00:00:00.162 --> 00:00:07.450
- I call to order the Board of Public Works meeting tonight for Tuesday, October 6th. We are in council

00:00:07.450 --> 00:00:14.667
- chambers at City Hall at 401 North Morton Street. If you are on the Zoom link at the time for public

00:00:14.667 --> 00:00:21.884
- comment, you are welcome to either use the raise hand function or the chat. We will start tonight on

00:00:21.884 --> 00:00:26.814
- our agenda with opening of bids, which occurred at the work session.

00:00:26.914 --> 00:00:33.957
- Yesterday so we will move along to messages from board members any messages from the board. I Do have

00:00:33.957 --> 00:00:41.000
- one message in the interest of the meeting length and the fact that many of these items are ones that

00:00:41.000 --> 00:00:47.973
- we have heard in the past I'd like to make a motion that the board adopt a rule limiting oral public

00:00:47.973 --> 00:00:54.878
- comment on each agenda item to five minutes per speaker All right with the motion is there a second

00:00:56.290 --> 00:01:04.101
- I second that motion. All right, I will call the roll. Roach? Aye. Cox-Deckard? Aye. Caron, aye. Motion

00:01:04.101 --> 00:01:11.763
- passes. So public comment tonight will be limited to five minutes per individual. All right, first we

00:01:11.763 --> 00:01:19.424
- have an appeal for Wells and Wells of the engineering notice of violation issued November 24th, 2025,

00:01:19.424 --> 00:01:20.926
- the second hearing.

00:01:27.394 --> 00:01:37.141
- The appeals process will now be that the appellant will go first and then the city of Bloomington will

00:01:37.141 --> 00:01:46.603
- make their statements. So if someone is here to speak on behalf of Wells and Wells, you may step up

00:01:46.603 --> 00:01:56.350
- to the podium and state your name. Thank you, Miranda. Jesse Graber with Wells and Wells Construction.

00:01:57.410 --> 00:02:08.147
- Sorry, I just want to make sure that the captioning is picking up everything is. There we go, thank

00:02:08.147 --> 00:02:18.132
- you perfect. Absolutely again recording in progress. Here with the same petition and request

00:02:18.132 --> 00:02:24.574
- and understanding as the last time we all met. I think the.

00:02:24.962 --> 00:02:35.390
- You know, there's no reason to rehash what happened at the time. There is a substantial punitive fine

00:02:35.390 --> 00:02:45.817
- for opening the streets a couple days after our permit had expired. We discussed in quite detail last

00:02:45.817 --> 00:02:50.622
- time the reasons why our owners have requested

00:02:50.722 --> 00:03:03.048
- Which was at least an initially favorably received by transportation that we. donate or pay in kind

00:03:03.048 --> 00:03:07.486
- to the amount of the proposed fine.

00:03:07.650 --> 00:03:15.097
- to a capital improvement project on Washington Street that's much needed given the amount of current

00:03:15.097 --> 00:03:22.838
- student traffic and the proposed student traffic with a 600 car parking garage at the end of Washington.

00:03:22.838 --> 00:03:30.137
- The east side of Washington was fully redeveloped under the construction plans with new sidewalks,

00:03:30.137 --> 00:03:36.478
- new curb, new ADA ramps. The west side of Washington is in its original current state

00:03:36.930 --> 00:03:44.018
- There are no curbs. There are no sidewalks for the students. There is considerable amount of erosion

00:03:44.018 --> 00:03:51.317
- and runoff every time it rains down Washington Street and ruts out the property. We do acknowledge that

00:03:51.317 --> 00:03:58.686
- there is some construction damage that has been done to the west side of Washington that will need to be

00:03:58.786 --> 00:04:05.529
- addressed but in no way shape or form to the degree that would be required to support the amount of

00:04:05.529 --> 00:04:12.406
- students and traffic that is that Washington Street is going to receive. We had met transportation on

00:04:12.406 --> 00:04:15.710
- site a few months ago thought we at least had a.

00:04:15.906 --> 00:04:22.965
- plan to move ahead with a proposed capital improvement project, but was asked to come back here for

00:04:22.965 --> 00:04:30.095
- a second hearing. So no nothing new, same position as before. So happy to help the community and the

00:04:30.095 --> 00:04:37.436
- city with a project there that helps everyone. And I think one of the property owners from Washington's

00:04:37.436 --> 00:04:44.566
- here who had reached out to me, I just mentioned to her that there was a hearing tonight as well. So

00:04:44.566 --> 00:04:45.342
- thank you.

