
- we've been coordinating with our urban forester and typically that would be more of a staff-level approval.

00:36:42.925 --> 00:36:48.437
- But given that it's wrapped up in our discussions with NDOT and there's been so much attention on it,

00:36:48.437 --> 00:36:53.894
- we did want to bring it in front of you specifically just for that transparency, just wanting you to

00:36:53.894 --> 00:36:59.405
- be aware of it and that it is a part of this project. We discussed that at the work session yesterday

00:36:59.405 --> 00:37:00.702
- and noted that it would

00:37:00.866 --> 00:37:06.436
- probably occur any day now and today was actually the day that it started occurring. There has been

00:37:06.436 --> 00:37:12.061
- work out there today. I haven't seen it myself. I don't know the extents and for sure that they made

00:37:12.061 --> 00:37:17.630
- it into any of the city trees, but I'm guessing that they did. Unfortunately, the agreement that is

00:37:17.630 --> 00:37:23.479
- in your packet is still not final. We discussed at the work session that there's a typo in the signature

00:37:23.479 --> 00:37:29.438
- line. There's some language on the permitting and inspection that we've been trying to clean up with NDOT.

00:37:29.538 --> 00:37:37.129
- However, due to the time constraints on the project and in our reaching agreement with NDOT, we do want

00:37:37.129 --> 00:37:44.793
- to approve this agreement, at least in principle, and vote to allow a temporary transfer under the terms

00:37:44.793 --> 00:37:51.070
- as written, pending future approval of the memorandum of agreement in its final form.

00:37:51.234 --> 00:37:58.900
- This will allow NDOT to begin managing work that's occurring in that right-of-way, begin working in

00:37:58.900 --> 00:38:06.796
- that right-of-way, avoiding delays to the project. Staff is recommending that we approve the agreement

00:38:06.796 --> 00:38:14.538
- as it's written, allow us to indicate at least this high-level agreement to NDOT, and know that this

00:38:14.538 --> 00:38:21.054
- would come back to you again shortly in its new final form for the formal approvals.

00:38:21.186 --> 00:38:27.748
- Staff, that's what engineering and the legal department have worked out and support, and I would be

00:38:27.748 --> 00:38:34.310
- happy to answer any questions. Thank you. Questions from the board. Regarding the trees, since that

00:38:34.310 --> 00:38:40.938
- is an issue that has had a lot of attention and there's been a lot of conversation and compromise in

00:38:40.938 --> 00:38:46.910
- the way that the trees are handled. Is there a planting plan? Like, do you know if NDOT is

00:38:47.618 --> 00:38:55.444
- planning to plant new trees that don't interfere with the right of way. NDOT is planting a small number

00:38:55.444 --> 00:39:03.194
- of trees. I don't know that there are any planned replacements actually in these areas where the trees

00:39:03.194 --> 00:39:11.020
- are being removed, but we have been working with the Parks Department. One of the things that they have

00:39:11.020 --> 00:39:11.998
- said is that

00:39:12.130 --> 00:39:18.389
- The most important thing to them was protecting as many trees as we could. They had had a goal actually

00:39:18.389 --> 00:39:24.587
- of protecting seven or eight of them and we achieved eight. They also said replanting is what we would

00:39:24.587 --> 00:39:30.785
- typically require in a project and what we want. But what's most important is if we have a space where

00:39:30.785 --> 00:39:36.924
- we can replant, we don't mind as the city going back in and replanting some of those trees ourselves.

00:39:36.924 --> 00:39:40.414
- That's not a huge cost to replant them given that this is

00:39:40.610 --> 00:39:47.685
- or will become city right of way again, we'll have the authority to go in and replant some of those.

00:39:47.685 --> 00:39:54.900
- So the answer is there are some replacements, but not to a scale that we want. That agreement at least

00:39:54.900 --> 00:40:02.044
- hasn't been reached yet, but we do have the ability and the intention of replanting some trees there.

00:40:02.044 --> 00:40:09.049
- Very good. Not a question, but I just wanted to say these improvements have been a long time coming

00:40:09.049 --> 00:40:10.590
- and only exacerbated.

