- Welcome to the City of Bloomington Redevelopment Commission meeting for Monday, November 2nd, 2026.

00:00:06.335 --> 00:00:12.760
- We will start the meeting with a roll call. I just wanted to check, is Lori online? Okay, that's fine.

00:00:12.760 --> 00:00:19.247
- Just wanted to know what we got. Okay, roll call, please. C. Scamblari? Here. Brandi Cassidy here. John

00:00:19.247 --> 00:00:25.484
- West here. Deborah Meyerson here. And staff present, please. Hannah Tilly-Hudson. Christina Finley,

00:00:25.484 --> 00:00:28.478
- Hand Department. Amy Calzwell, Hand Department.

00:00:28.962 --> 00:00:37.344
- Jeff McKim, City Control. Jane Cooper-Smith, Economic and Sustainable Development. Michael Bitsky, City

00:00:37.344 --> 00:00:45.806
- Engineering. Hannah Dragovich, ESD. Okay. Dana Kerr, Legal. Thank you. And we will start with Director's

00:00:45.806 --> 00:00:54.026
- Reports, please. Do we have a report from hand? No Director's Report from me. However, we do have Mr.

00:00:54.026 --> 00:00:58.942
- John Zote here to give his annual report from CDFI Friendly.

00:00:59.490 --> 00:01:12.720
- Welcome. Thank you. Now you got a busy agenda tonight, so I'll be. As fast as I can here. I hope that

00:01:12.720 --> 00:01:26.079
- I can. So right as I see my email there. So I have. As Anna mentioned, I'm John Zoe from CDFI Friendly

00:01:26.079 --> 00:01:28.414
- Bloomington. And.

00:01:28.866 --> 00:01:36.355
- wanted to give our annual report to the RDC as we do every year. I'll go through quickly some of what

00:01:36.355 --> 00:01:44.137
- a CDFI is just for those watching at home and anybody that may be new to learning about our organization.

00:01:44.137 --> 00:01:52.286
- But we are a community development nonprofit organization that is a CDFI is the acronym for that and CDFIs are

00:01:52.450 --> 00:01:59.720
- mission-based lenders on a mission for responsible, affordable lending for community development projects.

00:01:59.720 --> 00:02:07.058
- So we help people in populations and communities that are generally economically distressed, disadvantaged,

00:02:07.058 --> 00:02:13.852
- underbanked, meaning they're not able to obtain traditional financing from banks. And we exist as a

00:02:13.852 --> 00:02:21.598
- $500 billion sector of, $500 billion sector of lending across the United States that sort of sit alongside banks.

00:02:21.794 --> 00:02:28.632
- for when they are unable to help folks. So we cover a... My slides aren't advanced, so you're everyone,

00:02:28.632 --> 00:02:35.668
- I'm sorry. There we go. So we cover a 13-county region here in the Indiana Uplands. Eleven of our counties

00:02:35.668 --> 00:02:42.374
- are the Uplands counties, if you know of regional opportunity initiatives that covers the Uplands for

00:02:42.374 --> 00:02:49.278
- regional economic development. We are a partner of theirs, and we also have Morgan and Jackson counties.

00:02:49.890 --> 00:02:55.772
- We help provide access to loans for folks that may not be able to get them in banks, like I mentioned,

00:02:55.772 --> 00:03:01.825
- and also provide free technical assistance to projects and those folks who might be looking for financing

00:03:01.825 --> 00:03:07.763
- for their small business. And I want to take a minute to recognize Emma Yoder, our program coordinator,

00:03:07.763 --> 00:03:12.446
- who has taken on a lot of small business activity this year for the organization.

00:03:19.138 --> 00:03:25.397
- So what is a CDFI friendly Bloomington? So that's that's told you a little bit about what a CDFI is.

00:03:25.397 --> 00:03:31.719
- But our job as a CDFI friendly, the friendly comes in because we are designed to be a connector. Most

00:03:31.719 --> 00:03:37.916
- CDFIs are direct lenders. They're called loan funds. So we are one of 1300 CDFIs that are certified

00:03:37.916 --> 00:03:44.114
- by the US Treasury, which spoke about that a little bit last year. But that's a vetting process you

00:03:44.114 --> 00:03:48.638
- go through to make sure that you are sort of doing the right things as a

00:03:49.058 --> 00:03:55.500
- loan fund financial institution. We are not regulated like banks are because we don't hold people's

00:03:55.500 --> 00:04:02.071
- money. We're not depository institutions, but we do go through the process of being certified to gain

00:04:02.071 --> 00:04:08.062
- access to US Treasury programs. If you've heard of programs like the New Markets Tax Credit,

00:04:08.642 --> 00:04:15.425
- the technical assistance grant program, financial assistance, which is loan capital that can be delivered

00:04:15.425 --> 00:04:22.464
- to communities through the U.S. Treasury's CDFI fund. And those are generally only available at organizations

00:04:22.464 --> 00:04:28.863
- if you have that certification. So in addition to providing that technical assistance and access to

00:04:28.863 --> 00:04:35.262
- loans for those that might need them, we also were awarded a second $500,000 EPA brownfields grant.

00:04:35.262 --> 00:04:36.926
- So when you're looking at

00:04:37.058 --> 00:04:43.348
- community development across the board, thinking about a housing project, thinking about someone wanting

00:04:43.348 --> 00:04:49.339
- to acquire a piece of property, a small business or a facility for childcare, we cannot come in and

00:04:49.339 --> 00:04:55.329
- pay for those initial environmental assessments, something this body knows well, phase one, a phase

00:04:55.329 --> 00:05:01.500
- two assessment to understand what's under the surface so that you're getting a better idea of what you

00:05:01.500 --> 00:05:05.214
- might be acquiring, especially when there's housing or where,

00:05:05.538 --> 00:05:11.962
- kids might be present. So we were glad to get a $500,000 grant three years ago that is spent down, and

00:05:11.962 --> 00:05:18.323
- we were just awarded another one. So we have a fresh $500,000 we are able to spread across the region

00:05:18.323 --> 00:05:24.622
- to get assessments done. So as far as what the eligibility and uses for CDFI loans are, we're really

00:05:24.622 --> 00:05:30.984
- talking, our organization focuses in three main areas, small business, housing, and nonprofits, which

00:05:30.984 --> 00:05:33.790
- kind of includes childcare most of the time.

00:05:33.890 --> 00:05:39.068
- Small business and business lending is something banks do quite a bit of, and we work with banks, they

00:05:39.068 --> 00:05:44.145
- work with us, but they can't help everybody, especially if it's a startup, because there's a lack of

00:05:44.145 --> 00:05:49.323
- sort of financial history, tax returns. So with startups, they may be looking for financing, a smaller

00:05:49.323 --> 00:05:54.400
- amount of financing, and that's where the CDFI community can come in. As long as they're registered,

00:05:54.400 --> 00:05:59.478
- a business entity with a state, they've been in business. Sometimes for one day, they can get access

00:05:59.478 --> 00:06:01.790
- to certain levels of CDFI financing, housing,

00:06:02.050 --> 00:06:08.432
- We are part of the capital stack for a project. So the sort of pool of financing that it takes to get

00:06:08.432 --> 00:06:14.690
- a project across the finish line, that may be a grant. We've worked with the city a number of times

00:06:14.690 --> 00:06:20.947
- on housing projects for affordable housing, so that income-restricted housing. We have come in with

00:06:20.947 --> 00:06:27.204
- a loan with a partnering CDFI, and the city has come in with a grant. So we can help with that cash

00:06:27.204 --> 00:06:30.270
- flow and the debt service coverage on a project.

00:06:30.466 --> 00:06:37.766
- And we can also bring in other CDFI partners to come and help with pre-development expenses or acquisition

00:06:37.766 --> 00:06:45.271
- of property and things like that. With nonprofits, there are specific CDFIs out there that help organizations

00:06:45.271 --> 00:06:48.478
- with their structure and their basic operating

00:06:48.834 --> 00:06:54.610
- that status, I guess, if you will. They can come in and do facility assessments. If it's a nonprofit

00:06:54.610 --> 00:07:00.672
- child care, they can help assess whether a child care might, what a child care might need for a building.

00:07:00.672 --> 00:07:06.391
- And so they're gonna come in and help and offer bridge lending. A lot of times if there's a capital

00:07:06.391 --> 00:07:12.567
- campaign going on, a CDFI partner can come in and do a bridge loan as the nonprofit is working to fundraise

00:07:12.567 --> 00:07:15.198
- for their project. So a lot of different ways

00:07:15.362 --> 00:07:20.914
- CDFI lending, mission-based lending here in the region can help make a difference. So in terms of what

00:07:20.914 --> 00:07:26.465
- our technical assistance looks like, that is, again, free. I want to make sure people know that that's

00:07:26.465 --> 00:07:31.532
- free. But we will work one-on-one with project leads, whatever it is, a small business owner,

00:07:31.532 --> 00:07:37.030
- an entrepreneur, a housing project, a child care. They'll come in the door and we will help them walk

00:07:37.030 --> 00:07:42.581
- through their project and think about what steps they might want to take next. And many times that may

00:07:42.581 --> 00:07:44.414
- be connecting them with a lender.

00:07:44.706 --> 00:07:49.552
- a CDFI partner, but the first question we'll ask them, do you have a relationship with a bank?

00:07:49.552 --> 00:07:54.806
- If you do, have you spoken to them? Are they able to help you? If not, okay, let's talk a little more.

00:07:54.806 --> 00:08:00.110
- We met with someone today, for instance, who was not able to get help from a bank, and so we're looking

00:08:00.110 --> 00:08:05.262
- around now. Our next action step from that meeting, that technical assistance meeting we had, was to

00:08:05.262 --> 00:08:09.598
- reach out to a lender we know that specifically works in the project area where that

00:08:09.762 --> 00:08:16.000
- Person is interested and we're going to reach out and try to get them connected to understand better

00:08:16.000 --> 00:08:22.485
- what their project might need next that is a project that could be Operating in multi and in about three

00:08:22.485 --> 00:08:27.550
- counties in our region. So it has reached outside the city of Bloomington as well

00:08:28.226 --> 00:08:34.603
- And then we follow up. We have a customer pipeline that we develop and work with our clients and hopefully

00:08:34.603 --> 00:08:41.159
- if they've been referred from a bank then we can create that customer pipeline for the financial institutions

00:08:41.159 --> 00:08:47.357
- in our region. So right now we have about 25 projects in our pipeline. We track that monthly along with

00:08:47.357 --> 00:08:52.542
- our impact. So as far as our impact goes, the 25 projects in our pipeline are a subset

00:08:52.642 --> 00:08:58.987
- This year, we've worked on 11 housing projects, 24 small businesses, and 21 nonprofits in child care.

00:08:58.987 --> 00:09:05.331
- And that could be everything from them getting connected to a loan, a financing product, to us having

00:09:05.331 --> 00:09:11.614
- ongoing technical assistance with them. Housing projects, as this group knows, can take a while, and

00:09:11.614 --> 00:09:16.030
- so those are an immediate turnaround. And so we are glad, though, that

00:09:16.194 --> 00:09:21.610
- we can see some of those projects moving through our pipeline and that we kind of leaned into small

00:09:21.610 --> 00:09:27.297
- business this year. We have not been doing a ton of small business work and this year kind of said we're

00:09:27.297 --> 00:09:32.822
- going to really take small business in and figure out how we can sort of increase our flow there. And

00:09:32.822 --> 00:09:38.400
- Emma has been a big part of that and working with a lot of clients to understand what financing is for

00:09:38.400 --> 00:09:40.350
- the different stages of businesses.

00:09:41.826 --> 00:09:48.385
- So overall, we've had about $29 million of additional CDFI investment in our region over the life of

00:09:48.385 --> 00:09:55.139
- our organization and Jane Cooper-Smith's in here, our former executive director. It's about 425 housing

00:09:55.139 --> 00:09:59.166
- units that have been created or preserved. And that's not us.

00:09:59.426 --> 00:10:05.997
- building and lending on every one, but that's technical assistance, that's partnering lending, that

00:10:05.997 --> 00:10:13.029
- is impacting the conversation and connecting those projects that may not have been able to get traditional

00:10:13.029 --> 00:10:19.600
- financing with the CDFI to get those units online here in the region. And overall, that's about $74

00:10:19.600 --> 00:10:25.054
- million in projects over the last five to six years. So when you take a look back,

00:10:25.218 --> 00:10:31.353
- take a kind of a bird's eye view of this across the country. I talked about this last year, but it's

00:10:31.353 --> 00:10:37.610
- important to point out why CDFIs are important. The lending industry, the traditional lending industry

00:10:37.610 --> 00:10:43.806
- with banks is pretty robust. We want to avoid predatory lending. So this community development sector

00:10:43.806 --> 00:10:50.002
- of lending is really important to sit alongside traditional lending in regions across the country and

00:10:50.002 --> 00:10:53.950
- in Indiana. We are underserved by community development lending.

00:10:54.082 --> 00:11:01.971
- In the last 20 years or so, if you spread CDFI lending across each resident of the United States, you'd

00:11:01.971 --> 00:11:09.708
- get about $825 a person. In Indiana during that time, we are at—well, right now we are at $57. When

00:11:09.708 --> 00:11:16.990
- our organization started, that was $22. So you see the per capita amount increasing slowly, but

00:11:17.250 --> 00:11:23.813
- In other parts of the country, you see a much larger number in how that lending is spread out. We are

00:11:23.813 --> 00:11:30.377
- what's called an opportunity market for community development lending, where there's really only been

00:11:30.377 --> 00:11:37.004
- kind of one lending industry available in addition to that predatory lending. So we want to try to get

00:11:37.004 --> 00:11:43.568
- in there and fill gaps across the region where we can. So just over the last year, in addition to our

00:11:43.568 --> 00:11:46.206
- 300 hours of technical assistance, we've

00:11:46.466 --> 00:11:52.041
- These are just pictures of different events we've been to. We've made a couple trips to DC for some

00:11:52.041 --> 00:11:57.616
- important conversations with our federal representatives, talking about those federal programs that

00:11:57.616 --> 00:12:03.358
- I mentioned earlier. We've presented at a number of conferences and just really tried to get out there

00:12:03.358 --> 00:12:05.086
- and make sure people know that

00:12:05.442 --> 00:12:11.047
- the community development lending industry is there for them when they're not able to access other financing

00:12:11.047 --> 00:12:16.394
- and that's really important and you do that by word of mouth. We've been to about 100 events this year,

00:12:16.394 --> 00:12:21.536
- had a lot of conversations and just trying to make sure people know that word of mouth is there and

00:12:21.536 --> 00:12:26.729
- they can contact us if they need it. Our latest visual example of the project we've worked on is the

00:12:26.729 --> 00:12:32.386
- Chandler Early Learning Center up at the Bloomington Housing Authority with Summit Hill Community Development

00:12:32.386 --> 00:12:33.054
- Corporation.

00:12:33.186 --> 00:12:39.003
- We were one of many partners on this, IHCDA, the City of Bloomington, the Community Foundation, lots

00:12:39.003 --> 00:12:44.934
- of folks over the last five years helped get this project done. And this is a childcare center serving

00:12:44.934 --> 00:12:50.924
- 29 kids, ages zero to three, and there are three units of affordable housing on the second floor. We're

00:12:50.924 --> 00:12:57.086
- really proud to be a partner on that to help finish out construction with IHCDA as the other lender there.

00:12:57.250 --> 00:13:03.532
- And then just an example of a small business, Andrew Statiker has a business on the east side called

00:13:03.532 --> 00:13:10.125
- a clientele, or Supreme Clientele, Minspa. We were able to help him with a loan with Allies for Community

00:13:10.125 --> 00:13:16.345
- Business. Allies is a CDFI out of Chicago that we work a lot with. They're a micro lender. So their

00:13:16.345 --> 00:13:22.627
- average loan size is about $15,000. And we have given them, or loaned them, I should say, capital to

00:13:22.627 --> 00:13:26.110
- get lending, to do those small loans out in our region.

00:13:26.210 --> 00:13:31.984
- And then they'll, of course, return that capital back to us after a certain period of time. But they've

00:13:31.984 --> 00:13:37.758
- got the infrastructure to do those small micro loans and have been able to help a lot of entrepreneurs.

00:13:37.758 --> 00:13:43.365
- And so we are working with them on a sort of capital partnership to get more small business amped up

00:13:43.365 --> 00:13:48.972
- in the region. So that's it. I'll be happy to take questions. I really appreciate the opportunity to

00:13:48.972 --> 00:13:54.302
- present annually. And I really appreciate the RDC's support over the years of our organization.

00:13:54.402 --> 00:14:01.303
- make good on that support and get capital dollars out the door, make sure we are focusing hard

00:14:01.303 --> 00:14:08.785
- on project-based work and providing that technical assistance so that we can get more things done here

00:14:08.785 --> 00:14:16.050
- in the region as a community partner. So any questions? Yeah. Thank you for the presentation. Thank

00:14:16.050 --> 00:14:22.878
- you for all you've included here about impact of CDFI-friendly Bloomington. I'm curious about

00:14:23.714 --> 00:14:29.480
- not just how you measure impact, but how you measure success. Do we benchmark ourselves against other

00:14:29.480 --> 00:14:35.528
- CDFI friendlies? How does that work? That's a good question. There aren't that many other CDFI friendlies.

00:14:35.528 --> 00:14:41.350
- There are four of us across the country. Two of the others are in Indiana, South Bend, and Evansville.

00:14:41.350 --> 00:14:47.003
- So there isn't a benchmark, so to speak, to measure ourselves against. I just asked last week about

00:14:47.003 --> 00:14:49.886
- that technical assistance. That is something every

00:14:50.050 --> 00:14:55.957
- CDFI has to do if you're certified technical assistance slash development services is one of those things

00:14:55.957 --> 00:15:01.641
- you have to provide and so I said for a two-person shop kind of what's our benchmark what should that

00:15:01.641 --> 00:15:07.325
- be for technical assistance and the experts in the field are the folks that helped us get started and

00:15:07.325 --> 00:15:13.009
- seem to be and they're they're consultants in the industry said you know we're doing pretty well with

00:15:13.009 --> 00:15:18.748
- our technical assistance hours but we need to make sure we're outpacing last year which so far we will

00:15:18.748 --> 00:15:20.030
- we outpace 2024 and so

00:15:20.162 --> 00:15:26.554
- We have a sheet, an impact sheet that we update monthly for our board that says how many technical assistance

00:15:26.554 --> 00:15:32.422
- hours, how many training hours, how many folks have we helped, just to sort of measure what that is,

00:15:32.422 --> 00:15:38.291
- because we're kind of breaking new ground here as an organization, because it's an unusual setup for

00:15:38.291 --> 00:15:44.218
- CDFI. Most are just loan funds, and I shouldn't say just, but most of their activity are those loans,

00:15:44.218 --> 00:15:49.854
- and they have a lot of loan volume. Our genesis was not loan volume as much as it was to connect

00:15:50.178 --> 00:15:56.976
- projects with other lenders around the country, and to kind of be a hub, and to be the boots on the

00:15:56.976 --> 00:16:03.842
- ground. So we're kind of blazing a trail here, but it's still important to measure that success, and

00:16:03.842 --> 00:16:10.776
- we're able to kind of chart what that is. Thank you. Commissioner West. First of all, that event last

00:16:10.776 --> 00:16:17.643
- week was great. Oh, thanks. It was well done, and I learned quite a bit from being there. How do you

00:16:17.643 --> 00:16:19.614
- fund yourself operationally?

00:16:20.066 --> 00:16:27.020
- a couple of different ways. We have a loan portfolio that comes in. We get payments. We have some interest

00:16:27.020 --> 00:16:33.519
- there. That is a piece of our operations. The Urban Enterprise Association has given us operational

00:16:33.519 --> 00:16:40.148
- dollars and we have another grant from the city. We also get grants from from banking partners. So we

00:16:40.148 --> 00:16:46.646
- are able to access those federal programs. So we just got done with a $300,000 technical assistance

00:16:46.646 --> 00:16:49.246
- grant whose purpose is to provide those

00:16:49.442 --> 00:16:56.264
- services on the ground. So we just spent that down last month, actually, and that was a that was a two

00:16:56.264 --> 00:17:02.887
- to three year grant. So a lot of different sources, but it's getting more competitive. And so we're

00:17:02.887 --> 00:17:09.642
- always looking for ways to make sure that we can be more self sufficient. One of those is to grow our

00:17:09.642 --> 00:17:15.934
- loan portfolio and have proceeds and interest coming in. So working on that. Thanks. Yes, sir.

00:17:17.474 --> 00:17:23.400
- of your project pipeline, how many of them are in our municipal area? That is a great question. I can

00:17:23.400 --> 00:17:29.559
- get that to you, Commissioner. I will say that our technical assistance, we do about 60% of our technical

00:17:29.559 --> 00:17:35.369
- assistance inside Bloomington. So the pipeline is strong. I would say this year, it's been a lot of

00:17:35.369 --> 00:17:41.237
- activity is in Bloomington. The majority of those housing projects, the 11 that we've worked on have

00:17:41.237 --> 00:17:47.454
- been in Bloomington, most of the small businesses. So it's at least a majority. Majority, of course. Yeah.