00:05:07.202 --> 00:05:16.307
- Hi, good evening, Alex Pratt with City Legal. I will just recap for the board real quick what this appeal

00:05:16.307 --> 00:05:25.326
- is about. So the appellant, Wells and Wells Construction, was issued a notice of violation that occurred

00:05:25.326 --> 00:05:34.174
- on September 20th, 2025. And basically the appellant was granted approval via permit for road closures

00:05:34.306 --> 00:05:42.724
- both North Lincoln Street from July 2nd to July 23rd, 2025, and again at North Washington Street from

00:05:42.724 --> 00:05:51.060
- July 23rd to August 13th of 2025. Appellant requested extension for the closure dates for these both

00:05:51.060 --> 00:05:57.662
- locations and was given a deadline until September 19th of 2025 for completion.

00:05:57.890 --> 00:06:06.585
- The parent was not able to complete the project in a satisfactory condition and was assessed a fine

00:06:06.585 --> 00:06:15.367
- of 27,000 in accordance with Bloomington Municipal Code. And we asked the board to uphold the notice

00:06:15.367 --> 00:06:23.454
- of violation and deny the appeal. And we would also request that the board just refrain from

00:06:23.810 --> 00:06:38.896
- adjudicating how the funds will be spent because under the code, their authority is to render a decision

00:06:38.896 --> 00:06:53.694
- and uphold or reduce or eliminate the fine. Yes, thanks. Just a general clarification, and I think you

00:06:54.018 --> 00:07:02.916
- I'm sorry, I forget your name. I think you said it right there at the end. Tonight's request and the

00:07:02.916 --> 00:07:11.814
- charge of the board is to determine whether a fine or excuse me, excuse me, a violation happened and

00:07:11.814 --> 00:07:18.686
- whether the city should uphold the fining structure that exists in city code.

00:07:20.130 --> 00:07:28.506
- not to make any kind of determination about any negotiation that may or may not have happened or negotiations

00:07:28.506 --> 00:07:36.348
- that fell apart or how those fine dollars should be spent. Is that correct? Yes, that is correct. Just

00:07:36.348 --> 00:07:43.963
- a little clarification that you are able to reduce the fine if you see extenuating circumstances in

00:07:43.963 --> 00:07:45.790
- this appeal. Thank you.

00:08:02.114 --> 00:08:16.470
- Hello, my name is Mitzi Lewis, I live at 110 East 19th Street I am here regarding the poor and unsafe

00:08:16.470 --> 00:08:28.574
- condition of North Washington Street between 19th South to the new parking garage and

00:08:29.154 --> 00:08:37.540
- I own two student rental properties on North Washington directly across from Hub 2. And we've rented

00:08:37.540 --> 00:08:45.927
- those properties 135 years, 120 years, at least. And I would just want to say the relocating and new

00:08:45.927 --> 00:08:54.562
- level of North Washington Street has left the west side of the street with wide gaps of dirt, unsightly

00:08:54.562 --> 00:08:56.638
- and unfinished sections.

00:08:56.930 --> 00:09:05.787
- My own asphalt parking area in front of 1321 destroyed The asphalt was replaced with compacted fill

00:09:05.787 --> 00:09:14.822
- which is treacherous as my tenants Step out from their cars onto these loose stone pebbles on a slope

00:09:14.822 --> 00:09:21.022
- now there's a slope because Washington's lower than it was before and

00:09:21.474 --> 00:09:29.417
- But maybe worst of all is there is now a significant drop off from the edge of the pavement along the

00:09:29.417 --> 00:09:37.361
- west edge of the street. Because the street was also moved to the east a bit. So I call this drop off

00:09:37.361 --> 00:09:45.382
- a gully because after every hard rain or two, the rock which gets repeatedly replaced to fill this gap

00:09:45.382 --> 00:09:50.366
- washes out and we're quickly back to this significant drop off.

00:09:51.234 --> 00:09:58.746
- I believe this gullies a liability for the city and will become a bigger problem when the traffic and

00:09:58.746 --> 00:10:06.479
- significantly increases once Hub two is completed in the parking garages in full use I Did send pictures

00:10:06.479 --> 00:10:13.917
- today of North Washington Street to your public works email I don't know if you had a chance to look

00:10:13.917 --> 00:10:20.030
- at those and I just would encourage this may not be your you know a wheelhouse but

00:10:20.258 --> 00:10:27.989
- Or your decision, but I just encourage you maybe to visit the area and take a look in person what I'm

00:10:27.989 --> 00:10:35.948
- trying to describe and with the pictures. This section of North Washington Street badly needs curb slash

00:10:35.948 --> 00:10:44.286
- gutter. Install to eliminate the goalie and the side and they need sidewalk replacement and much more I just.