00:40:10.946 --> 00:40:18.030
- I can't talk tonight, by the hospital and changes in that area. And I think East 10th Street has seen

00:40:18.030 --> 00:40:25.114
- a lot of improvements with the pedestrian improvements further to the east on Smith. So thank you for

00:40:25.114 --> 00:40:30.878
- your work and thank you for everyone's involved in saving these atries. Thank you.

00:40:30.978 --> 00:40:39.707
- And just to clarify, this is kind of a phase of NDOT's plans for that whole area, so their project stretches

00:40:39.707 --> 00:40:48.036
- from the bypass to just a little ways east of Pete Ellis, and then continued improvements up past Smith

00:40:48.036 --> 00:40:56.045
- and further would be a future phase. Any other questions from the board? All right, is there public

00:40:56.045 --> 00:40:57.406
- comment on this?

00:40:57.602 --> 00:41:06.346
- Again, if you are on Zoom, feel free to use the raise hand function or chat. None on Zoom. All right,

00:41:06.346 --> 00:41:15.347
- is there a motion? I move that we approve the Pete Ellis discovery transfer with NDOT. Just a clarifying

00:41:15.347 --> 00:41:24.262
- question. Do we need to phrase that in a specific way, since it's not an actual contract approval, such

00:41:24.262 --> 00:41:27.262
- as the board approves the contract

00:41:27.682 --> 00:41:34.476
- concept of the of the transfer So in staff's discussions with legal we kind of asked, you know, what

00:41:34.476 --> 00:41:41.405
- would the motion look like and ultimately the answer was let's just approve it as written just pretend

00:41:41.405 --> 00:41:48.199
- It's a normal item just basically approve it but knowing that it would come back again in the future

00:41:48.199 --> 00:41:54.590
- approve but not sign Yeah, it's just not being signed. It's not in that case second. All right

00:41:55.138 --> 00:42:05.063
- Thank you for clarifying. I will call the roll. Cox-Duckard? Aye. Roach? Aye. Caron? Aye. Motion passes.

00:42:05.063 --> 00:42:15.083
- Thank you. Sorry, Miranda. Next, we have the contract with Sarah Road Mitigation Project with Echo Logic.

00:42:15.083 --> 00:42:19.998
- Hello, Sarah Gomez with the engineering department.

00:42:20.642 --> 00:42:28.374
- here to award the project for the Sarah Road mitigation. The project includes the removal and replacement

00:42:28.374 --> 00:42:35.669
- of 22 dead native trees and the treatment of woody invasive species at an IDNR permitted mitigation

00:42:35.669 --> 00:42:40.702
- site for a former city project from Buttonwood to College Mall Road.

00:42:41.410 --> 00:42:54.500
- Quotes were received at noon on Monday, January 15th, 2026. The quotes were as follows. Steve Chafin,

00:42:54.500 --> 00:43:04.638
- $14,655. EcoLogic, $35,395. Sorry, $35,395.47. And Habitat Solutions, $52,335.

00:43:04.866 --> 00:43:13.491
- Although Steve Chafin was the lowest bidder, it was unresponsive in meeting the city insurance requirements

00:43:13.491 --> 00:43:21.557
- for the quote, and EcoLogic was the second lowest responsible and responsive bidder, and engineering

00:43:21.557 --> 00:43:29.942
- recommends awarding the contract to EcoLogic. Thank you. Questions from the board? Question here. Sarah,

00:43:29.942 --> 00:43:34.814
- I'm at a loss. Where is this located? I'm a little confused.