00:17:47.650 --> 00:17:53.325
- look at where you're, if you can explain a little bit how you're working with Ally out of Chicago as

00:17:53.325 --> 00:17:59.000
- them taking care of things easily. What is the amount of micro loans they will loan up to, you know,

00:17:59.000 --> 00:18:04.676
- we're comfortable from a financial standpoint with CDFI to help build our small businesses? Yeah, so

00:18:04.676 --> 00:18:10.520
- we loaned them a fairly modest amount of capital just to get the partnership going and to keep, because

00:18:10.520 --> 00:18:16.251
- we don't have a ton ourselves as far as capital goes. They will loan as little as $500 all the way up

00:18:16.251 --> 00:18:17.150
- to $100,000 for

00:18:17.250 --> 00:18:24.123
- entrepreneurs who have been in business for two years or less. Once you get above that, they have a

00:18:24.123 --> 00:18:31.271
- revenue-based financing model where they can do $250,000 if your numbers will show that you can support

00:18:31.271 --> 00:18:38.488
- that sort of debt. Their average loan is about $15,000. And so for us, we've been able to close a couple

00:18:38.488 --> 00:18:40.894
- of loans this year that are in the

00:18:40.994 --> 00:18:46.924
- $2500 range that is sort of a starter amount that they'll do if you haven't been in business very long

00:18:46.924 --> 00:18:53.084
- you need to kind of get going we worked with somebody that was wanting to start a web to get their website

00:18:53.084 --> 00:18:59.187
- going and just some basic business expenses here and there if they just had no cash and so you can pretty

00:18:59.187 --> 00:19:01.950
- easily with you know through an application get

00:19:02.306 --> 00:19:06.890
- get that $2,500 from allies, and then that's called a credit builder, so you can then build up. If you

00:19:06.890 --> 00:19:11.475
- do well with that, then you can get more money. So the idea is to increase the amount that you're able

00:19:11.475 --> 00:19:15.926
- to borrow. And as it builds up, if they've been in business and they can support it, it could go up

00:19:15.926 --> 00:19:20.376
- to $250,000. That's correct. And when we look at it, is this comparable bank interest rates, or are

00:19:20.376 --> 00:19:24.516
- these a little bit sub-interest rate in order to try to build up our entrepreneurial and our

00:19:24.516 --> 00:19:29.278
- small businesses? On the small business side, they're actually going to be a little bit higher than banks,

00:19:29.442 --> 00:19:36.219
- A CDFI borrower traditionally has a profile where they may not be in a secure financial position as

00:19:36.219 --> 00:19:42.997
- someone who can get a bank loan, right? So their credit score may be a factor. A lack of collateral

00:19:42.997 --> 00:19:49.910
- may be a factor. Being in business for a very little period of time, a bank won't usually do that. So

00:19:49.910 --> 00:19:53.502
- a CDFI will have a couple of basis points, you know,

00:19:54.146 --> 00:19:59.281
- allies rates run between nine and twelve percent I think so that's above market but not too far and

00:19:59.281 --> 00:20:04.519
- it definitely not predatory we want to be very clear that the predatory loan industry is you're gonna

00:20:04.519 --> 00:20:10.065
- get into the 20s and 30s with a lot of fees so we want to. Approximately nine to twelve with no prepayments

00:20:10.065 --> 00:20:15.611
- and such so. That's right. You know as we start out our small businesses you know even the largest business

00:20:15.611 --> 00:20:20.952
- small that start does a small one so. Yeah. Those capital. So so the product is designed to be flexible

00:20:20.952 --> 00:20:23.006
- you may pay a higher interest rate but.

00:20:23.170 --> 00:20:29.539
- the flexibility is there. So if something isn't going well, they'll want to renegotiate the terms and

00:20:29.539 --> 00:20:36.033
- try to not. So if anyone's out here listening and such identifies that, how do they actually go through

00:20:36.033 --> 00:20:42.465
- an application by contacting you? Yeah, go to our website and contact myself, John Zote or Emma Yoder.

00:20:42.465 --> 00:20:45.150
- We'll see what they have, what's in there.

00:20:45.666 --> 00:20:51.205
- idea pipeline, if you will, and then see if they should be connected with a lender, or if we want to

00:20:51.205 --> 00:20:56.799
- work with them a little bit. Or we may refer them to the SBDC, the Small Business Development Center,

00:20:56.799 --> 00:21:02.502
- if they don't have a business plan that's finished, or they have some legal stuff they need worked out.

00:21:02.502 --> 00:21:08.041
- We don't provide legal advice. That's SBDC and others. So they'll come back to us when they might be

00:21:08.041 --> 00:21:13.690
- ready to talk about financing. If they need that, what kind of time frame does this entail? It varies.

00:21:13.690 --> 00:21:15.390
- So with a small business loan,

00:21:15.586 --> 00:21:22.578
- of the sort of under $10,000 you can usually we're talking a week or two if everything goes well. Housing

00:21:22.578 --> 00:21:29.306
- projects will take a while to underwrite. Usually that's a 90 day to 120 day start to finish. But for

00:21:29.306 --> 00:21:35.968
- small business, we're talking weeks. Small business. Yes. Okay. Thank you. Appreciate it. Thank you.

00:21:35.968 --> 00:21:43.422
- Do you foresee any potential for where RDC business might intersect with what CDFI friendly Bloomington could do

00:21:43.778 --> 00:21:50.141
- I'm thinking, for example, Hobo South, as those units move towards development, but there may be others

00:21:50.141 --> 00:21:56.749
- as well. I'm just curious if you have insights or thoughts that might be helpful just to pique our interest

00:21:56.749 --> 00:22:03.051
- for the future. Yeah, I do. I think, you know, certainly rely on you all and staff at the city to sort

00:22:03.051 --> 00:22:08.190
- of guide how that's all developed, but certainly CDFI's could be a lending partner.

00:22:08.354 --> 00:22:14.281
- there. I think one thing we've talked about some is that in the CDFI community, there aren't a lot of

00:22:14.281 --> 00:22:20.208
- mortgage products, right? So we're talking about how to increase homeownership here in Bloomington or

00:22:20.208 --> 00:22:26.368
- anywhere else in the region. There aren't a lot of CDFIs that do mortgages, but banks, banks do mortgages

00:22:26.368 --> 00:22:29.854
- that can be designed for those who might need an affordable

00:22:29.954 --> 00:22:35.757
- product right so banks kind of have this community development lending responsibility a lot of mortgages

00:22:35.757 --> 00:22:41.725
- operate in that space and so we've worked with banking partners to try to collect some mortgage information

00:22:41.725 --> 00:22:47.473
- that may be a way we can help we're here to here to help the city however can get that done we've tried

00:22:47.473 --> 00:22:53.331
- to be supportive during the PUD development and consideration process just to keep those options flexible

00:22:53.331 --> 00:22:55.486
- for how we can develop housing because

00:22:55.778 --> 00:23:04.352
- I don't have to tell anybody in this room. It takes a while. I need a lot of tools on the table to get

00:23:04.352 --> 00:23:12.926
- it done. So I'm glad to be a partner. Anything else? OK. Thank you so much for the presentation. Thank

00:23:12.926 --> 00:23:21.500
- you all. Thank you, John. So next on our agenda, we have another. Well, we have legal report. Is that?

00:23:21.500 --> 00:23:24.414
- My discussion will come later. OK.

00:23:24.642 --> 00:23:33.362
- So we will come back to that. We have a treasurer's report. Yeah, so this is the first of two items

00:23:33.362 --> 00:23:42.430
- today in which my role is primarily to introduce Justin Chang from Leedy. This is also the first of two

00:23:42.786 --> 00:23:50.475
- statutorily required presentations that are being provided. This one in particular is the, under the

00:23:50.475 --> 00:23:58.164
- Treasurer's Report, is the annual TIF impact presentation. And this is statutorily not only targeted

00:23:58.164 --> 00:24:04.254
- at you, the Redevelopment Commission, but to the governance bodies of the other

00:24:04.578 --> 00:24:13.590
- taxing units that overlap the TIF. And so they are invited and encouraged to attend. And actually,

00:24:13.590 --> 00:24:22.784
- I see Dr. Winston from MCCSE on Zoom. So I only have them in PDF form. So it's not quite as slick as

00:24:22.784 --> 00:24:32.798
- Justin's original slide presentation. But it's fine. I'll go ahead and control that and take it away, Justin.

00:24:32.898 --> 00:24:38.958
- Perfect. Justin Chang with 3D Financial Group. It's great to see everyone again. I believe I did this

00:24:38.958 --> 00:24:45.315
- presentation for everyone last year as well. But just as a quick recap, like Jeff mentioned, the reporting

00:24:45.315 --> 00:24:51.375
- really is meant for the public. So some of this information you may already know, but for the sake of

00:24:51.375 --> 00:24:57.554
- the reporting, I have to include them. I'll try to make this meeting as useful to you as possible while

00:24:57.554 --> 00:25:01.950
- also meeting the statutory requirements. So the second slide here is just

00:25:02.146 --> 00:25:08.675
- a checklist of all the requirements that we did this year, just as a reminder, there are six total,

00:25:08.675 --> 00:25:15.399
- and there's only two left. You'll see at the bottom, it's the prior to December 1st TIF spending plan,

00:25:15.399 --> 00:25:21.732
- which we will do after this, and we are currently doing the December 31st end-of-year TIF impact

00:25:21.732 --> 00:25:28.456
- presentation. So one of the information that we're required to provide is basic information on the TIF

00:25:28.456 --> 00:25:29.566
- allocation area.

00:25:29.890 --> 00:25:35.901
- Bloomington RDC has two main TIF allocation areas. First is the Bloomington Consolidated Allocation

00:25:35.901 --> 00:25:42.031
- Area, which consists of, I believe, 26 different TIFs. And then North Kinser Pike. Keep in mind, this

00:25:42.031 --> 00:25:48.042
- does not include any of the new ones that we created this year, so Shasta Metal is not on here this

00:25:48.042 --> 00:25:54.112
- year. Neither is Hopewell, but they will be in 2027 when we do this. For the expiration years, 2029,

00:25:54.112 --> 00:25:59.582
- that is the earliest expiration that we know within Consolidated Allocation Area, but that

00:25:59.714 --> 00:26:06.608
- we do have most of the areas in that Bloomington consolidated does go out to 20 40 North Kinser Pike.

00:26:06.608 --> 00:26:13.503
- Unfortunately, it's gone after this year and we will not be collecting increment on that tip starting

00:26:13.503 --> 00:26:20.397
- in 27 incremental AV. We saw about 1.29 this year. We are looking at closer to 1.3 to 1.4. As you may

00:26:20.397 --> 00:26:25.534
- know, we just completed the residential removal, so that's going to change.

00:26:25.858 --> 00:26:33.228
- what we're seeing a little bit for page 27, we will let you all know once we have those final numbers,

00:26:33.228 --> 00:26:40.527
- which we just received the parcels for last Friday. Are you indicating up or down? Up. Thank you. But

00:26:40.527 --> 00:26:47.683
- don't quote me, but up. No quote, just trying to get a gauge. But probably up, most likely up, yes.

00:26:47.683 --> 00:26:53.694
- Next tab, this is the financial positions tab. So if we just look big picture wise,

00:26:54.082 --> 00:27:02.340
- for the Bloomington consolidated allocation area, we're projecting about $24 million in revenues and

00:27:02.340 --> 00:27:10.599
- 22.2 in expenditures. So we're projecting about $1.6 million increase in cash balance. Keep in mind,

00:27:10.599 --> 00:27:18.857
- these are projections. So current year expenses here today might not reflect this number, and a good

00:27:18.857 --> 00:27:21.310
- example is North Kinser Pike.

00:27:21.410 --> 00:27:28.280
- I believe there hasn't been any expenditures out of that TIF allocation area. We just have that in there

00:27:28.280 --> 00:27:34.954
- because we were projecting a cash spend down due to that TIF expiring. Can you remind me what happens

00:27:34.954 --> 00:27:41.758
- with any end of year balance that's not spent down from the expiring North Kinser Pike allocation area?

00:27:41.758 --> 00:27:48.694
- So nothing really happens. And one of the reasons is that we don't actually know yet because North Kinser

00:27:48.694 --> 00:27:50.526
- Pike is probably one of the

00:27:50.658 --> 00:27:57.001
- earliest to expire in the state. So we don't have a lot of precedence for that yet. As of now, we've

00:27:57.001 --> 00:28:03.408
- not seen anything from the DLGF or SBOA telling us, hey, let your clients know to spend these dollars

00:28:03.408 --> 00:28:09.814
- now. We haven't seen anything like that yet. But we do encourage it to not hold dollars for too long.

00:28:09.814 --> 00:28:16.283
- We need to make sure we have a project in place prior to the expiration of the TIF in order to utilize

00:28:16.283 --> 00:28:19.486
- it without having to be a test case for the state.

00:28:20.418 --> 00:28:27.030
- probably a better question for legal, but we don't see anything that says we need projects in place

00:28:27.030 --> 00:28:33.642
- before TIFA expiration. We do have... It's nice to just cease bringing in funds, but there may be a

00:28:33.642 --> 00:28:40.585
- way to use the funds after the actual expiration. I'm just understanding expiration means that the funds

00:28:40.585 --> 00:28:44.222
- are no longer coming in. Correct. Well, nothing has to

00:28:44.418 --> 00:28:50.350
- indicated that we need to spend the funds by December 31st, 2026. We just won't be receiving any more

00:28:50.350 --> 00:28:56.224
- TIF revenues. But the ideal situation would at least have a project identified prior to it. We would

00:28:56.224 --> 00:29:02.040
- highly encourage that, yeah. We would encourage that. Occurring long-term future plans for the REC,

00:29:02.040 --> 00:29:07.390
- just some of the projects that we have going on is the Hopewell TIF, which we just created.

00:29:07.490 --> 00:29:14.955
- The summer project, we created a Shasta Meadows. I know there's future plans for that as well. And we

00:29:14.955 --> 00:29:22.785
- had the potential hotel project and I know a few public safety projects as well that are under discussion.

00:29:22.785 --> 00:29:30.104
- So these are just future plans that the RDC has. Nothing set in stone yet. This tab sort of sets up

00:29:30.104 --> 00:29:33.470
- the actual impact analysis that is coming up.

00:29:33.570 --> 00:29:39.811
- Many of you have already been on the RDC for a while, so I'm not going to spend a whole lot of time

00:29:39.811 --> 00:29:46.177
- on this. Essentially, this is just illustrating how a TIFF works, which is you have the base assessed

00:29:46.177 --> 00:29:52.792
- values, which is the AVs of the parcels prior to creating a TIFF. Once you create a TIFF, any incremental

00:29:52.792 --> 00:29:59.095
- AV goes towards the RDC, goes towards the TIFF allocation areas. And once that TIFF expires in 2025,

00:29:59.095 --> 00:30:00.094
- all that growth

00:30:00.258 --> 00:30:07.375
- due to the TIF goes back to the base. And this is, again, this is one of the slides that's more meant

00:30:07.375 --> 00:30:14.492
- for the public, because you all have seen this quite a few times. So another setup slide for the next

00:30:14.492 --> 00:30:21.609
- analysis, which is essentially our impact essentially answers the question, what would happen if this

00:30:21.609 --> 00:30:28.656
- TIF, all the assessed values in the TIF would have happened if we didn't provide all the incentives?

00:30:28.656 --> 00:30:29.982
- So if we think of,

00:30:30.562 --> 00:30:38.378
- Meridian was a good example where we had to provide an economic development agreement. And it's essentially

00:30:38.378 --> 00:30:46.122
- asking if all the assessed value came into the Meridian, from the Meridian TIF came into the base assessed

00:30:46.122 --> 00:30:53.504
- values anyways, what would happen to property tax collection. So this is a very hypothetical scenario

00:30:53.504 --> 00:30:59.294
- that wouldn't actually happen because, again, Meridian TIF, that TIF would not,

00:30:59.458 --> 00:31:06.706
- would not be around if it wasn't because the RDC was able to provide some sort of economic development

00:31:06.706 --> 00:31:13.814
- agreement. But this is just a setup slide to say this is the preface before we go into the analysis.

00:31:13.814 --> 00:31:20.992
- The impact chart, essentially what this does is it takes all that assessed value, that $1.289 billion

00:31:20.992 --> 00:31:27.326
- that we saw on page three, I believe, and we said we threw this entire $1.29 billion into

00:31:27.490 --> 00:31:35.375
- the base assessed values, what would be the impact to all the underlying units? And you'll see, even

00:31:35.375 --> 00:31:43.493
- though Monroe County is listed first, that is because we list that based off the Circle Breaker impact,

00:31:43.493 --> 00:31:51.690
- but you'll see the highest impact is actually to Bloomington City due to that $644,000 rate-driven funds

00:31:51.690 --> 00:31:54.110
- impact. So what this shows is,

00:31:54.594 --> 00:32:02.990
- of a total, if we look at that $48,000 plus $1 million in the middle, right under the blue,

00:32:02.990 --> 00:32:12.389
- of that $1.1 million impact, about $650,000 of that is actually going to the city. So the message that

00:32:12.389 --> 00:32:21.698
- I try to convey is, for the most part, the city is bearing most of the impact anyways for having this

00:32:21.698 --> 00:32:23.614
- tip allocation area.

00:32:23.906 --> 00:32:30.818
- Jeff, can we go to the next page, actually? Just for all of our clarification, what's a rate-driven

00:32:30.818 --> 00:32:38.006
- impact? Rate-driven impact is, so this could take a while. No, it won't. But the way Indiana taxes work

00:32:38.006 --> 00:32:44.987
- is that we're a levy-based state. So essentially what that means is we can't change our property tax

00:32:44.987 --> 00:32:52.382
- rates. So when you throw a bunch of assessed value into the property tax base, it just drops the tax rate.

00:32:52.514 --> 00:32:59.730
- So our levy stays the same. Rate-driven funds acts the opposite way. There's only two rate-driven funds

00:32:59.730 --> 00:33:06.947
- from here. It's Monroe County has a CCD fund, which is a capital development fund, and Bloomington City

00:33:06.947 --> 00:33:14.233
- also has a cumulative capital development fund. Those rates stay the same. So when you throw an assessed

00:33:14.233 --> 00:33:20.894
- value into the base, those rates can actually capture on the entire increase in assessed value.

00:33:21.026 --> 00:33:27.970
- And for Bloomington, which has a very, very low circuit breaker, their rage driven funds impact is actually

00:33:27.970 --> 00:33:34.463
- the highest, which is very rare because most of our clients have higher circuit breaker. Bloomington

00:33:34.463 --> 00:33:40.892
- is fortunate in that instance where circuit breaker is low, tax rates are low. So the entire impact

00:33:40.892 --> 00:33:47.386
- really goes straight to their rage driven funds instead of circuit breaker. This page summarizes all

00:33:47.386 --> 00:33:48.350
- those numbers.

00:33:48.770 --> 00:33:55.347
- from that previous page, essentially what we created is called the TIF margin. So 0.95 TIF margin is

00:33:55.347 --> 00:34:02.054
- probably the highest of all my clients at least. Essentially what that means for every dollar that the

00:34:02.054 --> 00:34:08.631
- TIF brings in, 95 cents of that is because we utilize the TIF allocation area. So if we look at that

00:34:08.631 --> 00:34:15.273
- in green under that, that 23.7, that's the total TIF revenues that the RDC brought in. But under that

00:34:15.273 --> 00:34:18.334
- in yellow, 22.6 is because we utilize the TIF.

00:34:19.266 --> 00:34:27.119
- If we did not utilize the TIF and the AVs still came into all the base units, all the base units added

00:34:27.119 --> 00:34:34.896
- together would have only received $1.1 million. So for utilizing the TIF, we generated an extra $22.6

00:34:34.896 --> 00:34:42.749
- million annually for the community. So quick question in regards to that. If that was the case, you're

00:34:42.749 --> 00:34:46.942
- saying that $21 million would reduce taxpayers' bills?

00:34:47.938 --> 00:34:57.100
- 21 million would reduce. 22 million, 661 minus the 1.2. Just curious. For this instance, let me think,

00:34:57.100 --> 00:35:06.884
- if we're looking at. If we didn't have TIF. Portions of it, yes, but not the entire thing. Again, rate-driven

00:35:06.884 --> 00:35:14.622
- funds is a big part of it. Rate-driven expenses. And one way that I think about it is,

00:35:14.946 --> 00:35:22.184
- you saw a large drop, a lot of the units will start to find ways to increase that property tax level

00:35:22.184 --> 00:35:29.351
- too. So if in a vacuum, to answer your question, yes. But it doesn't work that way in reality, yes.

00:35:29.351 --> 00:35:36.517
- OK. Thank you. But that concludes my presentation. Happy to answer any other questions. I feel like

00:35:36.517 --> 00:35:43.683
- this is an extremely important slide because this question comes up all the time. We see what we're

00:35:43.683 --> 00:35:44.830
- losing from it.

00:35:45.090 --> 00:35:50.821
- But what are we actually getting? And the answer is we're losing a million dollars, but we're getting

00:35:50.821 --> 00:35:56.721
- $22.6 million. Correct. And that's every single year that the TIF is active. And that money collectively

00:35:56.721 --> 00:36:02.509
- can do our redevelopment projects. It helps increase the quality of the community, the infrastructure,

00:36:02.509 --> 00:36:07.678
- in order to make the community a better place. That's the basis of it. Is that correct? OK.

00:36:09.730 --> 00:36:16.342
- So if we're looking over a life of 25 years, that's over $400 million. And right now, given the existing

00:36:16.342 --> 00:36:23.144
- TIF we have, excluding the two that we've just done, what's our time frame on our TIFs, on our consolidated

00:36:23.144 --> 00:36:29.504
- TIF? Because consolidated TIF has a bunch in between there. We have some starting to expire in 2029,

00:36:29.504 --> 00:36:35.802
- but we really won't. I would say 80% of it doesn't expire till 2040. So we still have, what's that,

00:36:35.802 --> 00:36:37.502
- 13, 14 years around there?

00:36:37.858 --> 00:36:44.478
- So as we look at projects without redoing a TIF, we need to be cognizant of the fact that we've got

00:36:44.478 --> 00:36:51.165
- a 13-year time frame for our financial. Yes. And your bond modeling takes that into account. Yes. So

00:36:51.165 --> 00:36:57.851
- one of the things that we've actually discussed with Jeff and Anna was we have certain bond projects

00:36:57.851 --> 00:37:04.670
- like the Hopewell Bonds, Summit Bonds, Public Safety. When we started looking at these back in 23, 24,

00:37:05.794 --> 00:37:12.883
- we could bond for a lot more with a lower impact, but because the TIF life is the same, we're essentially

00:37:12.883 --> 00:37:20.039
- thinking about it as if you're taking out a mortgage, $200,000 mortgage over 30 years, the monthly payment

00:37:20.039 --> 00:37:26.860
- is different from $200,000 over 10 years. So as we drag along some of these projects, our flexibility

00:37:26.860 --> 00:37:31.742
- is reduced because our TIF life can't expand over what they already are.