00:10:44.706 --> 00:10:52.687
- guess I'd like to know maybe you're not again not the party to ask but does the city have a plan and

00:10:52.687 --> 00:11:00.747
- money to do these much needed upgrades and so I just like to say I vote in favor of the appeal not to

00:11:00.747 --> 00:11:08.728
- find them but rather let them use their resources toward this capital improvement project that needs

00:11:08.728 --> 00:11:14.654
- to be done. Seems like that would be a better use of resources. Thank you.

00:11:19.298 --> 00:11:31.509
- Any final questions from the board Excuse me, I guess this is for city staff probably Andrew Are there

00:11:31.509 --> 00:11:43.364
- any short or long-term plans for any public improvements in this general area? Good evening, Andrew

00:11:43.364 --> 00:11:45.854
- seabor city engineer

00:11:46.242 --> 00:11:54.615
- The city of Bloomington does not have a city-funded capital project programmed on North Washington at

00:11:54.615 --> 00:12:03.069
- this time. We are aware that the condition of some of the work in the area still needs to be remedied,

00:12:03.069 --> 00:12:11.442
- and that's been coordinated and in process with the developer, but there are no city capital projects

00:12:11.442 --> 00:12:15.710
- currently planned. What I'm hearing you say is that

00:12:15.938 --> 00:12:23.385
- problems created as a direct result of construction will be remedied. That's what I would expect, not

00:12:23.385 --> 00:12:30.759
- knowing the details, but any damages caused should be brought back to equal or better condition. But

00:12:30.759 --> 00:12:35.358
- not necessarily other capital plans. Correct. Okay, thank you.

00:12:47.234 --> 00:12:54.439
- engineering program manager. Just to state that those conditions are very common around any work area

00:12:54.439 --> 00:13:01.502
- and the expectation if there's no planned improvements for that section would be for restoration to

00:13:01.502 --> 00:13:08.919
- at least the standard that they were currently existing in prior to the start of the project. And before

00:13:08.919 --> 00:13:13.086
- the start of the project was that area of North Washington

00:13:15.682 --> 00:13:26.212
- on any kind of future list for improvements? Not that I'm aware of. Okay, thank you. All right, is there

00:13:26.212 --> 00:13:36.240
- any other public comment, Miranda? None on Zoom. Okay, thank you. Is there a motion? I move that we

00:13:36.240 --> 00:13:45.566
- uphold the engineering notice of violation issued to Wells and Wells on November 24th, 2025.

00:13:47.106 --> 00:13:58.400
- Second. With a motion and a second, I will call the roll. Roach? Aye. Cox-Dekard? Aye. Caron, aye. Motion

00:13:58.400 --> 00:14:10.334
- passes. Next, we have the CGR appeal of engineering notice of violation, issue June 10th, 2026, second hearing.

00:14:15.874 --> 00:14:24.361
- There's a representative from CGR to speak on behalf of this appeal. You may step up to the microphone.

00:14:24.361 --> 00:14:32.521
- If you would state your name, please, and then you'll have five minutes. Thank you. Yes. My name is

00:14:32.521 --> 00:14:39.294
- Carvin Thomas. I am the managing partner of CGR services LLC Bloomington, Indiana.

00:14:43.362 --> 00:14:51.229
- And when I left here the last time, I wasn't for sure what the reason was for the table. Adam suggested

00:14:51.229 --> 00:14:58.869
- we table this motion into this meeting. I'm not sure what he was seeking to find. But I will just go

00:14:58.869 --> 00:15:07.038
- back and reiterate what I said before, that this project that we started begun under RAD 2. It was a RAD 2.

00:15:07.490 --> 00:15:15.618
- project up at Crestmont. Actually, Rad 1, we were involved in down at Stonewood on the south side of

00:15:15.618 --> 00:15:24.148
- Bloomington. Not, I'm sorry, Walnut Woods south side of Bloomington. And continued up at Reverend Butler,

00:15:24.148 --> 00:15:32.839
- Rad 1. Rad 2 began on Crestmont, and that's where we started this project. After Rad 2, we were contracted,

00:15:32.839 --> 00:15:36.702
- we were contracted to do some sidewalk repairs.