00:43:36.162 --> 00:43:43.828
- Let's see, just south of where Moores Pike and College Mall intersection is at, the trail that comes

00:43:43.828 --> 00:43:51.569
- down goes over a creek, and there's a pedestrian bridge, and to the right-hand side, if you're headed

00:43:51.569 --> 00:43:59.767
- south, there is about an acre of land that has what looks to be dead trees and shrubbery. A little triangle

00:43:59.767 --> 00:44:06.142
- there at the lighted intersection? Yes, correct. And those were, that was a minute,

00:44:06.274 --> 00:44:14.307
- Those were a mitigation planning from another project. Correct. So the Sarah Wood Sarah Road project,

00:44:14.307 --> 00:44:22.339
- I believe it was in 2019, goes from Buttonwood to College Mall Moores Pike intersection. And that was

00:44:22.339 --> 00:44:30.530
- for that trail extension along there, including that pedestrian bridge, as well as it's associated with

00:44:30.530 --> 00:44:35.806
- I'm sorry, I'm forgetting the name of the street, but in any case,

00:44:36.066 --> 00:44:44.222
- There were a number of trees that were taken down as part of that project. And so the IDNR said we need

00:44:44.222 --> 00:44:52.064
- to have a mitigation site where we can plant other trees because of those trees will not be able to

00:44:52.064 --> 00:44:56.926
- be replaced in their current location. Great. Thank you. Yes.

00:44:57.602 --> 00:45:04.621
- Could you just mention briefly the project schedule, how long it will take for what phases of this?

00:45:04.621 --> 00:45:11.992
- I see it in the service agreement, but it says three one-day visits between April and November. Correct.

00:45:11.992 --> 00:45:19.152
- So they'll come in and it's a process of each item has to be taken care of separately. So there'll be

00:45:19.152 --> 00:45:25.118
- multiple times where they'll come in and they'll do their invasive species spraying.

00:45:25.890 --> 00:45:33.795
- for the kind of ground cover invasive species in shrubs. And then they'll have to do that a number of

00:45:33.795 --> 00:45:42.165
- times. And then they'll come back out for tree removal. And then they'll come back again for tree planting.

00:45:42.165 --> 00:45:50.147
- Yeah, got it, thank you. And we had talked yesterday during the work session about the fact that there

00:45:50.147 --> 00:45:55.262
- is a renewal clause in the agreement that if the work should have

00:45:55.522 --> 00:46:05.863
- should have to continue beyond the planned timeline that we do have the opportunity to renew for another

00:46:05.863 --> 00:46:15.712
- potentially additional two one-year terms if something was needed during that time. Correct. Great,

00:46:15.712 --> 00:46:19.454
- is there public comment on this item?

00:46:24.706 --> 00:46:32.822
- Is there a motion I Move that we approve the contract for say road mitigation project with eco logic

00:46:32.822 --> 00:46:40.857
- Second I will call the roll Cox Decker. I roach. I grown I motion passes. Thank you. Thank you Next

00:46:40.857 --> 00:46:48.972
- is the contract with precision concrete for sidewalk cutting Yep, Adam Wason on behalf of our Street

00:46:48.972 --> 00:46:52.990
- Division at Public Works. This is a contract with

00:46:54.274 --> 00:47:03.232
- Sorry, with precision concrete for sidewalk cutting. This is a annual project and contract that we put

00:47:03.232 --> 00:47:12.104
- out for sidewalk trip hazard mitigation. And we will have precision start this work here this spring.

00:47:12.104 --> 00:47:21.758
- The amount not to exceed is 300,000 and we'll focus on roughly 4,500 plus trip hazards in this contract alone.

00:47:23.170 --> 00:47:24.766
- Thank you, questions from the board.

00:47:25.634 --> 00:47:32.549
- I just wanted to voice that this has been a really successful partnership. We've seen a lot of improved

00:47:32.549 --> 00:47:39.331
- sidewalks for greatly reduced costs compared to something like a replacement through this. I'm amazed

00:47:39.331 --> 00:47:46.047
- by the fact that they're going to have the opportunity to correct the 4,500 plus trip hazards that's

00:47:46.047 --> 00:47:52.762
- going to make a huge difference for walkability. Just appreciate the city's work to make this happen

00:47:52.762 --> 00:47:55.422
- so that we have the improved sidewalks.

00:47:55.586 --> 00:48:05.267
- Thank you. Any public comment on this item? All right, is there a motion? I move that we approve the

00:48:05.267 --> 00:48:15.140
- contract with precision concrete for sidewalk cutting. Second. I will call the roll. Cox Deckard? Aye.