00:37:34.498 --> 00:37:41.708
- There's been talk about the possibility of, let's say, establishing a downtown TIF that I believe would

00:37:41.708 --> 00:37:48.640
- be taking that out of what is currently a consolidated TIF. What does that do for the TIF timeline,

00:37:48.640 --> 00:37:56.058
- if that were to occur? So the new downtown TIF would have its own timeline. It will not affect the current

00:37:56.058 --> 00:38:03.198
- TIF's timeline. Now, if we are taking parcels out of the current TIF into the new TIF allocation area,

00:38:03.650 --> 00:38:10.022
- then that parcel after it's been moved gets 25 years with that new TIF allocation area. But it loses

00:38:10.022 --> 00:38:16.710
- any incremental AV it previously had. So we want to be selective when we do that. We don't want to remove

00:38:16.710 --> 00:38:23.082
- something that's currently making, you know, $200,000 a year because we've just taken that away. Are

00:38:23.082 --> 00:38:29.454
- you able to pick those particular parcels if it's within a geographic area? As long as they meet the

00:38:29.454 --> 00:38:32.798
- continuity test, then yes, we can certainly do that.

00:38:33.378 --> 00:38:41.331
- We have done that in the past. Thank you so much for your presentation. Do we go to the spending plan

00:38:41.331 --> 00:38:49.128
- next? No, it's a little bit later. Okay, because I have one question in regards to that. Thank you.

00:38:49.128 --> 00:38:57.159
- Anything else for me? One quick question in regards to dealing with our trades district and the amount

00:38:57.159 --> 00:39:01.214
- that we received in that has been within the 25-19.

00:39:02.498 --> 00:39:11.114
- Is that whole fund amount still available to be utilized? Well, it's not segregated. I mean, it's just,

00:39:11.114 --> 00:39:19.482
- yeah, it's not segregated, particularly. But I mean, you did receive it. OK. So it's all part of the

00:39:19.482 --> 00:39:27.933
- $33 million that's in the bank, as far as what? Yes. OK. Thank you. OK. Well, next item on our agenda

00:39:27.933 --> 00:39:30.750
- is a business development update.

00:39:30.882 --> 00:39:37.833
- Just a small business development update to let you know the OT 987 sculpture in the Trace District,

00:39:37.833 --> 00:39:44.853
- the lights are back on for those of you who have been curious about that. So it's been quite a bit of

00:39:44.853 --> 00:39:51.873
- investigative work on the part of our arts team, along with some technical support. So that's it. And

00:39:51.873 --> 00:39:57.310
- I second John's, or Commissioner, oh my god. Just John. Okay, I second John's.

00:39:58.242 --> 00:40:05.154
- kudos to the CDFI event at the trades district and then we also had a really wonderful three-day AMP

00:40:05.154 --> 00:40:12.271
- Bloomington event working to connect people doing all things tech and startup bringing kind of students

00:40:12.271 --> 00:40:19.525
- and community together and the creative economy as well so that event roved from the mill to the Buzzkirk

00:40:19.525 --> 00:40:26.437
- Chumley and then on campus so it was really really awesome and I hope some of you were able to see a

00:40:26.437 --> 00:40:27.806
- little bit of that.

00:40:28.034 --> 00:40:35.003
- Great. Thanks. Thank you. And I don't see Hopewell on our agenda, but I saw Mr. Knuckey online. I just

00:40:35.003 --> 00:40:42.107
- want to make sure that I'm not missing anything. No Hopewell updates this evening. He's here for another

00:40:42.107 --> 00:40:48.941
- agenda. OK. Thank you. Can we ask a question about Hopewell? Sure. OK. How long in the time frame to

00:40:48.941 --> 00:40:51.038
- try to get that moved forward?

00:40:52.066 --> 00:41:00.059
- and CCRs? Well, we did give a community update last week for the Hopewell project. Hopewell South was

00:41:00.059 --> 00:41:07.973
- really in the spotlight. We continue to work with civil engineering and so we've made a submittal to

00:41:07.973 --> 00:41:16.122
- CBU and planning to make sure. We're trying to work towards our secondary plan. And so we're continuing

00:41:16.122 --> 00:41:18.238
- to work on that right now.

00:41:18.690 --> 00:41:25.099
- There are a lot of millions of details that have to get worked out. So we're moving as quickly as we

00:41:25.099 --> 00:41:31.445
- possibly can. Do we think sometime an application before the end of the year will be first in line?

00:41:31.445 --> 00:41:37.854
- We are trying to make an application before the end of the year, yes. Absolutely. So right now we're

00:41:37.854 --> 00:41:44.453
- doing a lot of pre-review to make sure that we don't have a lengthy process when it comes to the actual

00:41:44.453 --> 00:41:45.278
- application.

00:41:46.562 --> 00:41:53.655
- go secondary plat and then we'll be able to start correct. So right now we're working on getting covenants

00:41:53.655 --> 00:42:00.416
- and restrictions put together before that plot is recorded. So a lot of little legal things that need

00:42:00.416 --> 00:42:07.111
- to be done. And in fact, we have an update as far as that's concerned, that we'll talk about in just

00:42:07.111 --> 00:42:14.071
- a bit. So unless you would you like to talk about it now? The outside council? Oh, yeah, I guess I could

00:42:14.071 --> 00:42:16.126
- have mentioned this during the

00:42:16.546 --> 00:42:27.425
- Legal report the. Corporation Council Marjorie said in talking with other department heads and determined

00:42:27.425 --> 00:42:37.894
- that there was a need for outside counsel to help with the covenants and restrictions and some of the

00:42:37.894 --> 00:42:45.694
- HOA documentation just due to the bandwidth of. What we have in the office.

00:42:45.986 --> 00:42:59.473
- And so as Corporation Council, she is the one who is able to enter into engagement letters to do that.

00:42:59.473 --> 00:43:12.830
- And so she has... She's online. I don't know if she wants to chime in. But the current letter is a...

00:43:13.346 --> 00:43:25.161
- engagement is a not to exceed of $25,000. And so that would be an administrative type of cost to the

00:43:25.161 --> 00:43:36.859
- RDC. But the bandwidth again of the legal departments to do that on top of everything else was just

00:43:36.859 --> 00:43:42.942
- too much. So she engaged outside counsel to assist.

00:43:43.874 --> 00:43:49.640
- I think it's designed to really expedite things. I mean, we also, if we're talking about condos for

00:43:49.640 --> 00:43:55.406
- the two multifamily structures, there needs to be a horizontal property regime. You know, there's a

00:43:55.406 --> 00:44:01.172
- lot of little minute details that we need to try and button up so that we don't get to the end, the

00:44:01.172 --> 00:44:07.227
- finish line and go, oops. So also purchase agreements to make sure that all of our language is in place,

00:44:07.227 --> 00:44:10.110
- rights of first, or rights of, I can't even talk.

00:44:10.274 --> 00:44:17.346
- tonight, rights of first refusal that should be part of those agreements. So just lots of little things

00:44:17.346 --> 00:44:24.282
- like that, but also the technical review of the civil engineers and planning, CBU, everyone. So we're

00:44:24.282 --> 00:44:31.286
- working as swiftly as possible, but a lot of details. And it did take quite some time to implement all

00:44:31.286 --> 00:44:36.318
- of the reasonable conditions that were added to the project from council.

00:44:37.442 --> 00:44:44.117
- So dealing with that word, I just heard from Dana in regards to it. Having outside counsel should expedite

00:44:44.117 --> 00:44:50.355
- the CCNRs and the necessary legal documents so we can get filed. Correct. Because you don't want to

00:44:50.355 --> 00:44:56.843
- do the secondary plat until you have the covenants and restrictions in place. Correct. Yeah. So I think

00:44:56.843 --> 00:45:03.082
- we're anticipating and hoping that we can go out for bid for infrastructure in February. So that is

00:45:03.082 --> 00:45:04.766
- the target date right now.

00:45:05.090 --> 00:45:11.470
- Hopefully, someone can be building yet this spring, summer. Yeah, because that's the goal we're looking

00:45:11.470 --> 00:45:17.788
- for come spring, that we start actually breaking down and providing housing. Right. So everyone thinks

00:45:17.788 --> 00:45:23.983
- it's taking a lot of time, but believe me, everyone is working really hard. Big shout out to Kendall

00:45:23.983 --> 00:45:30.301
- Kanoki in engineering and Anna Dragovich, who have all helped keep this moving as quickly as possible.

00:45:30.301 --> 00:45:33.982
- Legal has been working tirelessly. It's just a big project.

00:45:34.370 --> 00:45:41.043
- A lot of details, a lot of reasonable conditions to deal with. And with this, on the legal end of it,

00:45:41.043 --> 00:45:47.651
- do we have to go through a contract or are we already be able to engage quickly so we've got them on

00:45:47.651 --> 00:45:54.455
- board? They're already engaged. They're already engaged. All right, thank you. Okay, thank you for your

00:45:54.455 --> 00:45:59.166
- questions. We will now move on to other items of business starting with

00:45:59.362 --> 00:46:08.706
- We have two clean registers from October 23rd and November 6th, 2026. Well, November 6th, what's up

00:46:08.706 --> 00:46:18.050
- with that? We're not even there yet. Is that just? OK, anyway, it's for the time. It's 1024 to 116.

00:46:18.050 --> 00:46:27.394
- OK, so those are those cleaning periods and the previous one was 1010 to 1023, so it's when they'll

00:46:27.394 --> 00:46:28.702
- actually hit.

00:46:29.186 --> 00:46:34.858
- Right. That's the payday. That's the payday. So they're processed two weeks in advance for a payment.

00:46:34.858 --> 00:46:40.418
- So it's not often that the dates come up ahead of the actual meeting date. So I just wanted to make

00:46:40.418 --> 00:46:46.368
- sure that we were on the same page. It is surprising. We're not actually looking into the future. Exactly.

00:46:46.368 --> 00:46:51.984
- OK. So I'm just going to propose to RDC members that we consider either questions or motions on both

00:46:51.984 --> 00:46:57.601
- of these claims together unless you request to separate them. So any questions or comments on either

00:46:57.601 --> 00:46:59.102
- of these claims? Question.

00:46:59.778 --> 00:47:08.227
- Go ahead, John. You want to respond to that? Sure. John had emailed me a question regarding the crossroads

00:47:08.227 --> 00:47:16.123
- engineering claims that went through. There's six of them currently on page 506 of the claim period

00:47:16.123 --> 00:47:17.150
- 1024 to 116.

00:47:17.282 --> 00:47:26.455
- All of those claims were related to the beeline extension project that is going on. You guys approved

00:47:26.455 --> 00:47:35.447
- the resolution 25139 and 2625 for those. So that is just part of that project. And that's our local

00:47:35.447 --> 00:47:44.350
- match project that we had to do. Yeah. Next question? OK. The next question is a quamant, I guess.

00:47:45.058 --> 00:47:54.677
- Yes, a question and a comment. Okay, it's page one. Yeah, of course. You know, the account 53 990. Sorry,

00:47:54.677 --> 00:48:03.841
- it's claim October. October's claim. It's 1010 to 1023. Yeah, 1010 to 1023. Okay, 1010 to 1023. Yes,

00:48:03.841 --> 00:48:12.734
- sir. Account 53 990. It's line 9216. It's Williams Creek management for our evergreen project. So

00:48:12.834 --> 00:48:19.007
- The question I have is, since we've engaged legal to help with HOPE, well, can we engage someone to

00:48:19.007 --> 00:48:25.364
- help that one? Potentially, you know, we really don't know what to do with that situation. We met with

00:48:25.364 --> 00:48:31.907
- the homeowners several times according to the original agreement. The homeowners association was supposed

00:48:31.907 --> 00:48:38.265
- to take over that project and they do not feel like they are in a situation where they can financially

00:48:38.265 --> 00:48:39.006
- support it.

00:48:39.138 --> 00:48:46.271
- A lot of the homes have in the affordability periods have ended and there are new owners that knew nothing

00:48:46.271 --> 00:48:53.137
- of this situation. So, and in fact, I do believe that this Williams Creek agreement is expiring at the

00:48:53.137 --> 00:49:00.003
- end of the year. So we really do need to figure out what's next from my personal opinion to get an HOA

00:49:00.003 --> 00:49:02.270
- set up with no money in the bank.

00:49:02.594 --> 00:49:08.694
- is a hefty lift. And I think that that's one of the barriers. So if we were to consider transferring

00:49:08.694 --> 00:49:15.096
- this, it may be appropriate for you to entice with some seed money for that HOA to get it off the ground.

00:49:15.096 --> 00:49:21.196
- Otherwise, I just, I don't think that there's a lot of motivation. The city is still in ownership of

00:49:21.196 --> 00:49:27.477
- that retention pond, which is really that rain garden. And so we have to maintain it for CVU stormwater

00:49:27.477 --> 00:49:28.926
- purposes at this point.

00:49:29.026 --> 00:49:36.781
- But I think a transition plan where we potentially see that HOA might entice them to move. But we have

00:49:36.781 --> 00:49:44.536
- been unsuccessful in all of our meetings to date. That's why I bring this up, because this project has

00:49:44.536 --> 00:49:51.614
- been on for what, 15 years? Prior to this administration? I've only been here for a few, yes.

00:49:51.906 --> 00:49:57.708
- asked in regards to the comment or the question is what is the legal hurdles as we're looking to establish

00:49:57.708 --> 00:50:03.185
- HOAs for Hopewell that we could also actually utilize this so that 20 years from now we're still not

00:50:03.185 --> 00:50:09.150
- in that circumstance. And the homeowners have the control of their neighborhood, which was always the intent.

00:50:09.570 --> 00:50:16.170
- Well, and I think it's difficult. I don't want to speak for legal, but just from experience, you know,

00:50:16.170 --> 00:50:22.257
- setting up a new HOA is one thing, but once it's an established neighborhood, really that HOA,

00:50:22.257 --> 00:50:28.729
- those bylaws, everything associated needs to be decided by the homeowners, not by the city that only

00:50:28.729 --> 00:50:32.830
- owns one lot in the area. So we could, I don't know that hiring

00:50:32.962 --> 00:50:38.992
- outside council or structuring it for them is the right thing to do, but potentially seeing them with

00:50:38.992 --> 00:50:45.022
- the money to go make those decisions, to create those documents, that would be my personal opinion of

00:50:45.022 --> 00:50:51.230
- what the right thing to do. Sure. The problem that you always see in a homeowners association is getting

00:50:51.230 --> 00:50:57.319
- people to agree. And we are part of the homeowners association at the present moment. Is that correct?

00:50:57.319 --> 00:51:02.462
- Well, we have ownership. Yeah. So how to structure that? And I'll defer that to legal.

00:51:02.658 --> 00:51:08.507
- look at, because if we're establishing one for Hopewell, can we work on this one also in the same type

00:51:08.507 --> 00:51:14.356
- like? Oh, it's a different, way different scenario. Yes, different scenario and I'm not of the opinion

00:51:14.356 --> 00:51:20.602
- that you should, it would be similar. Okay. I think that they need to make those decisions as a neighborhood.

00:51:20.602 --> 00:51:26.735
- So they need to, we need to go to them or they need to come to us to ask for seed money to try to establish

00:51:26.735 --> 00:51:28.382
- it, because it won't go away

00:51:28.610 --> 00:51:35.389
- Well, we're at a crossroads when it comes to December. Like the end of December, their contract expires.

00:51:35.389 --> 00:51:41.909
- Williams Creek does for this management. So we need to figure out whether we offer the seed money to

00:51:41.909 --> 00:51:48.494
- get them going and give them an off-ramp, a timeline by which they need to execute in order to obtain

00:51:48.494 --> 00:51:55.079
- that money. And that's my suggestion. But of course, this is up to you guys. I'm not a voting member.

00:51:55.079 --> 00:51:57.790
- I like your plan. Just how do we execute?

00:51:58.018 --> 00:52:06.292
- you know, limited resources. We'll get it done. Okay, thank you. And then other questions. It would

00:52:06.292 --> 00:52:14.566
- be page four of page four of the packet. Number 29. And this is just a matter of miscellaneous that

00:52:14.566 --> 00:52:23.006
- plays all the way through through our utility bills. Again, just a comment based on utility bills and

00:52:23.006 --> 00:52:26.398
- maintenance for properties that we have.

00:52:26.626 --> 00:52:34.123
- that are either underutilized or not really anyone occupying at the present moment. It's about $18,000

00:52:34.123 --> 00:52:41.401
- when we total everything from janitorial to Duke in 2518. I know there's nothing we can do about it

00:52:41.401 --> 00:52:48.753
- at the present moment. We have to keep the facilities on. A lot of that is Hope Wall lighting. Those

00:52:48.753 --> 00:52:54.430
- are exterior lights that need to happen. Yeah, the particular ones I was more

00:52:54.850 --> 00:53:03.226
- question was, of course, our showers west in regards to our 714 utility bills and our college square.

00:53:03.226 --> 00:53:11.930
- Those would be the three in that particular room. I just want to make note that, you know, we're spending

00:53:11.930 --> 00:53:20.224
- a significant amount of money in underutilized facilities. And that takes care of my questions. That

00:53:20.224 --> 00:53:21.374
- was more of a

00:53:21.986 --> 00:53:34.908
- The question is, how do we not have? We're working on it. OK, any other questions on the claim registers

00:53:34.908 --> 00:53:47.708
- for both October 23rd and November 6th before we get a motion? One question on the November one on page

00:53:47.708 --> 00:53:50.046
- 639 of the packet.

00:53:50.658 --> 00:53:59.766
- Fund 4445, line 512. The seventh walnut garage taxes, which I know we've reviewed this before contractually,

00:53:59.766 --> 00:54:08.289
- were obligated to pay the property taxes for the seventh and walnut garage. And I guess this would be

00:54:08.289 --> 00:54:11.966
- a question for Jeff. When is that paid off?

00:54:14.498 --> 00:54:21.464
- so we can... When is the debt paid off? Yeah, when is the debt paid off? At that point, then the parking

00:54:21.464 --> 00:54:28.297
- garage, whatever portions is taxable. The walnut or the mercury? Walnut, yeah. This one is the seventh

00:54:28.297 --> 00:54:34.997
- and walnut at five. The walnut is February of 31. 31, so we're getting closer. Getting closer. Yeah,

00:54:34.997 --> 00:54:42.494
- because at that point, then those tax dollars will become part of the revenue that will come back into the city.

00:54:44.482 --> 00:54:51.025
- I mean, it'll be interesting to see what happens. The documents are really complicated, and I have not

00:54:51.025 --> 00:54:57.504
- yet. I mean, we're definitely going to need legal assistance to understand exactly what the impact is

00:54:57.504 --> 00:55:03.857
- once we pay off those leases. OK. Thank you. But it is definitely on my radar. OK. Appreciate that.

00:55:03.857 --> 00:55:10.590
- Thank you. OK. If there are no other questions, I will ask for a motion for both of these claims, please.

00:55:11.906 --> 00:55:18.869
- I'll move approval of claims for October 23rd and November 6th. Second. Move a first and a second. All

00:55:18.869 --> 00:55:25.630
- in favor say aye. Aye. Any opposed? Passes unanimously. Thank you. Next item in the agenda, we also

00:55:25.630 --> 00:55:32.593
- have two payroll registers, one from October 16th, the other from October 30th. I will also invite you

00:55:32.593 --> 00:55:39.353
- to ask questions about both and entertain a motion for both at the same time. I'll make a motion to

00:55:39.353 --> 00:55:41.246
- approve of payroll records.

00:55:41.410 --> 00:55:48.918
- registers as presented. Second. First and a second all in favor say aye. Aye. Any opposed passes unanimously.

00:55:48.918 --> 00:55:55.879
- Now we have the minutes from three different meetings two executive sessions one from October 5th the

00:55:55.879 --> 00:56:02.909
- other from October 19th and then the regular meeting minutes from October 19th. I will also invite any

00:56:02.909 --> 00:56:08.574
- questions about these collectively as well as a motion that would cover all three.

00:56:11.074 --> 00:56:19.857
- I'll move approval of minutes for October 5th, October 19th in both cases. Second. We've got a first

00:56:19.857 --> 00:56:28.901
- and a second. All in favor say aye. Aye. Any opposed? Passes unanimously. Thank you. Okay, we are going

00:56:28.901 --> 00:56:37.597
- to a presentation on proposed product delivery system for 714 South Roger Street. Who would like to

00:56:37.597 --> 00:56:38.814
- present that?

00:56:39.106 --> 00:56:50.505
- and then there may be others jumping in. To start, I just wanted to kind of go back to the initial thought

00:56:50.505 --> 00:57:01.690
- of how the readaptive use of 714 building would work for the Bloomington Police Department headquarters.

00:57:01.690 --> 00:57:06.910
- And we originally started looking at the process

00:57:07.394 --> 00:57:17.991
- which would include an owner's representative who would be looking out for the RDC cities and Bloomington

00:57:17.991 --> 00:57:28.588
- police departments best interest in this. And then a CMC, which is a construction manager as constructor.

00:57:28.588 --> 00:57:37.086
- There are benefits to a CMC that such as at some point during the process they would

00:57:37.218 --> 00:57:46.881
- could end up with a guaranteed maximum price. And then if there's overruns or issues with subcontractors,

00:57:46.881 --> 00:57:56.727
- things like that, the construction manager would be the one that would have to deal with all that. However,

00:57:56.727 --> 00:58:06.846
- during the process of looking for an owner's representative, we now got some proposals of people familiar with

00:58:07.362 --> 00:58:18.228
- Bloomington and the project, yet none of the proposals were well-suited for what the RDC's needs were

00:58:18.228 --> 00:58:28.881
- in the project. So during discussions about that, it was brought up by a department head, a contact

00:58:28.881 --> 00:58:35.806
- that they had, or company they had heard about, Garmong. And so,

00:58:36.194 --> 00:58:46.640
- When that was mentioned, I perked up my ears because I had a contact at Garmong that I had previously

00:58:46.640 --> 00:58:57.188
- worked with and was familiar with. His name's Dan Zerner. And so I contacted Dan and asked him if they

00:58:57.188 --> 00:59:05.790
- would be interested in being owner's representative and give us a proposal on that.

00:59:05.954 --> 00:59:19.016
- And he asked to meet. And so Anna Killian Hanson and I met with him outside the 714 Roger Street building.