00:15:36.994 --> 00:15:44.990
- in addition to the continuation of the RAD2 project. During the... when we signed the initial contract

00:15:44.990 --> 00:15:53.528
- for the concrete sidewalk repair, there was nowhere in the contract that had stated we needed a right-of-way.

00:15:53.528 --> 00:16:01.369
- We just can... we, CGR, just assumed we were continuing to work under the RAD2 project, which didn't

00:16:01.369 --> 00:16:04.862
- require right-of-ways to finish the project.

00:16:05.090 --> 00:16:11.653
- So we were approached after we were shut down. Rhonda from the city of Bloomington shut us down for

00:16:11.653 --> 00:16:18.478
- like a month and a half. We weren't allowed to continue our repairs, so we come back shortly in January

00:16:18.478 --> 00:16:25.040
- and continued our repair when we were approached by the city to have right-of-way permits, which we

00:16:25.040 --> 00:16:30.750
- thought was unfair to CGR, because we would have put that in the cost of the contract.

00:16:30.946 --> 00:16:38.455
- for right-of-way permits. So we were under the assumption we would continue to operate under the RAT2

00:16:38.455 --> 00:16:46.332
- agreement, which was what we were doing was to fence off all of our repairs, and mind you, like I repeated

00:16:46.332 --> 00:16:54.061
- last time, like I said the last time, we were talking probably 10 feet, sometimes five feet of concrete,

00:16:54.061 --> 00:16:58.110
- sometimes 10 feet of concrete, and there were probably

00:16:58.914 --> 00:17:07.584
- you know, 10 to 15 spots all over Crestmont that we had repaired. And like I said last time, we had

00:17:07.584 --> 00:17:16.341
- came together under the Rad2 agreement and agreed that the best way to partition off these sidewalks

00:17:16.341 --> 00:17:25.272
- for safety was to put up the orange fencing, which is what we continued to do under this project. Then

00:17:25.272 --> 00:17:27.006
- we were approached,

00:17:27.106 --> 00:17:34.765
- about the right-of-way, which for our position, again, had we known from the beginning, we would have

00:17:34.765 --> 00:17:42.499
- factored in those costs. So for that to happen to us midstream, we kind of felt like that was a little

00:17:42.499 --> 00:17:49.182
- unfair to us. But as Secretary Roach had discussed last time, it was all about the city,

00:17:49.282 --> 00:17:56.486
- and putting up the signs for street closures, which, at that time, I thought was not as effective as

00:17:56.486 --> 00:18:03.262
- the orange fencing. I get what you said about the safety, and I just wanted to reiterate that.

00:18:04.450 --> 00:18:11.496
- We know up at Crestmont, there's tons of kids, there's tons of folks. It was around starting back to

00:18:11.496 --> 00:18:18.543
- school, and we knew there would be a lot of folks getting on buses, so we put up the orange fencing,

00:18:18.543 --> 00:18:25.659
- which we thought was the best way to proceed with that. And just a further one last point I'd like to

00:18:25.659 --> 00:18:32.775
- make, that when we received our final payment for this project, it came out of the RAD2 funds for our

00:18:32.775 --> 00:18:33.822
- final payment.

00:18:34.306 --> 00:18:42.312
- So just to try to boast our point that we thought we were continuing this project under the Rad2 agreement,

00:18:42.312 --> 00:18:49.948
- which called for no right-of-way offsets or permits. Again, I'm not sure why Adam tabled that. I never

00:18:49.948 --> 00:18:57.583
- did get an excuse on why this was tabled. I don't know what he was looking at. If there was additional

00:18:57.583 --> 00:19:01.438
- information, I'm not sure what that was. All right.

00:19:03.458 --> 00:19:17.541
- You have someone from the city, please. Alex Pratt with CityLego again. So a brief recap of this appeal,

00:19:17.541 --> 00:19:30.686
- the appellant's CGR services, LLC, was issued a notice of violation that occurred from April 7th.

00:19:31.042 --> 00:19:42.579
- 2026 to April 24th of 2026 Appellant applied for right-of-way permits with the city and After that staff

00:19:42.579 --> 00:19:54.336
- repeatedly requested additional information in order to issue the permit The appellant failed continuously

00:19:54.336 --> 00:19:59.390
- failed to provide that information and was on

00:19:59.650 --> 00:20:08.392
- April 24, 2026 there was issued a fine of $3,000 for working in the right of way without a permit. The

00:20:08.392 --> 00:20:16.964
- parent was eventually issued a retroactive permit. And so we asked the board to uphold the notice of

00:20:16.964 --> 00:20:23.838
- violation and the fine and deny the appeal. Thank you. Questions from the board?