00:48:15.140 --> 00:48:18.878
- Roach? Aye. Caron? Aye. Motion passes.

00:48:20.162 --> 00:48:28.057
- Next we have the right-of-way closure request for Duke Energy on Grant Street, Dunn Street, and Sixth

00:48:28.057 --> 00:48:35.875
- Street. Hello, Zach Bell, Engineering. Duke Energy is requesting lane and sidewalk closures on Grant

00:48:35.875 --> 00:48:43.770
- Street, Dunn Street, and Sixth Street from 511 26 to 706 26 for work on IU's circuit loop. There will

00:48:43.770 --> 00:48:48.414
- be 10 total work zones. They have supplied traffic control,

00:48:48.578 --> 00:48:58.486
- and communicated to adjacent businesses and all affected people. I also reached out to them about the

00:48:58.486 --> 00:49:08.588
- reasoning for the night work and encouraged them to apply for a noise permit. Thank you. Questions from

00:49:08.588 --> 00:49:18.398
- the board. There was some confusion yesterday about the accessibility of the supplemental documents.

00:49:18.914 --> 00:49:38.558
- I don't see them on the drive. Was that something that I should be seeing on the track? Miranda scrolling

00:49:50.370 --> 00:49:57.898
- No, this is a section and I can take this section out the relevant materials included in the packet

00:49:57.898 --> 00:50:05.802
- section is a was on the standardized template And that is if if they provided those items that we should

00:50:05.802 --> 00:50:13.781
- have those However with the maintenance of traffic plan. It is a portion of the MUT CD that they normally

00:50:13.781 --> 00:50:16.190
- provide to us as Duke Energy so

00:50:16.290 --> 00:50:22.022
- What happened here is we use a template document for the accessibility of these staff reports. We should

00:50:22.022 --> 00:50:27.536
- have just removed that last section for this one and not included it at all, but then it looked like

00:50:27.536 --> 00:50:33.050
- it should have been hyperlinked like the rest of them. Yes, so that was on us. So that's part of the

00:50:33.050 --> 00:50:38.564
- kinks we're working out with this new program here. We talked about that in our coordination meeting

00:50:38.564 --> 00:50:39.710
- today, actually, so.

00:50:40.834 --> 00:50:46.280
- And I'll just add, so we talked about this a little bit in the work session yesterday. This is a major

00:50:46.280 --> 00:50:51.621
- project for Duke to, for the transmission lines that go into Indiana University. Starts in the alley

00:50:51.621 --> 00:50:57.014
- there behind Village Deli and Osterio Raggo, moves out to Grant Street, goes up to Sixth Street, back

00:50:57.014 --> 00:51:02.407
- over towards campus and down behind the Von Lee. Major project, we've been coordinating with Duke for

00:51:02.407 --> 00:51:08.382
- some time on this. They know they need to work with all the adjacent property owners, maintain access, work with

00:51:08.514 --> 00:51:15.126
- you know, work through all that. So big project in coordination, also with all of our other downtown

00:51:15.126 --> 00:51:21.803
- projects that we've got going this summer. So lots of work to take place, but all in the name of good

00:51:21.803 --> 00:51:28.415
- progress and such. So thank you. Did Duke Energy give an indication that they did believe that there

00:51:28.415 --> 00:51:34.962
- would be some additional noise, whether that be from the trucks or any kind of boring activity? No,

00:51:34.962 --> 00:51:38.366
- no, I only encourage them to do that because of the

00:51:38.530 --> 00:51:45.563
- time period that they did. I have not heard back from them on the noise level specifically with this

00:51:45.563 --> 00:51:52.945
- application. All right, yeah. And I think we had discussed the possibility that the nature of the closure

00:51:52.945 --> 00:51:59.978
- may not indicate active work or noise being created. But if they do determine that, it would be good

00:51:59.978 --> 00:52:06.942
- to have us approve. Yeah, I expect to hear back from them soon. Any other questions from the board?