00:59:19.016 --> 00:59:30.614
- And prior to that, I had given him the reports that we had to date on the building. And during

00:59:30.614 --> 00:59:34.398
- our discussions, he brought up

00:59:35.042 --> 00:59:47.636
- idea of, instead of using an owner's representative and a CMC, of using a CMA instead, which a CMA is

00:59:47.636 --> 01:00:00.847
- a construction manager as an agent. So they act as an owner's representative. They aren't the constructor,

01:00:00.847 --> 01:00:04.798
- so they aren't contracting with

01:00:05.250 --> 01:00:17.379
- any of the subs they are so there's no financial benefit to them in any of those financial or contractual

01:00:17.379 --> 01:00:29.737
- obligations their whole financial interest would be for the city and so that therefore that would eliminate

01:00:29.737 --> 01:00:35.230
- the need of an owner's representative there are

01:00:35.362 --> 01:00:47.457
- pros and cons, which I'll talk about in a minute, but after he spoke with Anna and I, we felt that this

01:00:47.457 --> 01:00:59.087
- sounded like a good approach, and so he met with a larger city team to explain the process, and the

01:00:59.087 --> 01:01:03.390
- larger city team also felt that this

01:01:03.554 --> 01:01:13.943
- looked like a way to go, but felt that we needed to reach out to some other people as well. Now, CMC,

01:01:13.943 --> 01:01:23.822
- there's a statute that requires you to go through a request for proposal process. For an owner's

01:01:23.822 --> 01:01:29.118
- representative, that's not required. It's services.

01:01:29.250 --> 01:01:42.666
- and for a CMA that's not required its services. Yet, for due diligence purposes, the team felt that

01:01:42.666 --> 01:01:57.022
- it was important to reach out to others that are known CMA vendors and to get proposals from them as well.

01:01:58.114 --> 01:02:10.315
- looking at those proposals compared to the information that Garmong had presented in the meeting with

01:02:10.315 --> 01:02:22.397
- us and he had actually presented a proposed agreement. The Garmong group was less, their pricing was

01:02:22.397 --> 01:02:24.670
- less. They were at

01:02:25.058 --> 01:02:33.909
- 2% for the construction management, 2% of construction costs. We received two proposals from the several,

01:02:33.909 --> 01:02:42.509
- I think there was six or seven that was requested from maybe. And one of the others was 2.25%. And the

01:02:42.509 --> 01:02:51.193
- other had a very interesting way that they laid everything out. And when you kind of added it together,

01:02:51.193 --> 01:02:54.366
- it looked like it was more like 2.9%.

01:02:54.530 --> 01:03:03.115
- The two and a quarter percent company also required or said there would be additional costs for any

01:03:03.115 --> 01:03:11.957
- pre-construction work. So any of the design work that they would do with the architects and, you know,

01:03:11.957 --> 01:03:20.542
- making sure that they had value engineering through the process, all of that would be an additional

01:03:20.542 --> 01:03:24.062
- cost that they did not give a price for.

01:03:24.162 --> 01:03:40.662
- Garmong has offered to do those services for not to exceed fee of $20,000. So anyway, as a short discussion

01:03:40.662 --> 01:03:53.342
- of the difference between the two, again, the major benefit to the city of the CMA

01:03:53.794 --> 01:04:05.120
- is that the CMA is again looking out for the best interest of the city. They have no benefit, financial

01:04:05.120 --> 01:04:16.229
- interest at all in the contracts. So their interest is solely in getting the best product at the best

01:04:16.229 --> 01:04:22.110
- price and looking out for the city. And the owner has

01:04:23.714 --> 01:04:34.654
- using this CMA approach, you do not get the guaranteed maximum price, but you have to understand how

01:04:34.654 --> 01:04:46.136
- the guaranteed maximum price is set, and that isn't set until bidding is complete, and then a contingency

01:04:46.136 --> 01:04:52.094
- is added to that. Well, once the bidding is completed,

01:04:52.962 --> 01:05:01.715
- complete and they had a contingency, that contingency would actually be the city's contingency and not

01:05:01.715 --> 01:05:10.213
- theirs with the CMA. So the city would be controlling that contingency. So there's a benefit there.

01:05:10.213 --> 01:05:19.052
- Another benefit is that the CMA would divide out the bidding into prime contracts. So instead of having

01:05:19.052 --> 01:05:22.366
- one general contractor, there would be

01:05:22.818 --> 01:05:32.786
- four or five, three, four, five prime contractors that where you would divide out the scope of work

01:05:32.786 --> 01:05:43.252
- to fit their trades. And therefore you can reduce the number of markups from subs by doing that as well.

01:05:43.252 --> 01:05:51.326
- So their cost savings there. So Dan had talked to us and knowing that the budget

01:05:51.522 --> 01:06:00.718
- this project is so tight that was the first thing he said when we met is that it's going to be very

01:06:00.718 --> 01:06:10.190
- difficult to do this project with this budget and so you need to find a way to save as much as you can

01:06:10.190 --> 01:06:20.030
- and going the CMA route is a route that could save you money that could be put into the project instead of

01:06:20.162 --> 01:06:35.380
- fees and other costs. So let me see what I'm missing here. The other benefit to the city is that the

01:06:35.380 --> 01:06:46.078
- city, you know, the CMC, when they, yes, they would have the contracts

01:06:46.402 --> 01:06:56.407
- And they would be responsible for the subcontractors. If there's failures to do the work and inefficiencies,

01:06:56.407 --> 01:07:05.586
- they would be responsible for that. Yet, they'd have to deal with that. But that doesn't mean there

01:07:05.586 --> 01:07:14.398
- wouldn't be those issues. You might have those same issues even if the city held the contracts.

01:07:14.818 --> 01:07:24.856
- But if the city held the contracts, the city wouldn't be in control of dealing with that directly. And

01:07:24.856 --> 01:07:34.796
- you still have the construction manager that's looking out after that day after day after day, making

01:07:34.796 --> 01:07:44.542
- sure to catch those things as they were to happen to try to head them off at the pass, so to speak.

01:07:44.866 --> 01:07:55.218
- pros and cons of each one. It did appear, at least to me, that the CMA would give more money to the

01:07:55.218 --> 01:08:05.881
- project and more flexibility as well. Because the CMA, we could, once you have your project and you're

01:08:05.881 --> 01:08:13.438
- guaranteed a master in the process, you have your project. With the CMA,

01:08:13.538 --> 01:08:22.597
- If you start down the road and find out that there's an issue and you need to pivot, you can pivot because

01:08:22.597 --> 01:08:31.487
- you've got that flexibility. You don't have a contract for the entire thing. So there's some flexibility

01:08:31.487 --> 01:08:39.954
- there. I did invite Dan Zerner to join us. He understands that you guys are just hearing about this

01:08:39.954 --> 01:08:42.494
- for the first time, so you've

01:08:42.754 --> 01:08:52.034
- You're not going to make any decisions tonight on whether you want to do a CMC or CMA or whatever, but

01:08:52.034 --> 01:09:01.405
- he can help explain the differences between the two, how a CMA works best for this project. He can tell

01:09:01.405 --> 01:09:09.694
- you a little bit about his company. If you decided to do a CMA route, we wouldn't recommend

01:09:09.794 --> 01:09:20.794
- Garmong is to go with, again, we did due diligence in looking for the owner's rep, which was not suitable.

01:09:20.794 --> 01:09:31.280
- We did our due diligence with looking for the CMA. Again, even though we heard from Dan first, we did

01:09:31.280 --> 01:09:39.710
- go and seek other proposals. And Garmong led by not only pricing, but experience.

01:09:39.842 --> 01:09:49.121
- And so we wouldn't recommend him if you chose to go that route. But again, he understands he's not here

01:09:49.121 --> 01:09:58.044
- to, that you're not gonna vote on a contract for it tonight, that you're not even possibly choosing

01:09:58.044 --> 01:10:05.182
- a direction to go. But we're trying to help you with understanding the process.

01:10:05.346 --> 01:10:14.057
- And another thing I meant to mention with the CMA is since the contracts are with the city, it's a much

01:10:14.057 --> 01:10:22.685
- more transparent approach. With the CMC, they hold the contracts. You don't necessarily see them. It's

01:10:22.685 --> 01:10:31.815
- not a public bidding process. You don't know what you're getting for what. So there's some more transparency

01:10:31.815 --> 01:10:35.166
- that you get when the city is doing the

01:10:35.426 --> 01:10:43.448
- the bidding. So I think that was the last point I want to try to get in there. But anyway, this is Dan

01:10:43.448 --> 01:10:51.703
- Zerner from Garmong. And I'd, again, like for him to start with adding anything to the difference between

01:10:51.703 --> 01:11:00.192
- CMA and CMC and why CMA would work best for this particular project. A quick question. When you're referring

01:11:00.192 --> 01:11:01.438
- to CMA and CMC,

01:11:01.602 --> 01:11:09.068
- CMC or construction management as constructor. That's the CNT2 thing. And then we're also looking at

01:11:09.068 --> 01:11:16.756
- it from an owner's rep standpoint that we've went out to previously. If we're talking about two, should

01:11:16.756 --> 01:11:24.222
- we talk about the third also so we get a good understanding? With an owner's rep, you still need the

01:11:24.222 --> 01:11:29.470
- construction manager as constructor. We would just have an owner's rep

01:11:29.890 --> 01:11:39.541
- work with the construction manager to represent our interest, to make sure our interest was represented

01:11:39.541 --> 01:11:48.821
- all the way through. So owner's rep is not a third mechanism. It would be used with the CMC. So the

01:11:48.821 --> 01:11:58.564
- CMA is a way to combine the construction management part with the owner's representative part. So during

01:11:58.564 --> 01:11:59.678
- the initial

01:12:00.034 --> 01:12:08.053
- the initial pre-construction, which would be from, depending on how early the CMA was brought on, from

01:12:08.053 --> 01:12:16.384
- helping select the architect engineers to, through the bidding process, those services would be considered

01:12:16.384 --> 01:12:24.170
- owner's representative type services. And then the construction manager services would kick in, but

01:12:24.170 --> 01:12:27.518
- it would still be as an agent for the city

01:12:27.906 --> 01:12:34.102
- and not as a constructor, but they would do all the things that the construction manager as construction

01:12:34.102 --> 01:12:40.179
- would do. And then the architectural and the engineer from their construction management. You wouldn't

01:12:40.179 --> 01:12:46.198
- include that. That would be part of the CMA. You will have an architect and an engineer. Right. We'll

01:12:46.198 --> 01:12:52.335
- have an architect and engineer, but any construction management services would then be transferred from

01:12:52.335 --> 01:12:55.934
- architect and engineer into a construction management agent.

01:12:56.034 --> 01:13:03.109
- Okay, you wouldn't have extended services as you and I know of an architect's contract. Okay. Good question.

01:13:03.109 --> 01:13:09.600
- Thank you. So I guess if you're looking at me, it's my time. First of all, I want to thank Dana and

01:13:09.600 --> 01:13:16.221
- Anna and Anna for all the conversations we've had about this project to this point. Second, as I told

01:13:16.221 --> 01:13:20.894
- the other group, my kids tell me that I'm not who are now in their 40s.

01:13:21.058 --> 01:13:26.299
- Tell me that I'm not sucking up, but I do want you to know that I reviewed all your bios today. And

01:13:26.299 --> 01:13:31.802
- how humbled I am to be a part of this group and be here this evening and thank you for this opportunity.

01:13:31.802 --> 01:13:37.410
- Third, I want to assure you that there is no pressure on my part here. You should know that I was actually

01:13:37.410 --> 01:13:42.703
- the liaison to the City of Lawrence Redevelopment Commissioner for Mary Collier for four years. So I

01:13:42.703 --> 01:13:46.686
- understand exactly what you're going through and the role you have to play.

01:13:47.618 --> 01:13:54.418
- And I'm here primarily to provide clarity and to answer your questions. And if the opportunity comes,

01:13:54.418 --> 01:14:01.284
- I would be glad to serve you. I would be the guy serving you as your lead in this project. It wouldn't

01:14:01.284 --> 01:14:08.350
- be somebody any less senior. I am the most senior person at Garmont. I've been there 26 years. I probably

01:14:08.350 --> 01:14:14.750
- run close to a billion dollars in projects. Just to give you some idea, something very complex.

01:14:15.778 --> 01:14:21.368
- This is an extremely complex project as we're looking at it today. When you look at the Hopewell component

01:14:21.368 --> 01:14:26.697
- with all the utilities and stormwater and coordination that goes on there, the smallness of the site,

01:14:26.697 --> 01:14:32.026
- the complexities that were going to occur, I might kind of equate it with a project you probably know

01:14:32.026 --> 01:14:37.303
- about. But every time you go through Martinsville, if you make a left and go up like you used to and

01:14:37.303 --> 01:14:40.542
- you pass the south central RMC building, that was my project.

01:14:40.674 --> 01:14:46.535
- That was a seven-year development project to put Watt Auto Band on 15 acres in a seven-acre spot. It

01:14:46.535 --> 01:14:52.337
- had the primary Duke service line, the city split the middle of that project. It had the main sewer

01:14:52.337 --> 01:14:58.140
- line for the entire city of Martinsville come right down through the center of that project. We had

01:14:58.140 --> 01:15:03.943
- massive amounts of work to do to prepare that project and keep them in full operation while we were

01:15:03.943 --> 01:15:09.920
- there. So I am familiar with very difficult projects. I don't say that to be arrogant, but that's just

01:15:09.920 --> 01:15:10.558
- what I do.

01:15:12.258 --> 01:15:18.636
- I want to talk a little bit about the delivery systems in a different context and share with you a little

01:15:18.636 --> 01:15:24.834
- bit about Garmong and the process. When I came to Garmong in 2000, we were a $12 million company. This

01:15:24.834 --> 01:15:30.971
- year we'll do $500 million. We have offices now in Fort Wayne, Indianapolis, Terre Haute, Evansville,

01:15:30.971 --> 01:15:37.289
- and Savannah, Georgia. The Savannah, Georgia offices will do nothing but build prisons. That's its whole

01:15:37.289 --> 01:15:38.974
- focus, is to build prisons.

01:15:39.938 --> 01:15:46.280
- Our projects range in size right now, a project of $1.2 billion. We're finishing up for the state of

01:15:46.280 --> 01:15:52.685
- Indiana at a new prison that's a square mile under roof up in Westfield to $2 and $3 million. I would

01:15:52.685 --> 01:15:59.278
- say our sweet spot right now is somewhere in the $75 million project range. It's probably where we spend

01:15:59.278 --> 01:16:05.934
- a lot of time, but we do a lot of projects between $25 and $75 million. Delivery system-wise, it's really

01:16:05.934 --> 01:16:06.750
- interesting.

01:16:07.170 --> 01:16:12.923
- We do a lot of CMC work. It might surprise you to know that when the state, that's a relatively new

01:16:12.923 --> 01:16:18.792
- statute for yous that don't know it. It was about five years ago that the state of Indiana passed the

01:16:18.792 --> 01:16:24.603
- CMC legislation for public works. Prior to that, you could not do CMC in Indiana. So it's relatively

01:16:24.603 --> 01:16:30.471
- new. When that happened, Purdue University actually hired us to write their operations manager on CMC

01:16:30.471 --> 01:16:32.830
- to build their $200 million honors dorm.

01:16:34.114 --> 01:16:40.842
- So we have a tremendous amount of CMC experience. And then most of you that have been around know that

01:16:40.842 --> 01:16:47.962
- the latest buzzword is BOT. That's the new buzzword. And so we right now probably have, I'm just speculating

01:16:47.962 --> 01:16:54.624
- off the top of my head, we probably have 200 million in CMC work, 200 million in BOT work, and I have

01:16:54.624 --> 01:17:01.483
- about 150 million in CMA work. For the BOT, if you could explain that, please. Sure, I'd love to. That's

01:17:01.483 --> 01:17:04.030
- a build, operate, transfer. Thank you.

01:17:04.482 --> 01:17:09.189
- It originally started out with jails and hospitals and all where you would build it. You'd get it up

01:17:09.189 --> 01:17:13.989
- to fully operational and then you'd transfer the ownership over and you'd carry all the carrying costs

01:17:13.989 --> 01:17:18.649
- for the project as you went through the build operating procedure. What it's really become is a way

01:17:18.649 --> 01:17:23.449
- to get around the old bidding statutes because you can hire anybody you want to do the project. That's

01:17:23.449 --> 01:17:28.062
- really what BOT does for you. It allows you to hire anybody you want as a team to do your project.

01:17:29.058 --> 01:17:34.755
- And but most of the time now because they found out they had to pay the carrying costs one way or the

01:17:34.755 --> 01:17:40.452
- other either at the end or during the beginning. I would say a lot of that's transferring back to CMC

01:17:40.452 --> 01:17:46.094
- now in that regard. So I can talk to you equally about delivery systems and Garmont would be pleased

01:17:46.094 --> 01:17:51.847
- to build your project any way you want as would numerous other people. So I'm not prejudiced. I'd like

01:17:51.847 --> 01:17:57.488
- to say I'm not prejudiced to delivery systems. We'll deliver this project any way you'd like to have

01:17:57.488 --> 01:17:58.270
- it delivered.

01:17:58.434 --> 01:18:04.578
- If you go to CMC, then you have to turn around and go back out for proposals. And you get proposals

01:18:04.578 --> 01:18:11.090
- from teams to come back in, and you evaluate those proposals. As Dan already mentioned, CMA is considered

01:18:11.090 --> 01:18:17.479
- a professional service, because just like any engineering firm, we are responsible to you and you only.

01:18:17.479 --> 01:18:23.807
- We are a single service provider with the full responsibility of serving you. Some people like to say,

01:18:23.807 --> 01:18:26.142
- well, you don't have any risk of CMA.

01:18:26.754 --> 01:18:32.325
- because you don't have any money at stake. Well, I like to say I have the biggest risk, because my reputation

01:18:32.325 --> 01:18:37.389
- is 100% at stake with CMA. If I don't deliver, and you tell every other city in town that I didn't,

01:18:37.389 --> 01:18:42.707
- or in the county state I don't deliver, that's probably the biggest risk a guy could have in his career.

01:18:42.707 --> 01:18:47.873
- In my knowledge, in the 26 years I've been here, has every project gone perfect? No, but anybody that

01:18:47.873 --> 01:18:52.937
- tells you there will be such a thing as a perfect project, specifically this project, there's going

01:18:52.937 --> 01:18:54.558
- to be issues with this project.

01:18:55.810 --> 01:19:02.231
- I think to have a guy that's in your corner that has the reputation I do to fight for you like I fight

01:19:02.231 --> 01:19:08.651
- for you, and the team I will have behind me, which is second to none in Indiana, our typical schematic

01:19:08.651 --> 01:19:15.010
- phase estimate, for example, which is only at about 15, 20% design, is usually within 3% of the final

01:19:15.010 --> 01:19:21.306
- project cost. So one of the things that I think we can do for you is help you get to an early budget

01:19:21.306 --> 01:19:23.550
- and understand where we really are.

01:19:24.674 --> 01:19:30.369
- There's a lot of variables working in this community. This is a great community, and it's because you

01:19:30.369 --> 01:19:36.008
- have so many variables. But I don't have anywhere else, for example, that I'm gonna have to pay a 1%

01:19:36.008 --> 01:19:41.591
- deduct to an art council. That's probably a good thing, but it's coming off the top, right? So when

01:19:41.591 --> 01:19:47.230
- we look at 30 million, we gotta figure out right away, 1% is coming right off that project. And then

01:19:47.230 --> 01:19:49.854
- we have other factors we have to work through.

01:19:50.754 --> 01:19:56.703
- I think there are a lot of ideas we can bring to the table. One of the things that I've already suggested,

01:19:56.703 --> 01:20:01.817
- and I want to thank Anna Dragovich for her work on the RFPs. She's collaborated with me. We

01:20:01.817 --> 01:20:07.655
- made modifications together with the RFP to be sure it was more reflective of what I think some of these

01:20:07.655 --> 01:20:13.214
- issues are. I'm not worried about a contract, but I've already agreed to sit with Anna and her team

01:20:13.346 --> 01:20:18.818
- on the interviews to be sure that we ask the architects the right questions to drill down and get to

01:20:18.818 --> 01:20:24.453
- you what you need to do to have the best architect and engineer, because that's going to influence this

01:20:24.453 --> 01:20:30.033
- project dramatically. How do we tie this in? Another thing that's a concern to me that I'll be looking

01:20:30.033 --> 01:20:35.776
- for is we get closer way down the line towards bidding packages. But how do we structure bidding packages

01:20:35.776 --> 01:20:41.302
- to give Bloomington, Monroe County contractors the best opportunity to compete in a world that if the

01:20:41.302 --> 01:20:42.494
- playing field's level

01:20:43.330 --> 01:20:48.885
- Can they compete better than bring somebody outside to do the work? I think it's important to try to

01:20:48.885 --> 01:20:54.495
- make this an economic development project if we can and keep as much of that work in town. So anyway,

01:20:54.495 --> 01:21:00.106
- CMA, in my view, allows me to do a lot of things for you. It allows me to start with the architect on

01:21:00.106 --> 01:21:05.606
- day one and be sure that we're designing the most efficient way to build whatever we need to build.

01:21:05.606 --> 01:21:11.326
- Now, it won't necessarily be true on this as an example, but it's the example that's on top of my head.

01:21:11.906 --> 01:21:17.384
- When you're in engineering architect school, a lot of times you're taught design. For example, a steel

01:21:17.384 --> 01:21:22.916
- engineer will often design a steel by the pound. And so they try to design as light as they can to save

01:21:22.916 --> 01:21:28.394
- money on steel. Or we might look at that and say, you know, if you make that steel two gauges heavier,

01:21:28.394 --> 01:21:33.713
- we need two less bolts in every connection. Two less bolts may save us X amount of labor. Those are

01:21:33.713 --> 01:21:39.192
- the kind of things that we're going to be looking at on your behalf to see how we can do that. Another

01:21:39.192 --> 01:21:40.734
- thing I think is going to be

01:21:41.730 --> 01:21:47.294
- problematic here is the coordinating and scheduling with your adjoining housing project and how the

01:21:47.294 --> 01:21:53.136
- stormwater and utilities all tie in. How do we keep the schedule going? How do we keep the streets clean

01:21:53.136 --> 01:21:58.811
- and not impact? It'd be our job to coordinate all that safety and security that's going to have to go

01:21:58.811 --> 01:22:04.597
- along with that particular section of town as part of the construction project. And the real difference

01:22:04.597 --> 01:22:09.438
- is I'm not going to be looking at as a CMC, I'm looking at how do I keep my profit up?