00:20:29.250 --> 00:20:38.164
- Alex, don't go away too fast. Just to, like I did last time, I just want to reiterate my understanding

00:20:38.164 --> 00:20:46.906
- of our charge tonight. Our charge is to determine whether a violation took place, and whether that's

00:20:46.906 --> 00:20:55.906
- the fine assessed by the city is in line with city code, but we do have the ability to adjust that fine

00:20:55.906 --> 00:20:57.118
- as necessary.

00:20:57.218 --> 00:21:14.204
- Charge is to not adjudicate contract disputes That is correct. Okay. Thank you All right seeing no other

00:21:14.204 --> 00:21:23.102
- board questions is there public comment on this item I

00:21:27.074 --> 00:21:37.278
- None on Zoom. Thank you. Is there a motion? I move that we uphold the engineering notice of violation

00:21:37.278 --> 00:21:47.681
- to CGR issue June 10th of 2026. Second. I will call the roll. Roach? Aye. Cox-Deckard? Aye. Crohn? Aye.

00:21:47.681 --> 00:21:49.182
- Motion passes.

00:21:53.122 --> 00:22:01.014
- Next on tonight's agenda is petitions and remonstrances. This is a time for public to comment on any

00:22:01.014 --> 00:22:09.298
- item that is not on tonight's agenda. Again, if you are on Zoom, feel free to use the raise hand function

00:22:09.298 --> 00:22:17.503
- or chat. None on Zoom. All right, so we will move along to the consent agenda. Tonight is a noise permit

00:22:17.503 --> 00:22:21.566
- request for 50 year celebration at Rinseable Spoon.

00:22:21.954 --> 00:22:29.010
- Contract renewal with Ivy Tech for CDL training. Engineering service agreement with Rundle Ernstberger

00:22:29.010 --> 00:22:36.134
- Associates Inc. Preliminary engineering contract amendment two with Crossroad Engineers PC for Hopewell

00:22:36.134 --> 00:22:42.985
- South and payroll. Are there any items that need to be removed from the consent agenda tonight? Any

00:22:42.985 --> 00:22:49.150
- board questions on the consent agenda? Is there any public comment on the consent agenda?

00:22:51.266 --> 00:22:59.881
- None on zoom. All right. Is there a motion? I Move that we approve the consent agenda for October 6th

00:22:59.881 --> 00:23:08.580
- of 2026 second I will call the roll Roach. I Cox Decker. I Caron I motion passes Next we'll move along

00:23:08.580 --> 00:23:16.350
- to new business. We have a right-of-way closure request from Duke energy on Grimes Lane and

00:23:20.930 --> 00:23:29.022
- Good evening, Kyle Ball from Engineering again. Duke Energy had submitted this request for a right-of-way

00:23:29.022 --> 00:23:37.343
- closure along Grimes Lane just west of the South Walnut intersection to relocate some power that's currently

00:23:37.343 --> 00:23:45.054
- running to that signal ahead of some intersection improvements that are becoming, I believe in 2027.

00:23:45.634 --> 00:23:53.779
- The proposed closure includes or closures rather include the southern sidewalk and the southern eastbound

00:23:53.779 --> 00:24:02.001
- traffic lane. So this would actually be in between the B line trail overhead crossing and the intersection

00:24:02.001 --> 00:24:09.993
- itself roughly. Flaggers would be utilized for the lane closure and there would be a hard closure point

00:24:09.993 --> 00:24:13.758
- for the pedestrian traffic that would have folks

00:24:13.890 --> 00:24:20.133
- move around that closure to the north side along South Walnut Street and then we would actually get

00:24:20.133 --> 00:24:26.563
- to utilize our new mid-block crossing on that section of street just about 50 feet to the west of this

00:24:26.563 --> 00:24:33.055
- work area. So they're planning to perform this work between November 2nd and December 18th of this year

00:24:33.055 --> 00:24:36.926
- and plan for three to five days for the work to be completed.

00:24:46.146 --> 00:24:55.300
- Seeing none, is there any public comment on this item? None on Zoom. All right, is there a motion? I

00:24:55.300 --> 00:25:04.544
- move that we approve the right-of-way closure request from Duke Energy on Grimes Lane. Second. I will

00:25:04.544 --> 00:25:11.070
- call the roll. Roach? Aye. Cox-Deckard? Aye. Caron? Aye. Motion passes.