00:52:08.930 --> 00:52:16.443
- All right, public comment on this item? None on Zoom. Seeing none, is there a motion? I move that we

00:52:16.443 --> 00:52:24.253
- approve the right-of-way closure request for Duke Energy on Grant Street, Dunn Street, and Sixth Street.

00:52:24.253 --> 00:52:31.914
- Second. I will call the roll. Cox-Dekard? Aye. Roach? Aye. Caron? Aye. Motion passes. Thank you. Next,

00:52:31.914 --> 00:52:35.038
- we have the right-of-way closure request.

00:52:35.266 --> 00:52:47.069
- and noise permit for City of Bloomington Utilities on Gates Drive. Good evening, Kyle Wall from Engineering

00:52:47.069 --> 00:52:59.091
- again. City of Bloomington Utilities is requesting road closure and a noise permit for starting around 7 p.m.

00:52:59.091 --> 00:53:04.446
- on Thursday, April 9th until Friday, April 10th.

00:53:04.546 --> 00:53:13.535
- morning along North Gates Drive, so pretty adjacent to the IU credit union on that stretch of road there.

00:53:13.535 --> 00:53:22.524
- So it's just a single night closure, no sidewalks are planned to be impacted with a detour route planned.

00:53:22.524 --> 00:53:31.089
- So that's just south of the roundabout there near Circle Prosko and north of, I think it's Whitehall

00:53:31.089 --> 00:53:32.446
- crossing there.

00:53:34.850 --> 00:53:43.042
- Questions from the board. Is there public comment on this item? All right, is there a motion I move

00:53:43.042 --> 00:53:51.235
- that we approve the right-of-way closure request and noise permit for city of Bloomington utilities

00:53:51.235 --> 00:53:58.526
- on Gates Drive I Will call the roll Cox Deckard. I roach. Hi, Korone. I motion passes. I

00:54:00.898 --> 00:54:08.078
- Our final item of new business tonight is a right of way closure request for A&A Concrete at 1307 and

00:54:08.078 --> 00:54:15.398
- 1317 South Henderson Street. Zach Bell again, engineering. A&A Concrete is requesting sidewalk closures

00:54:15.398 --> 00:54:22.649
- totaling up to two weeks for sidewalk replacement at 1307 and 1317 South Henderson Street. I've spoken

00:54:22.649 --> 00:54:29.758
- with Angelo the applicant. His intended start date at this moment, which is tentative, is April 1st.

00:54:31.042 --> 00:54:37.907
- I'm also in discussions with him about finalizing the traffic control there. We're going to base it

00:54:37.907 --> 00:54:45.115
- off a typical application. He's also going to notify the local schools. The detour, the sidewalk detour,

00:54:45.115 --> 00:54:51.980
- will route pedestrians around the eastern sidewalk, via the western sidewalk, and cross at Hillside

00:54:51.980 --> 00:54:56.030
- and Henderson and Grimes and Henderson via the curb ramps.

00:55:01.506 --> 00:55:12.733
- Okay, thank you questions from the board As long as we're talking about packets and accessibility just

00:55:12.733 --> 00:55:24.288
- a quick question so in a case like this the staff report written in Verbal and if there are no additional

00:55:24.288 --> 00:55:30.174
- documents because nothing is accessible Currently yes

00:55:30.466 --> 00:55:37.357
- In our discussion this morning, we're going to provide more information on which portion of the MUTCD

00:55:37.357 --> 00:55:44.316
- that they will be using, making sure that we, in addition to duration, we get sort of a window of time

00:55:44.316 --> 00:55:51.478
- that they're going to be using. If it's an approval of something that you're approving a two-week closure

00:55:51.478 --> 00:55:58.234
- for, say, the month of April at some point, we're going to be including more of that information in

00:55:58.234 --> 00:55:59.518
- that staff report.