01:22:11.490 --> 01:22:16.952
- while I'm doing all those things for you, as a CMA, that's not a concern to me. My concern is 100% your

01:22:16.952 --> 01:22:22.466
- interest, and it's our job to keep everybody in line to those interests. Another thing I think is really

01:22:22.466 --> 01:22:27.770
- important, because you all haven't seen my proposed contract to the city that Dana and I have worked

01:22:27.770 --> 01:22:33.337
- out, my proposed contract says you can cancel my contract at any point in time with no penalty. No cause,

01:22:33.337 --> 01:22:38.798
- no penalty, no reason. You can cancel it. If at any point in time you don't think I'm doing a good job,

01:22:38.798 --> 01:22:41.214
- I think you need to be able to get rid of me.

01:22:42.882 --> 01:22:48.498
- But also what that does, I think, let's say we went four months down the road or five months down the

01:22:48.498 --> 01:22:54.058
- road, and we all decided after all the work we're doing, this project just isn't going to fly. For a

01:22:54.058 --> 01:22:59.784
- whole bunch of reasons, this old building, we just can't get it to where we want economically. We could

01:22:59.784 --> 01:23:05.454
- kill my contract and turn around and build a new building, either under CMA or CMC, and start all over

01:23:05.454 --> 01:23:11.070
- with it, with hardly any financial consequence to you other than what we spent in preliminary design.

01:23:12.258 --> 01:23:18.625
- So I think it offers you a tremendous amount of flexibility as CMA. I have a tendency to talk way too

01:23:18.625 --> 01:23:24.930
- much. And when I do, I get in trouble. I know that you've had a lot of real estate experience, John.

01:23:24.930 --> 01:23:31.359
- I've known Randy for a long time. Our companies have worked together. But I would rather at this point

01:23:31.359 --> 01:23:37.726
- stop and just breathe for a minute and take your questions, because I'm sure you got a bunch of them.

01:23:40.770 --> 01:23:48.135
- to ask a question about how your fee structure works. Sure. You have a flat fee structure, at least

01:23:48.135 --> 01:23:55.499
- to my understanding from what Mr. Kerr said, that would be for owner's representative services. And

01:23:55.499 --> 01:24:02.937
- then you're also describing where there'll be additional fees for the actual construction management

01:24:02.937 --> 01:24:10.302
- component. May I help you with that? Yes, please. So there's two technical terms that we live with.

01:24:10.818 --> 01:24:16.485
- are pre-construction and construction. So we have offered you a pre-construction phase fee, which is

01:24:16.485 --> 01:24:22.601
- way below market rate. And if I were you, I'd be suspicious of that. That's why I'm asking you the question.

01:24:22.601 --> 01:24:28.323
- Why would he possibly do that? Well, one is I think we need to earn your respect and earn your way to

01:24:28.323 --> 01:24:33.822
- the table and take the risk away from you in that pre-construction phase. Randy understands that.

01:24:34.274 --> 01:24:40.898
- For $20,000, it's going to cost us $150,000 to live that pre-construction phase, right? But we're also

01:24:40.898 --> 01:24:47.328
- going to charge you 2% for construction of a $30 million project. So 2% of $30,600,000 if my math's

01:24:47.328 --> 01:24:54.016
- right. We're willing to give up $100,000 up front to prove that we're as good as we say we are and help

01:24:54.016 --> 01:25:00.318
- you get to a project. Because if there is no project to construct, there is no $600,000, correct?

01:25:01.058 --> 01:25:07.085
- So I'm just being 100% transparent with you, that's the logic that goes into that. But for pre-construction,

01:25:07.085 --> 01:25:12.835
- what we're committing to is we're gonna sit with that architect, we're gonna work all the budget issues

01:25:12.835 --> 01:25:18.531
- out, we're gonna work the scope issues out, we're gonna work all the details that go with construction

01:25:18.531 --> 01:25:24.226
- out, get it to bid, and bid the project for you, all for $20,000. And at the time, and that's a value,

01:25:24.226 --> 01:25:30.142
- by the time you get those bids, we're gonna know exactly what that project's gonna cost, and this is where

01:25:30.882 --> 01:25:36.462
- Internally, we have our own debates about CMA and CMC. Because everybody wants a guaranteed maximum

01:25:36.462 --> 01:25:42.042
- price, and it's sold by a lot of people to municipalities as the greatest thing since sliced bread.

01:25:42.042 --> 01:25:47.790
- But a guaranteed maximum price isn't established until the bids are actually received. It's like going

01:25:47.790 --> 01:25:53.425
- to the back of the grocery store and picking up that gallon of milk for four bucks or whatever it is

01:25:53.425 --> 01:25:56.606
- today. I haven't bought a gallon of milk in a long time.

01:25:57.602 --> 01:26:02.919
- I used to work in a grocery store business, and I remember it at 49 cents. But you grab that gallon

01:26:02.919 --> 01:26:08.715
- of milk and you bring it up front, it's still $4 or whatever it was in the back. So when you're establishing

01:26:08.715 --> 01:26:14.244
- a guaranteed maximum price, they're really not taking the risk that you think they are. Plus, then they

01:26:14.244 --> 01:26:19.615
- add a contingency on top of that. And that contingency, in all fairness, can be negotiated a million

01:26:19.615 --> 01:26:25.038
- ways. It can be all the city's money that you control with a line item. It can be their money. It can

01:26:25.038 --> 01:26:26.846
- be sometimes they have guaranteed

01:26:27.074 --> 01:26:32.491
- savings, where they split the savings costs. What I'm proposing is that we're going to put together

01:26:32.491 --> 01:26:38.179
- the budget as CMA. We're going to know exactly what the cost is, and we're going to decide collectively,

01:26:38.179 --> 01:26:43.867
- as an RDC, as a team, how much contingency within the budget do we have to have to protect our interests

01:26:43.867 --> 01:26:49.392
- to be sure we've got enough money to finish the job. Normally that's, in this market right now, as of

01:26:49.392 --> 01:26:53.726
- all those things are, that's normally five or six percent of total contingency.

01:26:54.434 --> 01:27:00.481
- So a $30 million project, I would want you to have at least 5% put back for contingency items. Now,

01:27:00.481 --> 01:27:06.770
- there's a lot of details in this that we haven't even begun to think about. One of them is called FF&E.

01:27:06.770 --> 01:27:12.818
- But as we go through the pre-con, we have to decide for furniture, fixtures, and equipment. Where's

01:27:12.818 --> 01:27:18.986
- that all going to come from? How much is new? How much is transferred? How do we finance that as part

01:27:18.986 --> 01:27:24.126
- of the project? And you want that in your budget. You don't want that to come later.

01:27:25.154 --> 01:27:30.671
- Those are all details that we will be looking at on your behalf to help drive and manage and program.

01:27:30.671 --> 01:27:36.079
- If you look at the original study of the building, I know just enough to be dangerous, because this

01:27:36.079 --> 01:27:41.596
- is all I've seen. I have studied this inside and out. I've had a long conversation with both Anna and

01:27:41.596 --> 01:27:47.005
- Dana. Anna this morning was, Anna Dragovich was gracious enough to give me an hour on the phone. We

01:27:47.005 --> 01:27:51.710
- talked about the building at length. But I have not even been inside the building yet.

01:27:53.026 --> 01:27:59.131
- But I have a pretty good idea what I'm going to see. This building is almost identical to a building

01:27:59.131 --> 01:28:05.236
- I rehabbed in Terre Haute that was a housing project for Westminster Village in Terre Haute. They're

01:28:05.236 --> 01:28:11.522
- core slab floors, eight foot off the park. We'll probably have to use a VRF or some type of refrigerant

01:28:11.522 --> 01:28:17.929
- flow system to keep the ceiling heights acceptable. We may even have to cut a few of those ceiling panels

01:28:17.929 --> 01:28:23.006
- out if we put dispatch in there, those sorts of things. But I think it can be done.

01:28:23.682 --> 01:28:30.489
- And I understand the value of trying to restore the project. So I'm committed to make this building

01:28:30.489 --> 01:28:37.296
- work right now until we get to a point where at some point the flag just goes up and says, no, this

01:28:37.296 --> 01:28:44.443
- doesn't fly. And I'm not afraid to tell you if I get to that point. But I'm not there yet. I think there

01:28:44.443 --> 01:28:51.454
- is a really, I would call it a 75% chance right now that this is where we want to be. And to that end,

01:28:52.514 --> 01:28:58.107
- We all agreed when we put the RFP out that we took any reference to a new project out. I wanted all

01:28:58.107 --> 01:29:03.868
- the focus by the design teams to be on how can we utilize this building? What are the issues? What are

01:29:03.868 --> 01:29:09.629
- the opportunities? What's the focus? I only wanted to think, for example, that there's an out by going

01:29:09.629 --> 01:29:15.334
- to a new building. I'll give you an example of that. It's not totally accurate, but one of the things

01:29:15.334 --> 01:29:20.983
- I just helped out Hendricks County with, which is my biggest client, is they ran into a problem with

01:29:20.983 --> 01:29:22.046
- an animal shelter.

01:29:22.242 --> 01:29:28.018
- I'm not gonna go through the full story, but the bottom line is they brought a firm out of Pennsylvania

01:29:28.018 --> 01:29:33.961
- that specializes in animal facilities to give an air quality study. And that firm was a firm that designed

01:29:33.961 --> 01:29:39.570
- animal facilities for lilies and phisers and all kinds of laboratory units. And they saw this animal

01:29:39.570 --> 01:29:45.180
- shelter sitting under Henry's County new $70 million jail. We get to build a new animal shelter. And

01:29:45.180 --> 01:29:46.846
- they wrote a scathing report.

01:29:46.978 --> 01:29:52.720
- that made its way to Facebook before the commissioners got it said we believe the air quality might

01:29:52.720 --> 01:29:58.635
- be making our employees sick. You can imagine what that did when it really wasn't true. And so instead

01:29:58.635 --> 01:30:04.377
- of 20 million for an animal shelter, we just finished the total rehab of that building for $750,000

01:30:04.377 --> 01:30:10.177
- and met all the code requirements and standards. I think we can look at this building from that same

01:30:10.177 --> 01:30:15.230
- perspective. What do we have to do? So one of the things that I'm looking at already is

01:30:15.938 --> 01:30:20.942
- It appears to me that the people did this study tried to figure out how to use every corner of the building.

01:30:20.942 --> 01:30:25.532
- I don't think the police department is going to need four floors. I think they may need two floors,

01:30:25.532 --> 01:30:30.307
- two and a half floors. I don't know that answer yet. But I don't think we build out the entire building

01:30:30.307 --> 01:30:35.081
- if they don't need the entire building. I think we do the renovations to the exterior. I think we shell

01:30:35.081 --> 01:30:39.672
- it. We secure it. We make it all right. But then maybe there's an opportunity for the RDC to either

01:30:39.672 --> 01:30:44.446
- A, lease that space to a compatible private entity that would like to be next to the police department,

01:30:44.930 --> 01:30:50.944
- or B, use it for some other services that are adjacent. But I think we have to look at every possible

01:30:50.944 --> 01:30:56.839
- avenue as to how this building is going to be used, what's really required, and what we can afford,

01:30:56.839 --> 01:31:02.794
- and figure that out. The last thing I will tell you, and then I'll try to answer all your questions.

01:31:02.794 --> 01:31:08.984
- Hendricks County, in two weeks, we're going to cut a ribbon on a new highway garage that was $32 million

01:31:08.984 --> 01:31:14.526
- by the architect when I got hired. I got hired because they only had $19 million and $50,000.

01:31:15.554 --> 01:31:23.749
- We're finishing that project at 18,947,100 under where we were in 1950, which was a long way off of

01:31:23.749 --> 01:31:31.206
- 32 million. And we gave the city or the county everything they wanted on 17 acres. I think

01:31:31.206 --> 01:31:40.056
- there's opportunity here to do something really great. I don't know in my mind yet whether it's 30 million,

01:31:40.056 --> 01:31:43.006
- 35 million, 28 million, 42 million.

01:31:43.874 --> 01:31:51.233
- But what we'll be able to do is in very incremental phases consistently, we'll be able to advise you

01:31:51.233 --> 01:31:58.665
- where we are with that. And have you help us and guide us as to how aggressive we want to be or where

01:31:58.665 --> 01:32:06.170
- we want to go. That's all I can tell you is we'll be as transparent and treat you just like you're one

01:32:06.170 --> 01:32:13.310
- of us. That would be my role. That was a long answer to what you asked. I appreciate your answer.

01:32:13.826 --> 01:32:20.114
- I'm still not clear on how you cover your costs by delivering $150,000 worth of pre-development services

01:32:20.114 --> 01:32:26.402
- for $20,000. It's going to come to us out of the back end, out of that 2% on the back end of 30 million.

01:32:26.402 --> 01:32:32.451
- And then the counterpart question is, as you noted, that your terms and conditions would include the

01:32:32.451 --> 01:32:38.979
- ability for the city, if any reason was needed, to terminate the contract. What are the terms of termination

01:32:38.979 --> 01:32:43.710
- then? The terms, you would only owe us for whatever we provided to that point.

01:32:46.498 --> 01:32:53.135
- How many hours per week do you expect based on what you know now, which as you noted is fairly nominal

01:32:53.135 --> 01:32:59.643
- at this point, but how many hours maybe total would you expect for ownership services? Well, once we

01:32:59.643 --> 01:33:06.731
- get to construction, that's a 40 hour week job for more than one person. Right, I'm talking pre-construction,

01:33:06.731 --> 01:33:13.239
- huh? Pre-construction is going to vary. So right now, for example, I have committed to Anna, as long

01:33:13.239 --> 01:33:14.334
- as you all don't

01:33:14.530 --> 01:33:20.869
- shut us down for some reason, whether my contract's in place or not. I've committed to spend a day doing

01:33:20.869 --> 01:33:26.967
- interviews with architectural firms and help be sure we ask the right questions and we get the right

01:33:26.967 --> 01:33:33.005
- firm pinned down for the city. Once we get the architect in place, the architect will start driving

01:33:33.005 --> 01:33:39.103
- that with us providing oversight. I would expect that there would be, one, a meeting every two weeks

01:33:39.103 --> 01:33:42.846
- initially that I would actually be in town for. There will be

01:33:42.946 --> 01:33:49.257
- phone calls and zoom stuff and all in between that, but the architect will start driving that. Once

01:33:49.257 --> 01:33:55.695
- we get down to the schematic phase, which schematic phase means we've got a really rough blueprint of

01:33:55.695 --> 01:34:02.006
- what we want to do. We usually have a floor plan, a site plan, maybe a rendering that puts us where

01:34:02.006 --> 01:34:08.633
- we want. Garmong then will have a team of about two highly skilled estimators that will take three weeks

01:34:08.633 --> 01:34:10.526
- going through that to get you

01:34:11.490 --> 01:34:16.152
- in order of magnitude of what we're talking about to deliver what we're talking about today. And then

01:34:16.152 --> 01:34:20.997
- we have to either say, all right, we're perfect, or we can add something else, which very rarely happens,

01:34:20.997 --> 01:34:25.659
- or no, we need to take something out of the budget to get this back to where we are. Can we take some

01:34:25.659 --> 01:34:30.230
- scope out and yet maintain the integrity of the project where it delivers what you want to deliver?

01:34:30.230 --> 01:34:35.167
- You've been through that a million times. And so that would be the next phase. Once you go to the schematic

01:34:35.167 --> 01:34:39.326
- phase, then the architect goes to what we call seedings, which is a construction document.

01:34:40.450 --> 01:34:45.791
- He starts that phase. We're more involved as we go to CDs because we're looking at all how that's going

01:34:45.791 --> 01:34:50.978
- to fit together. How's it going to get constructed? How's it going to get built? What kind of safety

01:34:50.978 --> 01:34:56.217
- requirements are going to have to be provided in the project? What are logistics of getting materials

01:34:56.217 --> 01:35:01.404
- delivered? What outstreet are we going to have shut down? All that starts to happen in the CD phase.

01:35:01.404 --> 01:35:06.848
- So we'll have, at that point, a project manager sitting with me, besides me, doing that work. And they'll

01:35:06.848 --> 01:35:08.286
- be, at that point, probably

01:35:08.898 --> 01:35:14.461
- 8, 10 hours, 15 hours a week. And then we get to what we call DDs, and that's when CDs are done. DDs

01:35:14.461 --> 01:35:20.189
- are design, I'm sorry, I got it backwards. DDs and then CDs. CDs are construction documents, and that's

01:35:20.189 --> 01:35:25.972
- when we get all the final plans prepared to go to bid. And what we're really looking at, as your partner

01:35:25.972 --> 01:35:31.534
- in that, we're looking as a constructor at those set of documents to try to take out every potential

01:35:31.534 --> 01:35:37.152
- loophole for a contractor to bid that and say it wasn't in the plans. That's where your change orders

01:35:37.152 --> 01:35:37.758
- come from.

01:35:38.338 --> 01:35:43.518
- We're doing everything we can to alleviate change order risk by reviewing those just as if we're going

01:35:43.518 --> 01:35:48.596
- to bid that project. And we'll have more people involved in that time. So I don't know how to answer

01:35:48.596 --> 01:35:53.675
- exactly how many hours are going to be involved, but it's in the hundreds by the time we get through

01:35:53.675 --> 01:35:58.855
- pre-con. My question was really about the pre-development because it's the flat rate, right? The other

01:35:58.855 --> 01:36:04.085
- is actually at least tied to construction costs. I will tell you that that flat rate is a whipping boy.

01:36:04.085 --> 01:36:08.158
- If I was going to set that flat rate, I told Dana initially it was a lot higher.

01:36:08.898 --> 01:36:15.343
- But our company looks at this and says, hey, we have tried to work for the city of Bloomington for years.

01:36:15.343 --> 01:36:21.667
- We work for IU, we work for the community school corporation, we work for everybody else, but we really

01:36:21.667 --> 01:36:27.930
- haven't done much for Bloomington. We're willing to discount this to have a chance to show Bloomington

01:36:27.930 --> 01:36:34.254
- how good we really are. That's really your answer. Thank you for your help with that question. Do other

01:36:34.254 --> 01:36:37.598
- members of the commission have questions you'd like to

01:36:37.922 --> 01:36:50.876
- Yeah, I'd like to segue on to what you were asking. So take me from the construction docs to where we're

01:36:50.876 --> 01:37:03.460
- actually starting to bid the job. I know you're not the GC, so who is going to oversee that function?

01:37:03.460 --> 01:37:07.038
- Of GC? Well, who is going to

01:37:08.034 --> 01:37:13.948
- We will have we will have a full-time project manager and a full-time job site superintendent staff

01:37:13.948 --> 01:37:20.157
- on the job all day every day once construction starts All right, but in the prior to that in the bidding

01:37:20.157 --> 01:37:26.307
- process will have HVAC and plumbers and you know, we put all this goes on We put all that together with

01:37:26.307 --> 01:37:32.339
- the design firm and Garmon will actually write the bidding documents Darman will actually develop the

01:37:32.339 --> 01:37:35.710
- entire bidding book bidding documents. We do that all in

01:37:36.162 --> 01:37:43.082
- So the RDC slash city is not doing that legal work? No, we'll have the entire bidding package put together.

01:37:43.082 --> 01:37:49.937
- And then the other thing is, of course, we'll review it with your bond council and all the people involved

01:37:49.937 --> 01:37:56.985
- to be sure that all the documents tie together. Because the bond people want to be sure that the construction

01:37:56.985 --> 01:38:01.406
- documents and contracts are all set up right. So we review all that.

01:38:05.218 --> 01:38:14.364
- So the contracts are held by the city. Correct. And who in the city specifically is responsible for

01:38:14.364 --> 01:38:23.601
- that? It would be the, of course, with the RDC, because RDC is the owner of the property. But as far

01:38:23.601 --> 01:38:33.021
- as managing the legalities of the contract, it would be the legal department. And then both ANAs would

01:38:33.021 --> 01:38:34.942
- be heavily involved.

01:38:35.106 --> 01:38:42.356
- and as a project manager and it co enhances as the executive director. The other thing is we will provide

01:38:42.356 --> 01:38:49.332
- you, I could have brought you in tonight, I should have, but we will provide you a very comprehensive

01:38:49.332 --> 01:38:56.377
- monthly report of exactly where we are. It'll have photos, budgets, scopes, schedules, updates, you'll

01:38:56.377 --> 01:39:01.438
- get that once a month as an RDC and we're glad to provide that in person.

01:39:02.626 --> 01:39:10.094
- or not, depending on what you want with your meetings. It doesn't take very long, but we will provide

01:39:10.094 --> 01:39:17.855
- that every month. It's a turn of key, John, as far as. Well, I'm actually more concerned about the volume

01:39:17.855 --> 01:39:24.956
- of work and the scope of work for the city and the city staff, and whether they're A, qualified,

01:39:24.956 --> 01:39:26.494
- and B, have the time

01:39:26.850 --> 01:39:32.931
- That's a great question, but they really shouldn't have much because we will actually prepare the contracts

01:39:32.931 --> 01:39:38.674
- for their review. We will prepare all the pay apps on your behalf. We'll review all the invoices that

01:39:38.674 --> 01:39:44.529
- come in from the contracts. We will prepare all the pay apps. We'll consult with the architect, be sure

01:39:44.529 --> 01:39:50.159
- they're in agreement. Mutually together, we'll sign off on the pay apps. So really all the city has

01:39:50.159 --> 01:39:52.862
- to do is process a check and keep the electric.

01:39:56.578 --> 01:40:03.615
- That's all part of our function. When it says construction manager, we are literally responsible for

01:40:03.615 --> 01:40:10.581
- all those aspects. So really, the only difference between an A and a C in at least this scenario as

01:40:10.581 --> 01:40:17.688
- you presented is who? There's two differences. The two differences is, one, the contracts are held by

01:40:17.688 --> 01:40:25.630
- the city instead of the CM. The second difference, as you'll understand, there is not a guaranteed maximum price.

01:40:26.274 --> 01:40:33.906
- But I would like to also, since I do so much of both, I would like to also say that the guaranteed maximum

01:40:33.906 --> 01:40:41.610
- price isn't guaranteed if you change the scope. If you change the scope on a CMC and you want an additional

01:40:41.610 --> 01:40:49.385
- room, different building, price goes up, right? So the guaranteed maximum price thing to me is way oversold.

01:40:49.385 --> 01:40:53.950
- Should be a project without change orders. You understand that?