00:25:12.578 --> 00:25:19.635
- Next is a right of way closure request for August Mac environmental on North Morton between West 6th

00:25:19.635 --> 00:25:27.041
- Street and West Kirkwood and West 6th Street between North Morton and North College Avenue. Hello Rebecca

00:25:27.041 --> 00:25:34.237
- Davis from engineering department August Mac environmental is requesting approval of a temporary right

00:25:34.237 --> 00:25:35.774
- of way closure at the

00:25:36.098 --> 00:25:43.227
- on the 200 block of West 6th Street to accommodate removing environmental monitoring wells as well as

00:25:43.227 --> 00:25:50.426
- the repair of the sidewalks. The request includes temporary closures of the south sidewalk of West 6th

00:25:50.426 --> 00:25:57.695
- Street as well as the west sidewalk of North Morton Avenue in the same block. The closures are proposed

00:25:57.695 --> 00:26:02.238
- for periods of approximately 48 hours including overnight hours.

00:26:02.370 --> 00:26:09.909
- to allow for demolition and repair. Pedestrian traffic will be detoured in accordance with the approved

00:26:09.909 --> 00:26:17.447
- maintenance of traffic plan. The date of the closures is as of yet to be determined, but is anticipated

00:26:17.447 --> 00:26:24.696
- to be late October or early November. Again, the sidewalk closure of the south sidewalk of West 6th

00:26:24.696 --> 00:26:25.566
- Street will

00:26:25.698 --> 00:26:32.715
- be detoured to the north sidewalk of West 6th Street and the sidewalk closure of the east sidewalk of

00:26:32.715 --> 00:26:39.594
- North Morton will be detoured to the west sidewalk which is the beeline trail. The petitioner shall

00:26:39.594 --> 00:26:46.474
- install and maintain all required signage, barricades, and traffic control devices, maintain access

00:26:46.474 --> 00:26:54.110
- to adjacent properties, and limit the closure to the minimum area and duration necessary to complete the work.

00:26:56.546 --> 00:27:09.138
- Seeing none is their public comment on this item None on zoom, okay, I will call the roll Roach.

00:27:09.138 --> 00:27:14.590
- Oh I'm sorry. Is there a motion first? Oh

00:27:15.106 --> 00:27:20.827
- Yeah, I'll make a motion. I move that we approve the right-of-way closure request for August

00:27:20.827 --> 00:27:27.287
- MAC environmental on North Morton between 6th Street and West Kirkwood and West 6th Street between North

00:27:27.287 --> 00:27:33.993
- Morton and North College Avenue. Second. Now, with a motion and a second, I will call the roll. I apologize.

00:27:33.993 --> 00:27:37.438
- Roach? Aye. Cox-Dekard? Aye. Caron, aye. Motion passes.

00:27:39.394 --> 00:27:46.059
- On staff reports, we have a settlement agreement for Beacon Builders, Kinzer Ridge Engineering Notice

00:27:46.059 --> 00:27:52.921
- of Violation. I know there was a brief report at the work session yesterday, but is there anything you'd

00:27:52.921 --> 00:27:59.194
- like to include today? If I can pull it up, yes. So just noting, sorry, Kyle Ball, Engineering,

00:27:59.194 --> 00:28:05.859
- once again, just noting that this settlement is a little over a year in the making, so we're happy to

00:28:05.859 --> 00:28:07.166
- get this done with.

00:28:07.330 --> 00:28:14.860
- We have agreed in principle between both legal teams to settle on an amount of $21,250 to settle the

00:28:14.860 --> 00:28:22.389
- two NOVs surrounding the Kinzer Ridge development on Prow, Acuff area north of the Bloomington North

00:28:22.389 --> 00:28:30.068
- High School. And we're in the middle of executing that agreement at this point in time. So I just want

00:28:30.068 --> 00:28:37.150
- to make note of it. Great, thank you. Thank you. Next on the agenda is the approval of claims.

00:28:37.570 --> 00:28:48.506
- in the amount of $1,220,488.95. Does the board have any questions tonight on claims? Is there any public

00:28:48.506 --> 00:28:59.234
- comment on claims? None on Zoom. Is there a motion? I move that we approve the claims for this evening

00:28:59.234 --> 00:29:06.942
- in the amount of $1,220,488.95. Second. I will call the roll. Roach? Aye.

00:29:07.106 --> 00:29:14.782
- Cox Deckard? Aye. Caron? Aye. Motion passes. And with nothing else on the agenda, I will call for adjournment.