00:56:00.194 --> 00:56:07.006
- And that's where you'll see that come down. But yes, currently if we're using portions of the MUTCD,

00:56:07.006 --> 00:56:13.885
- if we include just one page, we have to make that page accessible. Otherwise we have to give you guys

00:56:13.885 --> 00:56:20.697
- the entire document in its entirety to not have changed the, to change the accessibility of that. So

00:56:20.697 --> 00:56:28.318
- you'll start to see more where it's just a staff report with an explanation of where that closure will be versus

00:56:28.514 --> 00:56:37.534
- a map of that closure at this time until we can. That's very helpful, thank you. Is there any public

00:56:37.534 --> 00:56:46.733
- comment on this item? None on Zoom. Is there a motion? I move that we approve the right of way closure

00:56:46.733 --> 00:56:53.342
- request for ANA Concrete at 1307 and 1317 South Henderson Street. Second.

00:56:54.114 --> 00:57:01.529
- I will call the roll. Cox Deckard? Aye. Roach? Aye. Caron? Aye. Motion passes. Thank you. Thank you.

00:57:01.529 --> 00:57:07.550
- Now we're on to staff reports and the 2026 fiscal year sidewalk improvement plan.

00:57:09.122 --> 00:57:15.188
- again, Public Works. We talked about this some yesterday in the work session, but just wanted to bring

00:57:15.188 --> 00:57:21.137
- this for the board for official acceptance. So each year we have a certain amount of limited dollars

00:57:21.137 --> 00:57:27.262
- amount of dollars and limited resources towards sidewalk improvement citywide. For several years, we've

00:57:27.262 --> 00:57:33.269
- come to you with our kind of annual sidewalk improvement plan to identify the locations and the types

00:57:33.269 --> 00:57:36.862
- of repairs we'd like we plan to make in a given year. As you

00:57:36.962 --> 00:57:46.534
- Approved tonight. We have the $300,000 contract for trip hazard removal. We also have plans for as part

00:57:46.534 --> 00:57:56.289
- of our paving season to do operate updated ADA compliant ramps 122 of those. Over the next several paving

00:57:56.289 --> 00:57:57.854
- seasons and then

00:57:58.178 --> 00:58:05.586
- We also have trip hazard repairs that we've listed by location in the document as well. Beyond that,

00:58:05.586 --> 00:58:13.141
- we have a sidewalk assistance program for residents that are in income eligible areas of the community

00:58:13.141 --> 00:58:16.222
- development block grant geographic zones.

00:58:16.770 --> 00:58:23.754
- And so that's $100,000 that we make available for matching program for residents that are in low income

00:58:23.754 --> 00:58:30.402
- areas wanting to make sidewalk repairs that are their responsibility will help offset their costs.

00:58:30.402 --> 00:58:31.678
- So overall, we are

00:58:32.066 --> 00:58:38.761
- presenting this to you tonight as our annual plan. It is possible that some of this would get moved

00:58:38.761 --> 00:58:45.455
- into a subsequent year or if resources don't allow for a certain project to be made, we'll add that

00:58:45.455 --> 00:58:52.217
- to a plan for next year and update the board with that. Otherwise, I'm happy to answer any questions

00:58:52.217 --> 00:58:56.702
- and appreciate your support of all of our efforts here. Thank you.

00:58:58.210 --> 00:59:05.729
- Next on the agenda is the approval of claims any questions that can you actually if you're so inclined

00:59:05.729 --> 00:59:13.394
- We'd ask that you make a motion to just accept the sidewalk improvement plan. Oh my apologies The Paving

00:59:13.394 --> 00:59:21.278
- list. Mm-hmm. It's a three-year period. Yes. Is that typical? It's like rolling three years. So next year's

00:59:21.378 --> 00:59:28.018
- sidewalk plan will be 27 28 29 yeah we're working on three years we'd love to work on a five-year plan

00:59:28.018 --> 00:59:34.465
- but depending on any given winter and what road decides that it's going to deteriorate more quickly

00:59:34.465 --> 00:59:41.041
- than planned that changes year to year but yes that's exactly what we're trying to do in the the road

00:59:41.041 --> 00:59:42.782
- sections listed that's the

00:59:42.978 --> 00:59:51.753
- the blocks that are being paved and the number of curb ramps that are associated with those. Yes. Okay.