01:40:57.122 --> 01:41:04.067
- So from my perspective, the one thing that I really ask for out of my consideration is not asking you

01:41:04.067 --> 01:41:10.876
- or baiting you into signing a contract. But if you really decide you want me to help you with these

01:41:10.876 --> 01:41:18.026
- services, which I'm really looking forward to doing, I'm going to tell you one more thing because you'll

01:41:18.026 --> 01:41:25.380
- probably hear it anyway. Anna's heard it. Dana's heard it. I shared it with Randy. 1229 is my last official

01:41:25.380 --> 01:41:26.878
- full-time date going.

01:41:28.738 --> 01:41:35.243
- But I have agreed, because I love Dana and we work together so much, I've agreed with Grandma that I'm

01:41:35.243 --> 01:41:41.684
- going to retain two clients, if you so choose. Hendricks County has asked me to stay in place to 2031

01:41:41.684 --> 01:41:48.189
- because they just gave me $160 million worth of work, continued upon me staying and running it. So I'm

01:41:48.189 --> 01:41:54.504
- going to stay in that capacity for Hendricks, and I've also agreed to stay in capacity and run your

01:41:54.504 --> 01:41:57.662
- project through completion, but you would be only

01:41:57.762 --> 01:42:04.666
- One of two clients I have after the first year. Well, you'll have a ton of time. Yeah, I just I'm type

01:42:04.666 --> 01:42:11.503
- A and I'm worried anyway about not knowing what I'm going to do after I retire, but I'm 71 years old.

01:42:11.503 --> 01:42:18.340
- I've enjoyed this. Eat and breathe it. I've got great clients and great great company. I'm really not

01:42:18.340 --> 01:42:25.245
- anxious to just totally walk out, but I think I gotta start to think in those terms. But but you would

01:42:25.245 --> 01:42:25.982
- be my sole

01:42:26.530 --> 01:42:32.237
- one of the two sole focuses if you decide to do this. But you might as well know that up front because

01:42:32.237 --> 01:42:38.054
- the other thing is I will have a tremendous amount of talent behind me. That's what gives me the comfort

01:42:38.054 --> 01:42:43.650
- to do this. I'll have our operating, I have two men in their 40s that are both Rose-Hulman engineers

01:42:43.650 --> 01:42:49.302
- and licensed engineers that will be involved with me in this project. I'll have a full team of people

01:42:49.302 --> 01:42:55.230
- behind me to help handle this. So I think we can do a good job for you if you decide you want us to do it.

01:42:59.682 --> 01:43:06.816
- Any other questions from commissioners? Question regards to when we look at our overall cost basis,

01:43:06.816 --> 01:43:14.165
- we know what our dollar amount is that we have from an affordability standpoint. 30, 35 millions would

01:43:14.165 --> 01:43:21.513
- have been told. Keep going down. I like your enthusiasm. Yeah, like your enthusiasm. Yeah, yeah. Let's

01:43:21.513 --> 01:43:27.934
- talk 30 plus, including soft. With that, based upon utilization of CMC or CMA, when those

01:43:28.354 --> 01:43:34.183
- Dollars come in based on your estimate, but whatever function. Where are you at if it goes too high?

01:43:34.183 --> 01:43:40.359
- And we either have to cut scope, as you know it, or figure some alternative to drive it down. Alternative,

01:43:40.359 --> 01:43:46.130
- dollar-wise. And when we look at things, not from a GMP standpoint, but when we do it. Well, let me

01:43:46.130 --> 01:43:51.902
- give you some examples. Since you asked a question, open the door. I'm already thinking, all right?

01:43:53.186 --> 01:43:59.420
- Again, I talked about some of the complexities of working in this beautiful city because it is what

01:43:59.420 --> 01:44:05.654
- it is because of what you do, right? But for example, there's discussion of tier four construction.

01:44:05.654 --> 01:44:12.138
- If you don't know what tier four is, that's virtually a bomb shelter. I've built several 911 facilities

01:44:12.138 --> 01:44:18.496
- and EMS facilities. None of them are tier four. I don't know where tier four came from. But to get to

01:44:18.496 --> 01:44:20.990
- tier four is a pretty significant cost.

01:44:21.570 --> 01:44:28.236
- I think we could, what I call, harden it to where there's no way anybody could possibly get hurt in

01:44:28.236 --> 01:44:35.436
- a storm. Structural steel, concrete, all kinds of things. But it may not be a full tier four authorization.

01:44:35.436 --> 01:44:42.302
- We could probably save considerably money that way. There's also in your statutes sustainability laws.

01:44:42.302 --> 01:44:49.502
- Does sustainability mean we have to go for full certification and leave? Or can we just put the sustainable

01:44:49.954 --> 01:44:56.115
- Can we use recycled materials? Can we do a bicycle rack? Can we do other things? But like, for example,

01:44:56.115 --> 01:45:02.098
- in the study, it mentions a green roof. Does anybody have any idea what a green roof costs? And then

01:45:02.098 --> 01:45:08.555
- to maintain it. If I have the flexibility and we have the full continuity and we can have the open dialogue,

01:45:08.555 --> 01:45:14.775
- OK, here's what this costs. Here's what the alternative costs. Those are the kind of discussions, Randy,

01:45:14.775 --> 01:45:19.870
- that you and I built with our whole career that we have to have to control that cost.

01:45:22.370 --> 01:45:27.666
- So that's the only answer I have for you right now. I don't know if it's a good one or not. It's a matter

01:45:27.666 --> 01:45:32.712
- of where we go to from a time frame standpoint. Right. Just say go, no go, and what the overall cost

01:45:32.712 --> 01:45:37.807
- is accordingly. That's right. Because if cost exceeds that, we've got a significant multiple thousand

01:45:37.807 --> 01:45:42.853
- square foot building here. And our affordability may go down. Next question, last question I have in

01:45:42.853 --> 01:45:48.099
- regards to it. When you look at the number of contracts that the city would have to have on this, what's

01:45:48.099 --> 01:45:51.646
- the total number you identify in regards to it? In my mind, it's five.

01:45:53.570 --> 01:46:01.397
- Usually it's mechanical, electrical, a general trades package, site package. So five to six max probably.

01:46:01.397 --> 01:46:09.149
- Now, it might vary. You might say that I'm not totally accurate in that because maybe we want a security

01:46:09.149 --> 01:46:16.755
- controls company. Maybe we want an IT company to come in. So those little minor, what I call ancillary

01:46:16.755 --> 01:46:23.326
- contract, but as far as prime major contracts, I'd say five. All at the same time, yeah.

01:46:23.522 --> 01:46:33.782
- accelerate projects. Yeah, we will have a very accurate bidding process that will get us a project number

01:46:33.782 --> 01:46:42.590
- that we all can live with. And it's just a matter of what we can afford. That's right. OK.

01:46:42.590 --> 01:46:50.430
- Anything else? Any other questions from commissioners? Not like competing firms.

01:46:51.234 --> 01:46:59.410
- distinguish themselves. What would they come in here and say to us? For this role? I'd say they'd probably

01:46:59.410 --> 01:47:07.509
- say much of the same thing. That's a hard question, because anything I sound is arrogant or self-serving.

01:47:07.509 --> 01:47:15.379
- But I don't think there's very many people that do exactly what I do. And that's why you don't see too

01:47:15.379 --> 01:47:18.206
- much CMA. You see very little of it.

01:47:18.562 --> 01:47:24.419
- It's almost non-existent. Almost non-existent. For obvious reasons, the GMP and the state law has changed.

01:47:24.419 --> 01:47:29.893
- But it's all about trust and transparency. And I will share this with you because I don't know that

01:47:29.893 --> 01:47:35.366
- it's ever been done, but I consider this a real tribute. When we started the highway garage project

01:47:35.366 --> 01:47:40.347
- a year and a half ago at Hendricks County, the commissioners passed a resolution that gave

01:47:40.347 --> 01:47:45.985
- me an authorization to spend $50,000 on their behalf for any change order without coming back to them.

01:47:45.985 --> 01:47:47.518
- Now why would they do that?

01:47:48.258 --> 01:47:54.130
- They only meet every two weeks. If I have to shut a project down for two weeks to get a change order

01:47:54.130 --> 01:47:59.944
- authorized, what's that cost? And they trusted me enough to give me that resolution as long as, and

01:47:59.944 --> 01:48:06.281
- I asked them for this, I put a check and balance in that either the county engineer or the county facilities

01:48:06.281 --> 01:48:12.212
- manager had to sign with them. I'm not gonna sign that on my own and put myself out there, right? But

01:48:12.212 --> 01:48:18.142
- it's another example of how we look at how do we control the project. So I think most companies will,

01:48:18.306 --> 01:48:23.647
- talk about themselves as CMs to answer your question because they're constructors, right? But I don't

01:48:23.647 --> 01:48:29.093
- think they understand what it takes to sit at the table and make these hard decisions with you and have

01:48:29.093 --> 01:48:34.590
- these discussions and be so aware of everything that's going on in the project. And again, there's going

01:48:34.590 --> 01:48:40.088
- to be mistakes. But what I say about contractors, and I don't know if I'm really answering the question,

01:48:40.088 --> 01:48:45.534
- but what I say about contractors is when there is a problem, do they become part of the problem or part

01:48:45.534 --> 01:48:47.838
- of the solution? That's the defining thing.

01:48:48.514 --> 01:48:55.468
- And I guarantee you that we'll be part of the solution. Whether it's the solution we like or not, we'll

01:48:55.468 --> 01:49:02.221
- be part of it. But there aren't too many people in Indiana that are really good CMs. There are a lot

01:49:02.221 --> 01:49:09.174
- of CMAs. There are a lot of really good CMCs. You and I can list 10 of them. I don't know if I answered

01:49:09.174 --> 01:49:15.860
- yours. I'm sorry. I just don't know how to answer that one. You gave me some things to think about,

01:49:15.860 --> 01:49:18.334
- and that was the goal. So thank you.

01:49:18.466 --> 01:49:23.991
- If Garmong had a choice and just walked in, would you prefer CMC, CMA, or a contract? If you could just

01:49:23.991 --> 01:49:29.304
- hand us a contract, we'd take CMC all day. And why would we take CMC? That's the question. We could

01:49:29.304 --> 01:49:34.883
- make a lot more money. Because we're going to control the budget. We're going to control the subs. We're

01:49:34.883 --> 01:49:40.408
- going to control the markups to our subs. We're going to control every aspect of the finances. You make

01:49:40.408 --> 01:49:45.827
- more money as a CMC. And we can self-perform. So our own forces can come in and self-perform. We make

01:49:45.827 --> 01:49:47.102
- money off our own soul.

01:49:47.202 --> 01:49:54.429
- So CMC is where we would make the most money. But CMA is where I'm going to be 100% focused on your

01:49:54.429 --> 01:50:01.872
- needs. And if we're really truthful about what this project is right now, this would be very difficult

01:50:01.872 --> 01:50:09.460
- to do CMC with because we don't have enough scope. We've got to define ahead of time, which is why we're

01:50:09.460 --> 01:50:14.302
- out for the RFP with the architect. Yeah, but the architect itself

01:50:14.530 --> 01:50:19.609
- Without a CM sitting with it, in my view, is very dangerous. Because you've seen it a million times.

01:50:19.609 --> 01:50:24.788
- We saw that back to my interest count exam. They got to $32 million in a highway garage. They got only

01:50:24.788 --> 01:50:29.817
- $419 million. Why don't you just design a $19 million to begin with? If that's your budget, control

01:50:29.817 --> 01:50:34.896
- it from the beginning. In your case, you're telling me I got $30 million max. We're going to have to

01:50:34.896 --> 01:50:40.176
- figure out, and we'll figure that out really quick, can we do anything for $30 million? And if we can't,

01:50:40.176 --> 01:50:44.350
- then we've got to figure out what we're going to do then. I will tell you, I just.

01:50:44.514 --> 01:50:50.837
- took one down, it would take a million dollars or more to take this building down. Am I close?

01:50:50.837 --> 01:50:57.759
- Now we know. No. They want more? No. The last bid that we had was while there was other demolition work

01:50:57.759 --> 01:51:04.548
- being done, and it was 250. Yeah, well, I just took one down very similar to this Henry's County, and

01:51:04.548 --> 01:51:11.203
- it was 750. So but anyway, my point to you is you're going to spend a half million to take it down.

01:51:11.203 --> 01:51:14.398
- Wouldn't use that half million in the building,

01:51:15.202 --> 01:51:22.009
- and make everything work, that's good money spent. And I'm not afraid of the project. I think it's exciting.

01:51:22.009 --> 01:51:28.253
- And what a tribute it would be to the community if we could put a police station right next to your

01:51:28.253 --> 01:51:34.560
- beautiful new neighborhood. I think it's fun to work on. But it's not, we're going to have to figure

01:51:34.560 --> 01:51:40.992
- it out pretty quick what the economics are. That's the problem. We have low in support. Right. We have

01:51:40.992 --> 01:51:42.366
- the structural. Yeah.

01:51:42.498 --> 01:51:49.529
- One thing that I did not hear Dan speak about that he shared with us was his experience in public safety

01:51:49.529 --> 01:51:56.493
- buildings. Would you mind sharing that with the RDC? I think maybe you didn't get maybe I did copy you.

01:51:56.493 --> 01:52:03.256
- I think I copy you and then I sent them a list of all the police stations. I know that list has gone

01:52:03.256 --> 01:52:10.220
- out. I know you got it. I know the chief got it. There's there's probably 1415 police stations we built

01:52:10.220 --> 01:52:11.358
- in recent times.

01:52:11.970 --> 01:52:18.752
- And some of those were renovations. The White County, we just did the community corrections facility

01:52:18.752 --> 01:52:25.601
- up there in a Bayer Pharmaceutical Office building that was a major gut in rehab on a 1950s building.

01:52:25.601 --> 01:52:32.315
- Of the 32 jails built in Indiana in the last 10 years since the Level 6 legislation came out of the

01:52:32.315 --> 01:52:39.232
- legislature, we built 28 of those 32. And the only reason I mention jails is because most of them have

01:52:39.232 --> 01:52:41.246
- a Sheriff's Office component.

01:52:42.530 --> 01:52:50.444
- Sheriff's Office component for a lot of times to duplicate what we would do in a police department.

01:52:50.444 --> 01:52:58.438
- How many of these are new? 28 are new construction versus rehab? On the jails, I'd say 10% or 10 out

01:52:58.438 --> 01:53:06.352
- of 28 are new and the rest were rehabs and additions. I feel like I've taken too much of your time,

01:53:06.352 --> 01:53:10.942
- but I am really humbled by how much time you've given me.

01:53:13.058 --> 01:53:20.224
- Any other questions? Dana or Anna, what do you need from us this evening? Or is this an opportunity

01:53:20.224 --> 01:53:27.462
- for us to just listen? I'm sorry? Is this an opportunity for us to just listen and ask questions, or

01:53:27.462 --> 01:53:34.844
- do you need something from us? Not at this time. Yeah. I don't have anything in front of you. This was

01:53:34.844 --> 01:53:41.150
- just to introduce you to this type of delivery system, and to introduce you to Garmont,

01:53:41.282 --> 01:53:48.359
- for you to take it under consideration, not asking you for anything tonight. We have given Dana an agreement.

01:53:48.359 --> 01:53:54.987
- So you know, and for me, if I'm really going to do a good job for you, the only thing I request is you

01:53:54.987 --> 01:54:01.485
- get me on board. It's not going to cost anything, all right, $20,000. Get me on board as fast as you

01:54:01.485 --> 01:54:08.241
- can so when we hire that architect, I'm sitting right with him day one. That's what I really appreciate.

01:54:08.241 --> 01:54:10.750
- Based on what you said, last question.

01:54:11.682 --> 01:54:19.587
- Can we still get a GMP? No, not under this delivery system. Not under this delivery system. And just

01:54:19.587 --> 01:54:27.571
- for reference, those A&E bids are due back on Friday, I believe it is, November 6th. Yeah. So I think

01:54:27.571 --> 01:54:35.554
- Anne and I discussed and she set some target dates. And so I think our goal would be for the December

01:54:35.554 --> 01:54:40.094
- meeting to have that decision in front of their proposal.

01:54:40.866 --> 01:54:46.576
- I think maybe staff needs to discuss, but my personal preferred would be the next RDC meeting. It's

01:54:46.576 --> 01:54:52.630
- November 16th. 16th. And we've said a couple of days where we can make that happen. All right. Appreciate

01:54:52.630 --> 01:54:58.397
- it. Thank you. Thank you very much. Thank you, Dave. Are you going to stay around for any reason, or

01:54:58.397 --> 01:55:04.507
- may I leave? You may leave. All right. We've got new business to start with. I've seen enough RDC business

01:55:04.507 --> 01:55:10.846
- in my career. I think I can stay for the rest of it. Thank you for what you do. Thank you, Dave. Thanks, Dave.

01:55:12.514 --> 01:55:19.967
- Okay. I do just want to point out that I believe that the agenda was amended. Number six was added and

01:55:19.967 --> 01:55:27.203
- A under seven are the same thing. So please feel free to skip A. Thank you. Seven A. I'm just going

01:55:27.203 --> 01:55:34.656
- to ask because we've been in meeting for almost two hours now. We are starting a new business of which

01:55:34.656 --> 01:55:42.398
- we've got, you know, almost a dozen items. I'm just going to ask our DC commissioners or staff if you need

01:55:42.530 --> 01:55:50.310
- a five minute break, I'm happy to do that. I just wanted to open that possibility if anybody would like

01:55:50.310 --> 01:55:58.315
- to request it. I would like to take that opportunity. Okay, so it is now 6.56. Is five minutes sufficient?

01:55:58.315 --> 01:56:05.871
- Do you need more? Or would you think more? I'm hopeful for five minutes. Okay, well, that's our goal

01:56:05.871 --> 01:56:07.966
- is five minutes. Thank you.

01:56:08.354 --> 01:56:15.197
- Awesome. Okay. Reconvening the RDC meeting for new business. Resolution 2682, determination of annual

01:56:15.197 --> 01:56:22.309
- spending plan for calendar year 2027. Who would like to speak to that? Great. Thank you very much. Again,

01:56:22.309 --> 01:56:29.219
- I'm going to be introducing Justin Chang from Reedy. But this is the second of our annual requirements

01:56:29.219 --> 01:56:35.928
- that we're reporting that we're going to be addressing tonight. And this one you will actually vote

01:56:35.928 --> 01:56:38.142
- on. So I'm going to go ahead and

01:56:38.242 --> 01:56:47.365
- share the detail of the spreadsheet that was provided in the packet. All right, so we're going to go

01:56:47.365 --> 01:56:56.579
- ahead, Justin. Yeah, so this is similar spending plan that we completed last year. This is the second

01:56:56.579 --> 01:57:00.734
- one. We have to do new reporting requirement.

01:57:01.474 --> 01:57:10.108
- Just really just here to answer any questions that you guys may have, but to preface these numbers before

01:57:10.108 --> 01:57:18.905
- you guys go into the questions, is that we try to put as much in there as possible to avoid the possibility

01:57:18.905 --> 01:57:27.050
- of having to come back and do another test fitting plan. Because why pay us twice when you can only

01:57:27.050 --> 01:57:30.878
- pay us once, right? We're here now, why today?

01:57:31.010 --> 01:57:37.791
- And just for for just letting you guys know the process is if we do overspend in any of these areas

01:57:37.791 --> 01:57:44.979
- so the big ones are the bolder ones like debt payments capital expenditures we have professional services

01:57:44.979 --> 01:57:51.827
- even if the total spending next year is under the total for all these categories if any one of those

01:57:51.827 --> 01:57:59.422
- categories go over then we have to redo one of these spending plans to make an amendment next year so we try to

01:57:59.810 --> 01:58:06.061
- We build a buffer in there based on the spending that we know to make sure we don't have to come back

01:58:06.061 --> 01:58:12.680
- and redo this spending plan amendment. But like I mentioned, this is really for you to ask me any questions

01:58:12.680 --> 01:58:15.070
- for why we put those numbers up there.

01:58:16.994 --> 01:58:25.317
- And we can scroll through these if you all want to see them or ask particular questions. But as you

01:58:25.317 --> 01:58:34.138
- can see, the majority of the big expenses are listed under debt payments. But then there's also a section

01:58:34.138 --> 01:58:42.711
- for capital expenditures. And then another section for finance proceeds expenditures. OK. So why don't

01:58:42.711 --> 01:58:45.790
- you drill down on that a little bit.

01:58:47.362 --> 01:58:55.861
- Why don't you tell me what finance proceeds expenditures really are? I see the projects. But the proceeds

01:58:55.861 --> 01:59:04.441
- are from elsewhere. So essentially, it's a little confusing the way the DLJF has this worded. Essentially,

01:59:04.441 --> 01:59:12.699
- it's when we issue a bond and we use that bond to spend money from that bond. Let's say we issue a $35

01:59:12.699 --> 01:59:13.822
- million bond.

01:59:13.986 --> 01:59:20.438
- that entire 35 million needs to go under finance proceeds expenditures. So let's take that police station

01:59:20.438 --> 01:59:26.646
- that we were discussing earlier. Let's say we do go for 35, and there's soft costs on top of that. So

01:59:26.646 --> 01:59:32.793
- we build a buffer for all those potential expenditures. Not saying this doesn't obligate us to spend

01:59:32.793 --> 01:59:39.123
- $40.2 million on the police station. It's just we go further down next year. Once we issue those bonds,

01:59:39.123 --> 01:59:40.158
- if there are any

01:59:40.546 --> 01:59:46.898
- Expenditures that we we didn't we didn't first foresee where do you build that buffer in there? and

01:59:46.898 --> 01:59:53.377
- So it's your contingency. Yes, correct. Correct. Well, well the reason I asked for the explanation is

01:59:53.377 --> 01:59:59.792
- if you look at the bottom spending and it's a hundred and fifty three million you look at it and say

01:59:59.792 --> 02:00:06.462
- well You don't have a hundred fifty three million but L is using bond money. It's not really defined and

02:00:06.626 --> 02:00:15.462
- Correct. It's money that the RDC borrows, essentially. Yes. It's not the payment. The payments are under

02:00:15.462 --> 02:00:23.878
- A, Section A. But yeah, L is the proceeds of the bond. Yeah, I don't know why they don't do it like

02:00:23.878 --> 02:00:32.293
- a real financial statement. This is one of those report requirements that came out. Yeah, I realize

02:00:32.293 --> 02:00:35.070
- it's not you. It's just bizarre.

02:00:35.202 --> 02:00:42.969
- Is there a section on here for Showers West operations? Showers West is paid for by 2519, is that correct?

02:00:42.969 --> 02:00:50.301
- So that fund does not collect TIF revenue, so this is specifically for TIF revenue collection funds.

02:00:50.301 --> 02:00:57.777
- No, I'm looking at that, but I'm seeing, for example, capital operating for the police station. So I'm

02:00:57.777 --> 02:01:03.294
- just trying to clarify, there's operational expenses in here for the police

02:01:03.586 --> 02:01:10.524
- I'm assuming that 714, is that? No, so what that was is if the RDC decides to, let's say, a $30 million

02:01:10.524 --> 02:01:17.529
- project for the police station, if we decide to cash fund $5 million of that, maybe to reduce the annual

02:01:17.529 --> 02:01:24.267
- debt payment, this allows us to do that. But that's why the numbers are so high, because we have to,

02:01:24.267 --> 02:01:29.470
- like I said, if one category goes above, we have to reduce this entire thing.

02:01:29.570 --> 02:01:35.714
- Duplicates essentially if we don't bond then we can use cash if we use cash them if we don't want to

02:01:35.714 --> 02:01:41.797
- use cash Then we can still bond sure. No, I understand that. I'm just trying to again clarify Where

02:01:41.797 --> 02:01:48.062
- the distinction is in terms of allocating the funds for operations from TIF funds compared to? Showers

02:01:48.062 --> 02:01:54.814
- West being from non TIF funds. None of the showers West is not on here. I understand that but I'm asking why I

02:01:55.394 --> 02:02:02.963
- why is there that distinction why is there money in here for the police station for the operations being

02:02:02.963 --> 02:02:10.172
- from tiff funds while they're not operations the operations for showers west is not from tiff funds

02:02:10.172 --> 02:02:17.453
- indiana code for the indiana code section it uh... the particular section says that expenditures can

02:02:17.453 --> 02:02:25.310
- be for capital uh... and or operations police fire and so that is so it's a public safety fair it's matching

02:02:25.474 --> 02:02:34.167
- the language that's in the statute, it's not saying you're going to spend it on operations. It's just

02:02:34.167 --> 02:02:43.201
- saying, it's saying in the category that matches the category of expenditures you can have in the statute

02:02:43.201 --> 02:02:51.809
- is matched together. So it's not saying you're using it for operations. But that... But it is. It is

02:02:51.809 --> 02:02:54.110
- being used for operations.

02:02:54.306 --> 02:03:03.062
- I see the difference is. We're not going to be operating the police station once it's not open right

02:03:03.062 --> 02:03:11.732
- and once it's operating. Well, but there's that maybe hours before transfer of ownership right that

02:03:11.732 --> 02:03:13.726
- there may be that and.

02:03:14.658 --> 02:03:20.116
- we're trying to transfer ownership. Anyway, just again, we're in a position now with Showers West where

02:03:20.116 --> 02:03:25.521
- we're trying to transfer ownership. We haven't done that yet. We are paying for operational costs, and

02:03:25.521 --> 02:03:30.874
- I'm just trying to clarify the difference, because that was also purchased with a public safety bond.

02:03:30.874 --> 02:03:36.122
- So I'm just trying to understand the differences in terms of how that works for those two different

02:03:36.122 --> 02:03:40.478
- buildings, which technically have similar sources of financing and outcomes. Yeah.

02:03:44.418 --> 02:03:57.197
- I guess, technically, you could say that part of the funding at Shower's West for the fire part would

02:03:57.197 --> 02:04:10.101
- be under the statute for that RDC could pay for. I will also say that there was a significant progress

02:04:10.101 --> 02:04:14.110
- being made to get Shower's West

02:04:14.274 --> 02:04:25.310
- And it's my understanding that on the December 7th meeting that there will be a presentation on what

02:04:25.310 --> 02:04:37.438
- that transition would look like. So we're inching towards that, that there has been significant progress made.

02:04:39.330 --> 02:04:46.948
- And I do just wanted to clarify one thing on the financing for the two projects are quite different.

02:04:46.948 --> 02:04:54.944
- The proposed financing for the police station would be a TIF revenue bond while the Showers West purchase

02:04:54.944 --> 02:05:02.713
- was actually not out of the TIF. It was out of the general revenue bond. Okay, thank you. I appreciate

02:05:02.713 --> 02:05:07.390
- that clarification. Other questions from commissioners on the

02:05:07.714 --> 02:05:15.640
- 2027 TIF spending plan before we have a motion. When we look at the estimated sum of debt, police station

02:05:15.640 --> 02:05:23.490
- debt, hotel bonds, and we're looking at our overall, you've got a contingency built in. Your contingency

02:05:23.490 --> 02:05:31.341
- is a percentage base or what was it based on? It's 15% is what we have in there. We've got a 15% overall

02:05:31.341 --> 02:05:35.902
- what our projected costs are at the present moment. Correct.

02:05:36.226 --> 02:05:44.035
- from a revenue standpoint where we can justify on our bonds and the rest, we can cover the entire amount.

02:05:44.035 --> 02:05:51.475
- It can go under. I'm sorry? It can be lower, but this will be the maximum that is allowable based on

02:05:51.475 --> 02:05:59.137
- what you're seeing from an expenditure standpoint and a revenue standpoint. We could actually go higher

02:05:59.137 --> 02:06:03.262
- on the annual debt payments. This is just based off our

02:06:03.746 --> 02:06:11.927
- Project estimates. Project estimates. Which brings me to the question I'm looking at in regards to Hopewell.

02:06:11.927 --> 02:06:19.433
- At the present moment, Jeff, how much have we got in Hopewell? I'm just asking. What do you mean in

02:06:19.433 --> 02:06:27.089
- Hopewell? How much have we spent on Hopewell so far? Do we have an idea? No, I don't have that right.

02:06:27.089 --> 02:06:33.694
- And is that amount in that $44 million? Or is this $44 million on top of what we spent?

02:06:34.434 --> 02:06:40.818
- That would be totally new that is not that this would be I understand. I'm just I understand I just

02:06:40.818 --> 02:06:47.202
- want to get this would be a potential Hopewell bond for future infrastructure development Including

02:06:47.202 --> 02:06:53.649
- sections of Hopewell other than Hopewell South. Okay, the entire Hopewell project east West it could

02:06:53.649 --> 02:07:00.097
- be you haven't made that to sell we haven't made that this is kind of a budget figure to you know to

02:07:00.097 --> 02:07:01.310
- make sure that the

02:07:01.602 --> 02:07:08.009
- I remember when we talked about just the overall TIF capacity, we want to make sure that any decisions

02:07:08.009 --> 02:07:14.415
- that you make on TIF bonding kind of take into account potential future plans as well as the... Right.

02:07:14.415 --> 02:07:20.760
- Because at the present moment, is there any bonding on Hopewell? No. That's what I wanted to clarify.

02:07:20.760 --> 02:07:27.229
- We've got expenditures out and we're potentially looking at another $44 million with a 15% contingency.

02:07:27.229 --> 02:07:28.286
- Okay. Thank you.

02:07:31.202 --> 02:07:38.710
- Any other questions regarding resolution 2682, the determination of annual spending plan for calendar

02:07:38.710 --> 02:07:46.733
- year 2027? One last question. Is there, when we're looking at our general, we've got our potential estimated

02:07:46.733 --> 02:07:54.241
- bond funds and then our existing garage leases, is there anything other leases out there that we have

02:07:54.241 --> 02:07:59.614
- any responsibility for in any capacity or that would be outside the TIP?

02:08:00.226 --> 02:08:08.099
- Is it 2519? Because 2519 is not in here. That you're paying leases on? Yes, that we would pay or potential

02:08:08.099 --> 02:08:15.605
- leases that we're unaware of. We're paying them or we're collecting them? Paying. He's saying paying.

02:08:15.605 --> 02:08:23.036
- I'm saying paying. Collecting them. This is a spending plan. Yeah. OK. Just clarification. Yeah, the

02:08:23.036 --> 02:08:29.438
- only payments. The only payments we make are the Wallen Street garage and the Mercury.

02:08:30.658 --> 02:08:38.231
- Yeah, it goes by lots of different names, doesn't it? Merrick Carrier, Register, Morton Street. Yeah,

02:08:38.231 --> 02:08:45.804
- it was Register when the Bowdeans were here, tearing it down. Okay, any other questions before we ask

02:08:45.804 --> 02:08:53.303
- for a motion on Resolution 2682? I'll move approval of Resolution 2682. I'll second. We have a first

02:08:53.303 --> 02:08:59.614
- and a second. All in favor say aye. Aye. Any opposed? Passes unanimously. Thank you.

02:09:00.258 --> 02:09:07.805
- Thank you. Thanks Justin. Okay, next item on the agenda is resolution 2683, which is approval of professional

02:09:07.805 --> 02:09:15.077
- services agreement between the City of Bloomington and Crossroads Engineers PC for engineering assessment

02:09:15.077 --> 02:09:21.937
- for TAP and Vanguard improvements. Good evening. I'm Michael Bitsky from City Engineering. I'm here

02:09:21.937 --> 02:09:28.798
- tonight to ask for funding for the contract you have in front of you for Crossroads Engineering for

02:09:28.798 --> 02:09:29.758
- surveying and

02:09:30.210 --> 02:09:36.974
- analyzing the intersection of Tapp and Vanguard. It was on the transportation impact assessment study

02:09:36.974 --> 02:09:43.738
- of the southwest side of town. So this is the part of phase one of those projects, if you recall. And

02:09:43.738 --> 02:09:50.966
- this would be pursuant to resolution 25-127 that set aside $5 million for this effort with the understanding

02:09:50.966 --> 02:09:57.730
- that we would bring these contracts back to the commission for approval. So this item was approved at

02:09:57.730 --> 02:09:59.454
- the Board of Public Works

02:10:00.002 --> 02:10:10.012
- I'm sorry, it will be approved by the Board of Public Works on November 4th. It's on their agenda. And

02:10:10.012 --> 02:10:19.731
- we do expect an addendum for final design once the analysis, the intersection is complete. So there

02:10:19.731 --> 02:10:25.854
- will be an addendum for this original contract. Any questions?

02:10:27.298 --> 02:10:33.997
- You've got it already got the other side. You already got the intersection built at this particular

02:10:33.997 --> 02:10:40.763
- point. No, we didn't. So there isn't a their intersection exists, but we're looking at modifying the

02:10:40.763 --> 02:10:47.662
- intersection to take the relocation of Weimar and bring in the South and card, which will increase the

02:10:47.662 --> 02:10:53.825
- amount of traffic. So we're looking at increasing the intersection, increasing the capacity

02:10:53.825 --> 02:10:55.902
- of the intersection. Yes, yes.

02:10:56.002 --> 02:11:02.120
- And that's what the analysis is for to understand what we need there based on the change and traffic

02:11:02.120 --> 02:11:08.237
- volumes. Yeah, because as we look going through this property and where we have you, do you have you

02:11:08.237 --> 02:11:14.415
- already got your right of ways in place? We're working on an agreement for that. And then part of the

02:11:14.415 --> 02:11:20.170
- next next contract includes some of that work. Yes, the is I guess was just for clarity, these

02:11:20.170 --> 02:11:24.894
- two resolutions were split apart because this first resident the construction

02:11:25.346 --> 02:11:31.805
- of this first resolution may contain federal funding. Okay. So we're splitting them apart just for clarity

02:11:31.805 --> 02:11:37.963
- of project. Okay. So as you look at this project overall, because you're trying to straighten out and

02:11:37.963 --> 02:11:44.121
- get out of the floodplain. That's correct. I mean, bring it to the top of the hill, go straight right

02:11:44.121 --> 02:11:50.218
- away acquisition. So because this has been going on for about 25 years. Straightening out right away

02:11:50.218 --> 02:11:54.142
- acquisition and then abandoning Weaver. Is that the overall from

02:11:54.370 --> 02:11:59.829
- from Wapahani where it takes the sharp turn to the east, yeah, that will no longer be a roadway. And

02:11:59.829 --> 02:12:05.396
- we looked at this and I may be getting into a little bit of weeds here. We're identifying the Vanguard

02:12:05.396 --> 02:12:11.018
- intersection. We still, you anticipate being able to get the right of way without having to go through,

02:12:11.018 --> 02:12:16.423
- come back and ask for money on that. So we, for the intersection of Tapp and Vanguard, when it was,

02:12:16.423 --> 02:12:21.882
- when right of way was originally given or purchased or created in that area, there was a significant

02:12:21.882 --> 02:12:23.774
- amount of additional right of way.

02:12:24.066 --> 02:12:29.665
- that is already public right away. Okay, so we've got that covered. Yes. And then long term,

02:12:29.665 --> 02:12:35.925
- looking at this, are we all also looking because this is a very expensive road that's going to be very,

02:12:35.925 --> 02:12:42.006
- very, very expensive, expensive intersection. And then what do we do as we hit Weimer coming back up

02:12:42.006 --> 02:12:48.507
- to Second Street? Is that part of any long term analysis? It's part of the next contract, the next business

02:12:48.507 --> 02:12:50.494
- item here on the agenda tonight.

02:12:51.330 --> 02:12:59.087
- just want to make because we bought we bought the fire extinguisher building about 20 some years ago

02:12:59.087 --> 02:13:06.768
- and so all right perfect thank you so much sure any other questions or comments on commissioners on

02:13:06.768 --> 02:13:14.602
- resolution 2683 if not I'll ask for a motion please got a first and a second all in favor say aye aye

02:13:14.602 --> 02:13:18.366
- any opposed pass unanimously thank you thank you

02:13:19.042 --> 02:13:25.546
- Okay, next item on the agenda. You're still up. 2684, please, which is approval of professional services

02:13:25.546 --> 02:13:31.740
- agreement between the city of Bloomington and Crossword Engineers PC for engineering assessment for

02:13:31.740 --> 02:13:38.058
- tap and Vanguard improvements. Sorry, I misread it. I hadn't scrolled down. I thought I clicked on to

02:13:38.058 --> 02:13:42.270
- the next one. I was expecting something similar, but it's actually.

02:13:42.402 --> 02:13:50.126
- So this is 2684, approval of professional services agreement between the city of Bloomington and Crossroads.

02:13:50.126 --> 02:13:57.778
- Engineers PC for engineering assessment for South Weimar Road relocation and Weimar-Bloomfield intersection

02:13:57.778 --> 02:14:05.077
- improvements. Yes, this will be the relocation, the full design of the Weimar relocation from Wapahani

02:14:05.077 --> 02:14:11.454
- down to the intersection of Schmalls and Vanguard, as well as the analysis of Bloomfield.

02:14:11.554 --> 02:14:19.927
- and Wimmer intersection, which includes the property that was purchased a while back. So this item was

02:14:19.927 --> 02:14:28.219
- approved by the Board of Public Works on October 20th. So we have an approved contract. We do expect,

02:14:28.219 --> 02:14:37.161
- like the other business item, we do expect an addendum for the final design of the intersection at Bloomfield

02:14:37.161 --> 02:14:41.470
- and Wimmer once the analysis is complete. Thank you.

02:14:41.570 --> 02:14:49.405
- further questions or comments from commissioners on 2684? I just want to verify. Do we have any idea

02:14:49.405 --> 02:14:57.549
- what this overall construction cost would be? I do not at this time. Because I'm just curious in regards

02:14:57.549 --> 02:15:05.307
- to where we come from a funding standpoint and trying to do this major road that should enhance our

02:15:05.307 --> 02:15:10.814
- ability to expand our employment opportunities given the zoning there.

02:15:11.106 --> 02:15:17.603
- reality of where we are able to fund this after we get the designs done. It concerns me when we spend

02:15:17.603 --> 02:15:23.972
- this kind of money and we really don't know or have an idea of what our overall construction. Don't

02:15:23.972 --> 02:15:30.787
- you have to spend this money to fund it? Once the intersection analysis is done, there's a huge difference

02:15:30.787 --> 02:15:37.157
- in cost between intersection types. So once those recommendations come in, I think we'll be able to

02:15:37.157 --> 02:15:38.558
- tie those costs down.

02:15:38.946 --> 02:15:45.853
- With a contingency to make sure we're going to hit the mark. Right, because when we look at 13 years

02:15:45.853 --> 02:15:52.692
- left into a TIF, and then what our federal funding will be, what our overall matching funds are. It

02:15:52.692 --> 02:15:59.668
- just concerns me, because it's such a large road that we just funded a piece of one a few years back,

02:15:59.668 --> 02:16:06.302
- and it's still setting. Thank you. I have a suggestion and a question. Since we're actually just

02:16:06.562 --> 02:16:13.636
- burning down the five million with each one of these resolutions. It just might be handy for us to have

02:16:13.636 --> 02:16:20.506
- in maybe the first whereas. It says we've earmarked five million. You also could give us the balance

02:16:20.506 --> 02:16:27.444
- of what's left that is available. So as we get additional resolutions, we know how much we can spend.

02:16:27.444 --> 02:16:34.382
- Yeah, I appreciate that. That's a good idea. That's a great idea. That's my token idea. I can go home

02:16:34.382 --> 02:16:35.742
- now. Call it a day.

02:16:36.194 --> 02:16:45.503
- Wait. Mike did provide me a breakdown. I do not have it available at the second minute, but I can get

02:16:45.503 --> 02:16:55.085
- that to you in an email, let you know. I mean, I can do the math. It's not too hard. It'd just be easier

02:16:55.085 --> 02:17:04.211
- not to have to do the math. We have not processed any claims against that $5 million yet. But we've

02:17:04.211 --> 02:17:05.854
- made commitments.

02:17:06.594 --> 02:17:13.337
- So I'm talking about reducing the five million by the commitments. We do have a project tracking sheet

02:17:13.337 --> 02:17:20.015
- that we will work on adding. Yeah, that could just be included even as an exhibit or reference in the

02:17:20.015 --> 02:17:26.562
- first whereas. But it would be nice to have something detailed as well. I have a separate question,

02:17:26.562 --> 02:17:33.305
- which is just based on Randy's note that in terms of the total life period of the TIF that's left. And

02:17:33.305 --> 02:17:36.382
- this is because this is largely, I don't know,

02:17:36.706 --> 02:17:43.176
- my take relatively undeveloped in terms of what's forthcoming. And this is a little adjacent, so it's

02:17:43.176 --> 02:17:49.519
- not really a direct question to you, but more to, let's say, legal. Is there any reason to consider

02:17:49.519 --> 02:17:56.243
- where maybe this part of the consolidated TIF might be taken out of that so that, because it's relatively

02:17:56.243 --> 02:18:02.713
- low assessed value right now compared to where the potential is, so that there could be more time for

02:18:02.713 --> 02:18:05.758
- the total build out that is going to be needed?

02:18:06.050 --> 02:18:13.031
- And you can certainly let me know if I'm off in my understanding of the total concept of where this

02:18:13.031 --> 02:18:20.431
- is, what the assessed value is, what the projected need may be. But I'm just asking that question because

02:18:20.431 --> 02:18:27.481
- we're talking about it now, even though it's not specifically germane to the actual approval of this

02:18:27.481 --> 02:18:34.462
- resolution. Yes, I would very likely recommend that there be a separate TIF created like we did for

02:18:34.462 --> 02:18:35.998
- Summit when this area

02:18:36.706 --> 02:18:48.110
- actually gets ready for development. Most of that property is owned by a public investment board. And

02:18:48.110 --> 02:18:59.402
- we have an agreement that is almost signed to where in the part that's not already platted that they

02:18:59.402 --> 02:19:06.110
- would provide a 65 foot right of way through their property

02:19:06.210 --> 02:19:15.792
- to where Wapahane and we were connect. And so they're going to provide that. If we need more than that,

02:19:15.792 --> 02:19:25.373
- they wouldn't, you know, wouldn't pay for that, but they're going to provide that. It's a detailed MOU,

02:19:25.373 --> 02:19:34.494
- so I won't get into the whole thing. But so the, that this area wouldn't develop without the road.

02:19:35.170 --> 02:19:44.922
- So it's going to need the road to develop. So we'll need to do the improvements. And then once

02:19:44.922 --> 02:19:55.393
- the improvements are made, then as it starts to develop and it's his own TIF, it can start generating

02:19:55.393 --> 02:20:01.758
- funds to help cover the cost of what had gone into that area.

02:20:01.890 --> 02:20:10.743
- that can be used on other projects as well. Like we're using those funds on this project. Okay. So what

02:20:10.743 --> 02:20:19.511
- I'm hearing, this thing will get broke out eventually if it's on TIF again. Yes. It's been a TIF since

02:20:19.511 --> 02:20:28.279
- 91 and then it's been reintroduced again. Right now the investment board pick property is not actively

02:20:28.279 --> 02:20:29.726
- being developed.

02:20:30.754 --> 02:20:40.240
- at this time. OK. So that'll be something that's forthcoming somewhere in the lifetime of this project

02:20:40.240 --> 02:20:49.633
- in, let's say, the next two years or so? Likely, or at least any time before the development actually

02:20:49.633 --> 02:20:58.014
- starts. OK. As long as it's on somebody's radar, just saying. Yes. Yes. Yes. Design. I am.

02:20:58.850 --> 02:21:13.702
- have been looking at areas that could use improvement that might be even if they're not inside the existing

02:21:13.702 --> 02:21:27.454
- TIF that the RDC might want to consider looking at to help with improvement. So yes, again, 2040 is

02:21:28.386 --> 02:21:35.134
- just around the corner in some ways. Okay. Well, thank you for your help with that question. Other questions?

02:21:35.134 --> 02:21:41.576
- Crossroads. They give you a time frame in order to, once you sign contracts with them, to get this done.

02:21:41.576 --> 02:21:47.895
- So we've got a time in there. We're a little behind the schedule that was presented in the request for

02:21:47.895 --> 02:21:54.029
- information just to get to this contractual phase. But we intend to have South William or the South

02:21:54.029 --> 02:21:56.606
- William relocation ready for construction

02:21:57.090 --> 02:22:04.747
- middle to the third quarter of next year. And then that's just to stay in line with the schedule that's

02:22:04.747 --> 02:22:12.404
- been presented to us by the developer of Summit. Just try to stay in step with them and what they think

02:22:12.404 --> 02:22:20.281
- they'll be doing. The Shasta Meadow area. Well, to me, specifically the construction of Adams and Sudbury,

02:22:20.281 --> 02:22:25.214
- which then sets up the ability to sell lots in Shasta Meadow, yes.