00:59:51.753 --> 01:00:00.529
- So for the 2026 paving list on the two 11 look there's 11 specific locations for paving there that will

01:00:00.529 --> 01:00:08.966
- have updated ramps in the amount of 44 total. Thank you. And one thing we discussed during the work

01:00:08.966 --> 01:00:11.582
- session was that these are all

01:00:11.778 --> 01:00:19.294
- repair sites and not new. Yes, that new will be

01:00:19.394 --> 01:00:25.562
- taken care of by the City Council. Yes. So sidewalk connections and requests for new sidewalks go through

01:00:25.562 --> 01:00:31.497
- a completely separate process. That's not part of our annual maintenance and repair budget. I'll just

01:00:31.497 --> 01:00:37.315
- reiterate what we talked about a little bit yesterday was sidewalk repairs and maintenance falls to

01:00:37.315 --> 01:00:43.134
- the adjacent property owner per city code as the responsible party for those. The one area where we

01:00:43.134 --> 01:00:49.360
- do make our investments is that one of the areas where we make our investments specifically is if the city

01:00:49.360 --> 01:00:55.419
- So this tree between the roadway and the sidewalk and the tree plot, which is city owned, if that's

01:00:55.419 --> 01:01:01.478
- what's causing the damage, that's where you're going to see us doing the trip hazard repairs. Those

01:01:01.478 --> 01:01:07.718
- are all going to be mostly all related to street tree related heaving of sidewalks and such. So that's

01:01:07.718 --> 01:01:13.898
- where we really try to focus our efforts and then work with the private property owners on what their

01:01:13.898 --> 01:01:19.230
- responsibilities would be. One more question for me, sorry. The maps that are included.

01:01:19.426 --> 01:01:44.670
- What are they supposed to represent? These are Sorry, I wasn't focused on the maps James I was focused on the

01:01:53.154 --> 01:02:02.706
- these these might be these might have been included by mistake okay sorry I was only focused on the

01:02:02.706 --> 01:02:12.926
- staff report trying to just look at that associated it does not associate directly with the paving list so

01:02:24.994 --> 01:02:32.153
- I will get back to you on exactly what those are. Those were submitted by Danny. Danny's not in today,

01:02:32.153 --> 01:02:39.381
- sorry. I'll follow up with you on that. The main point and the information that's most relevant to this

01:02:39.381 --> 01:02:46.749
- is the locations and the information located in the actual staff report. Thank you. All right, any public

01:02:46.749 --> 01:02:51.614
- comment on this item? None on Zoom. All right, now is there a motion?

01:02:52.226 --> 01:02:58.659
- I move that we approve the 2026 a fiscal year sidewalk improvement plan Second, I will call the roll

01:02:58.659 --> 01:03:05.092
- Cox Decker. I wrote I Caron I Motion passes. Okay. I think I figured it out But definitely follow up

01:03:05.092 --> 01:03:11.780
- for sure to make sure I think those maps are the locations in which the sidewalk grinding is gonna occur

01:03:11.780 --> 01:03:18.341
- So they'll go into those neighborhoods and find the trip hazards that qualify for remediation in those

01:03:18.341 --> 01:03:19.806
- geographic areas those

01:03:19.938 --> 01:03:28.131
- Those are some of the targeted areas. Yes, but I will follow up and make sure that I'm correct in that

01:03:28.131 --> 01:03:36.245
- response. Excellent. Now we will move to claims. Does the board have any questions on claims tonight?

01:03:36.245 --> 01:03:43.006
- Is there any public comment on claims? None on Zoom. Seeing none, is there a motion?

01:03:43.586 --> 01:03:50.273
- Move that we approve the claims for tonight's meeting in the amount of four million eight hundred eighty

01:03:50.273 --> 01:03:57.088
- nine thousand three hundred fourteen dollars and seventy one cents second I Will call the roll Cox Decker.

01:03:57.088 --> 01:04:04.094
- I Roach I Caron I motion passes and seeing there's nothing else on the agenda. I will call for adjournment. I