02:22:28.866 --> 02:22:35.316
- If there are no other questions or comments from commissioners, I will ask for a motion for resolution

02:22:35.316 --> 02:22:41.766
- 2684, please. I'll make a motion to approve 2684 as presented. Second. We've got a first and a second.

02:22:41.766 --> 02:22:46.462
- All in favor say aye. Aye. Anybody opposed? Passes unanimously. Thank you.

02:22:47.586 --> 02:22:56.612
- Okay, next item on the agenda is Resolution 2685, Approval of First Amendment to the Professional Services

02:22:56.612 --> 02:23:05.300
- Agreement with Applied Engineering Services, Incorporated for Plumbing and Engineering Services at the

02:23:05.300 --> 02:23:13.735
- 4th Street Garage. Who would like to speak to that? I will. Yeah, I think that's a data. During the

02:23:13.735 --> 02:23:17.278
- investigation work that Applied had done,

02:23:17.954 --> 02:23:30.966
- They ended up finding additional work that needed done, but we were able to get some things corrected

02:23:30.966 --> 02:23:43.978
- by the original contractor, which was good. So that saved us the cost of that actual activity. But in

02:23:43.978 --> 02:23:47.678
- doing so, it took some extra

02:23:47.842 --> 02:24:01.492
- time for applied engineering to do their work. And we need a concise report of the activities that were

02:24:01.492 --> 02:24:15.143
- done. And so in order to complete their scope of work, they needed some additional, their scope of work

02:24:15.143 --> 02:24:17.374
- was increased to

02:24:17.634 --> 02:24:28.844
- cover that. So there was further evaluation of repairs, additional work to address the existing piping

02:24:28.844 --> 02:24:39.727
- conditions, including the need to develop a revised design to provide adequate slope for the garage

02:24:39.727 --> 02:24:46.366
- drain system. So the additional work is laid out for you and

02:24:46.754 --> 02:24:59.467
- So this is just the cost to complete their part. Again, it was a great benefit that the contractor came

02:24:59.467 --> 02:25:12.424
- back and repaired some of the issues. And again, this is being paid out of the bond fund. Any idea what's

02:25:12.424 --> 02:25:15.358
- left in that? $450,000.

02:25:15.938 --> 02:25:22.980
- And that'll be used for ongoing maintenance and operation. Well, no, not maintenance, but not routine

02:25:22.980 --> 02:25:29.954
- maintenance. Yeah, let me rephrase that. When something fails. Yes, exactly. Just like the sprinkler

02:25:29.954 --> 02:25:36.858
- system. If and when we discover additional things. We discover anything additional. And this work's

02:25:36.858 --> 02:25:44.798
- already been done, performed, over with. We're just catching the dollars up with it. So it's an additional $8,465.

02:25:47.554 --> 02:25:54.707
- We're done. We're good on the 4th Street garage, on its drainage. We've got it figured out on its sprinkler.

02:25:54.707 --> 02:26:01.400
- To the best of our knowledge. You've been around the business long enough to know that things happen.

02:26:01.400 --> 02:26:08.160
- Water will always find a way. But this is the best effort that we have to get this fixed and done. And

02:26:08.160 --> 02:26:14.722
- we don't have to engage an engineer at this present moment to do any additional evaluation on this.

02:26:14.722 --> 02:26:17.150
- This is so we can process our claim.

02:26:18.466 --> 02:26:25.588
- If there's no further questions, I'll ask for a motion on 2685. Do you have another question? No. Okay.

02:26:25.588 --> 02:26:32.573
- Just a second. No. Okay. Approval of Resolution 2685. Second. Move a first and a second. All in favor

02:26:32.573 --> 02:26:39.558
- say aye. Aye. Any opposed? Okay. Sorry, be legal. Nope, nope. You're good. Make sure we're not in the

02:26:39.558 --> 02:26:41.886
- opposed line. Passes unanimously.

02:26:42.242 --> 02:26:48.203
- Okay, next item on the agenda is resolution 2686, approval of agreement with VET Environmental Engineering

02:26:48.203 --> 02:26:53.886
- LLC for lead-based paint and asbestos inspections at College Square. Who would like to speak to that?

02:26:54.146 --> 02:27:01.744
- I'd be happy to talk about it. As you know, any time you're considering demolishing a building, an item

02:27:01.744 --> 02:27:09.341
- will require specific testing for asbestos and lead-based paint testing. We have had phase ones on this

02:27:09.341 --> 02:27:16.647
- building, but they did not do this specific testing. So this is now to the tune of $17,184.81 if we

02:27:16.647 --> 02:27:23.806
- are to consider the possible demolition of the building. Obviously, no agreements have been made.

02:27:23.906 --> 02:27:30.404
- at a position to say that this is absolutely happening or not happening, but this is to better inform

02:27:30.404 --> 02:27:36.775
- us as we move forward with considerations of its future. Okay, thank you. Any comments or questions

02:27:36.775 --> 02:27:43.210
- from commissioners from resolution 2686? Is there any other things we need to be looking for besides

02:27:43.210 --> 02:27:45.758
- letting asbestos so it won't come back?

02:27:46.018 --> 02:27:53.226
- I don't think so. I mean, we've been working on trying to obtain closure letters from IDEM at College

02:27:53.226 --> 02:28:00.435
- Square following the remediation efforts that were recent. So we're still waiting on those right now.

02:28:00.435 --> 02:28:07.572
- But we've already done geotechnicals. We've already had phase ones. We've already had phase twos. So

02:28:07.572 --> 02:28:15.134
- this is just the next step. In the building itself. Yes. In the building itself as we consider its future.

02:28:16.066 --> 02:28:22.361
- Which? Who knows? Well, yeah, considering, I think we've spent about $700 or $800 on utilities on a

02:28:22.361 --> 02:28:28.720
- monthly basis. And we are actually in the process of billing back some of those utilities to Weddle,

02:28:28.720 --> 02:28:35.267
- who's been occupying the space right now, too. So those will be credited back to you soon. OK. And then

02:28:35.267 --> 02:28:41.814
- last question in regards to this. We've got to get it done if we're ever going to consider tearing this

02:28:41.814 --> 02:28:45.214
- down. And it's not getting cheaper, obviously. Right.

02:28:45.794 --> 02:28:51.647
- to tear them down. How many solar panels are in, how many are ours, and where are we gonna take them

02:28:51.647 --> 02:28:57.500
- so we can consider this, because we're spending $17,000 to tear them down, and we've got to. That is

02:28:57.500 --> 02:29:03.585
- a whole nother conversation. Director Cooper-Smith is no longer here with us tonight. She's been working

02:29:03.585 --> 02:29:09.380
- hard with Dana to come up with a plan of how to deal with the solar panels, so I assure you that it

02:29:09.380 --> 02:29:14.654
- is on our radar, and hopefully we'll be updating you soon. There's only so much bandwidth.

02:29:15.778 --> 02:29:26.894
- anything we can do to help with that. Thank you. Yes, sir. The contract, well, the way the resolution

02:29:26.894 --> 02:29:38.009
- reads, the funds are available up to June 1st of 2027. I believe that's what it says. But I don't see

02:29:38.009 --> 02:29:44.766
- anywhere in the documents where that actually has to complete

02:29:47.938 --> 02:29:56.141
- Maybe I missed it, so that's why another set of eyes is great. But it needs to have a deadline. I'd

02:29:56.141 --> 02:30:04.591
- be happy to add a deadline to this. I think when I last spoke to them, they were able to start working

02:30:04.591 --> 02:30:13.122
- on it pretty soon. But I think we were giving ourselves some flexibility if there was coordination with

02:30:13.122 --> 02:30:17.470
- IDEM. Well, I don't mind. The resolution reads fine.

02:30:17.954 --> 02:30:24.730
- how long the funds are available from us, but I don't want, I don't think that gives, that's

02:30:24.730 --> 02:30:32.745
- not a completion. The term of the agreement expires on June 1st, although that obviously does not necessarily

02:30:32.745 --> 02:30:40.178
- say that the work will be done by that time. There's like nothing in this proposal here. Oh, I'm just

02:30:40.178 --> 02:30:45.278
- looking at the agreement for services and the term, right, where that

02:30:46.338 --> 02:30:55.460
- says that it shall commence on the effective date and expire on the first day of June, 2027. So my inference,

02:30:55.460 --> 02:31:03.919
- which maybe it needs to be spelled out more clearly, was that that meant that- Well, I guess then the

02:31:03.919 --> 02:31:12.295
- follow up to that comment, it doesn't take that long. So let's shorten that up. Open to suggestions.

02:31:12.295 --> 02:31:15.198
- Happy to modify- By the end of the

02:31:15.298 --> 02:31:23.283
- first quarter of next year. I mean, we'd like the information sooner than later. If there's a remediation

02:31:23.283 --> 02:31:30.966
- problem that we don't want to wait till June to find out about it. Sure. I think that's fine. Because

02:31:30.966 --> 02:31:39.102
- if we look to tear it down, what is the time frame? Well, I'm trying to get them there as soon as possible.

02:31:39.362 --> 02:31:47.446
- Got to get this approved for them for me to give them the green light to go I April 1st is fine with

02:31:47.446 --> 02:31:55.531
- me March 1st is fine with me. Obviously we would like this Yeah, so I don't care It's it's literally

02:31:55.531 --> 02:32:01.374
- just like the report by March I will make sure that that works with them

02:32:04.642 --> 02:32:13.459
- So then you would need to, if you're going to approve it, move approval with that modification. I will.

02:32:13.459 --> 02:32:22.023
- And that modification would be in the resolution and in the agreement? Okay. Anything further? Thank

02:32:22.023 --> 02:32:31.179
- you for calling that to our attention. If not, I will ask for a motion for 2686, please. I'll move approval

02:32:31.179 --> 02:32:33.214
- of resolution 2686 with

02:32:34.562 --> 02:32:44.414
- modification that the completion date for the work from that environmental is March 1, 2027. Second?

02:32:44.414 --> 02:32:54.558
- We've got a first and a second. All in favor say aye. Aye. Any opposed? Passing unanimously. Thank you.

02:32:55.202 --> 02:33:03.385
- We now move on to resolution 2687, which is approval of amendment number three to the agreement with

02:33:03.385 --> 02:33:11.892
- Flintlock Limited Company for additional services related to the creation of a planned union development

02:33:11.892 --> 02:33:20.480
- PUD for Hopewell South. Would like to speak to that. I'm happy to also, sorry, I was updating that piece.

02:33:20.480 --> 02:33:24.126
- So as you know, with our pre-approved plans,

02:33:24.642 --> 02:33:33.893
- We are able to move forward with those without engaging. And in Indiana, you have to have a stamped

02:33:33.893 --> 02:33:43.236
- architectural drawings from an engineer in Indiana. And so these are for those multifamily buildings

02:33:43.236 --> 02:33:52.672
- that require additional work, unfortunately, for our plans. I don't know, Dana, do you have anything?

02:33:52.672 --> 02:33:54.430
- It's an MEP stamp.

02:33:54.850 --> 02:34:05.214
- was we did not have to have these larger multiplex buildings. But then as part of the design to keep

02:34:05.214 --> 02:34:15.680
- the number of units, when you looked at the right of ways of the roads and things like that that were

02:34:15.680 --> 02:34:24.094
- being done during the design to keep the unit number up, there had to be a larger

02:34:24.226 --> 02:34:34.706
- There's two six unit buildings and two 12 unit buildings. And so initially these weren't part of the

02:34:34.706 --> 02:34:45.394
- scope because they weren't needed. But when the area to build got smaller because of the right of ways

02:34:45.394 --> 02:34:54.110
- getting larger than we had hoped, then that made it again that we had to use these.

02:34:54.306 --> 02:35:04.819
- These are different structures than what was originally determined. And they have more than four units.

02:35:04.819 --> 02:35:15.129
- They require different building plans. And so when developing this project, it was said that we would

02:35:15.129 --> 02:35:19.678
- have pre-approved plans to a certain extent.

02:35:20.194 --> 02:35:29.942
- And so in order for that to be true for these buildings, they need this additional work to design them

02:35:29.942 --> 02:35:39.594
- out. These buildings weren't, again, part of the initial project. They came in as a result of changes

02:35:39.594 --> 02:35:49.342
- that were made because of right of way and such. And so because they require a different building code

02:35:49.538 --> 02:36:02.083
- that they fall under, they do require different types of drawings. And so this would cover those other

02:36:02.083 --> 02:36:14.506
- drawings so that these units would have the same offering as the other buildings where there were, to

02:36:14.506 --> 02:36:19.134
- a certain extent, pre-approved plans.

02:36:19.554 --> 02:36:28.727
- pre-designed buildings like the others were. For the footprint. Sorry. Go ahead. No, ladies first. I

02:36:28.727 --> 02:36:38.353
- was just going to say it requires an MEP stamp, which is mechanical, electrical, and plumbing engineering

02:36:38.353 --> 02:36:48.161
- stamp on these particular types. So looking back through the June 2025 when this was presented by Flintlock

02:36:48.161 --> 02:36:49.342
- at the time,

02:36:49.474 --> 02:36:56.979
- those buildings were there from a footprint standpoint. No? No. Because of the changes the council had

02:36:56.979 --> 02:37:04.265
- made, in order to preserve our unit count, they ended up adding back in these multifamily buildings

02:37:04.265 --> 02:37:11.770
- to help keep the unit count up. So there were several changes. And in fact, there is language in their

02:37:11.770 --> 02:37:18.910
- agreement that says, should this be something that comes up, that we would have to get this done.

02:37:19.074 --> 02:37:27.457
- and I can pull that up, because I questioned it. Well, I questioned it because I looked at the original

02:37:27.457 --> 02:37:35.517
- layout that was presented when we went through the planning. It had the Faulkner and Williams on it

02:37:35.517 --> 02:37:44.222
- as from a visual 2D look. So I understand because of the code issue, it got missed. But what I'm asking is,

02:37:44.514 --> 02:37:50.955
- is that a necessity to go ahead and have these pre-approved because they are the multi-family units.

02:37:50.955 --> 02:37:57.971
- And with the platting of what we're looking at now, is this something that has to be done from a pre-approved

02:37:57.971 --> 02:38:03.966
- standpoint? Because when we get into our multi-families, we're in a little bit of a different

02:38:04.866 --> 02:38:11.645
- set than providing single family and duplex. That is true. But unfortunately, the language in the PUD

02:38:11.645 --> 02:38:18.357
- does say pre-approved plans. And so this is a condition of that. And then also, it was buried in the

02:38:18.357 --> 02:38:25.202
- language of the proposal from Flintlock that as a contingency, that if this were to come up, that this

02:38:25.202 --> 02:38:32.446
- would be an additional fee. Indiana requires an Indiana-specific MEP stamp. Right. They were using Arkansas.

02:38:32.866 --> 02:38:40.806
- Yeah, the PUD requires a catalog of pre-approved plans. OK. So I guess the question I would look at

02:38:40.806 --> 02:38:48.032
- is, what's the timing on a pre-approved? Planning is actually already given their blessing

02:38:48.032 --> 02:38:56.131
- for the single-family residential house plans. So those are great from the pre-reviewed, pre-approved

02:38:56.131 --> 02:39:01.054
- standpoint. Obviously, these two buildings are the last ones.

02:39:02.018 --> 02:39:07.394
- because my concern of this is as we're looking at a multifamily building in regards to as who's going

02:39:07.394 --> 02:39:12.717
- to buy it and build it and is there any going to be any additional modifications that they see based

02:39:12.717 --> 02:39:18.146
- upon what the market conditions are in Bloomington in order to condo these out. Because while I... The

02:39:18.146 --> 02:39:23.680
- modifications who's paying for it. Exactly what's the modifications that would need to be made who would

02:39:23.680 --> 02:39:26.526
- have to pay for it and from a pre-approved standpoint

02:39:26.946 --> 02:39:34.257
- You know, because the singles, the duplexes, and even the tries, I understand. But when we're getting

02:39:34.257 --> 02:39:41.425
- into these four multifamily buildings, it just concerns me because of reconfiguration based on, oh,

02:39:41.425 --> 02:39:48.951
- here's what's pre-approved. Well, I'm sorry, but that's not necessarily what the market or the community

02:39:48.951 --> 02:39:56.190
- has the ability to absorb. We have to go back for an amendment. Well, the UDO does have a section of

02:39:56.866 --> 02:40:07.468
- what can be amended within the PUD. And there's a certain percentage of size. Height can be changed,

02:40:07.468 --> 02:40:18.070
- but not more than eight feet, or you can't add a story to it. So there are modifications that can be

02:40:18.070 --> 02:40:24.158
- made and still fall within the PUD. But so if a developer

02:40:25.282 --> 02:40:38.076
- this building and wanted to to change it they they could do so and you know rework it to their to their

02:40:38.076 --> 02:40:49.886
- likings as long as they stayed within the you know not changing it by a certain size or height.

02:40:50.946 --> 02:40:57.994
- based on the setbacks aside. It seems to me like we're talking about something that is hypothetical.

02:40:57.994 --> 02:41:04.971
- And if there is changes by a particular developer, most likely it would be on his nickel, not ours,

02:41:04.971 --> 02:41:12.228
- because we're providing a baseline of what we're going to do. And if they want to do some modifications

02:41:12.228 --> 02:41:17.950
- that are approved by planning, that's fine. But I don't know that we can sit here

02:41:18.082 --> 02:41:24.250
- No, my only concern, I'm not trying to hypothesize anything. I'm trying to get that word out. What I'm

02:41:24.250 --> 02:41:30.357
- looking at is, as we look at this, and we're supposed to try to make everything from an affordability

02:41:30.357 --> 02:41:36.525
- standpoint, each one of those costs that adds on always adds a little bit more. I know, Randy. But the

02:41:36.525 --> 02:41:42.573
- streamlining things by having the pre-approved plans, again, which is already amended by the PUD, is

02:41:42.573 --> 02:41:47.902
- at least supposed to help get through the review process more efficiently, more quickly.

02:41:48.066 --> 02:41:54.587
- I'm just quick looking like, for example, at South Bend's catalog, um, from 2025, where they've got

02:41:54.587 --> 02:42:01.499
- up to a sixplex apartment in there in terms of just as an example of what a catalog, the range of housing

02:42:01.499 --> 02:42:08.020
- that could be in there. Um, and I think again, as is coming out that we get what is pre-approved by

02:42:08.020 --> 02:42:14.606
- the city for our end of things. And, um, and that's hopefully something that then can follow through

02:42:14.606 --> 02:42:17.214
- in terms of make easing the way from a,

02:42:17.378 --> 02:42:22.866
- builder standpoint, so. Right, and if we were to hold off on this too, even if the PUD would allow for

02:42:22.866 --> 02:42:28.354
- it, I mean, how does that impact the affordability of the units that the builder has to take that cost

02:42:28.354 --> 02:42:33.735
- on? Because they have to have that. Right, the point is having the pre-approved plans is to make, to

02:42:33.735 --> 02:42:39.170
- streamline the total entitlement process so that you can go straight to site review as opposed to all

02:42:39.170 --> 02:42:43.326
- the other in-between. So anyway, just... Yeah, I don't disagree on any of it.

02:42:43.618 --> 02:42:51.840
- The only question was what the cost factor was that's come back to us at the end. Well, maybe not. Observe

02:42:51.840 --> 02:42:59.524
- that, right? Maybe not. It may be a perfect thing. Or maybe we pass that cost on to the individuals

02:42:59.524 --> 02:43:07.362
- that request it. Yeah. So just trying to minimize costs. I just don't want to have that conversation.

02:43:07.362 --> 02:43:11.742
- I know, but we're trying to keep the project moving too.

02:43:12.482 --> 02:43:22.197
- The point of pre-approved plans is to ideally to reduce the cost of the total by expediting the process

02:43:22.197 --> 02:43:31.632
- and reducing the upfront costs for the builder. Any other questions on this amendment that's part of

02:43:31.632 --> 02:43:39.198
- the agreement with Flintlock for resolution 2687? If not, I'll ask for a motion.

02:43:40.994 --> 02:43:49.685
- Approval of resolution 2687. Second. We've got a first and a second. All in favor say aye. Aye.

02:43:49.685 --> 02:43:58.739
- Any opposed? Passes unanimously. I'm sorry, you are? I am going to oppose. Okay, so we've got three

02:43:58.739 --> 02:44:05.438
- in favor, one opposed. Thank you. Okay, we are now on to resolution 2688.

02:44:05.762 --> 02:44:12.002
- which is approval of the third amendment to the agreement with Mother Nature Landscaping Incorporated

02:44:12.002 --> 02:44:18.181
- for erosion control measures at Hopewell East. I'm taking this one for Kendall this evening. We were

02:44:18.181 --> 02:44:24.421
- asking for an approval of amendment number three in the amount of 5825 with Mother Nature Landscaping

02:44:24.421 --> 02:44:30.661
- for what will be the final erosion control services at Hopewell East. We recognize that Milestone was

02:44:30.661 --> 02:44:32.190
- the original contractor.

02:44:32.706 --> 02:44:40.270
- We believe they satisfied their contract with the original install as well as multiple attempts to repair

02:44:40.270 --> 02:44:47.619
- what was damaged. But there was just, after repeated efforts, they're just approved and unapproved use

02:44:47.619 --> 02:44:54.969
- in the northwest corner of that development that we could not sustain and get to hold erosion control.

02:44:54.969 --> 02:45:01.534
- So in an effort to try to get the MS4 permit approved and completed by the end of the year,

02:45:02.082 --> 02:45:11.100
- We're asking to hire Mother Nature for this amount to get that area completed so we can get those permits

02:45:11.100 --> 02:45:19.777
- closed out. Thank you. Any questions or comments from commissioners on resolution 2688? Don't we have

02:45:19.777 --> 02:45:28.455
- an agreement with Calumet to utilize that area at the present moment for a lay down area? I'm unaware

02:45:28.455 --> 02:45:31.262
- of that. Yeah. No, I believe it.

02:45:31.458 --> 02:45:37.477
- That is not the same area North Calumet. I believe we were speaking for construction folks. I think

02:45:37.477 --> 02:45:43.615
- we've been chasing Calumet off that space. Well, I understand they're not using it, but we did. Well,

02:45:43.615 --> 02:45:49.935
- actually, they may not be using it continually. They're using the high. Yeah, I understand they're using

02:45:49.935 --> 02:45:56.194
- high speed for their lay down old high speed building for their lay down, but they have been used. They

02:45:56.194 --> 02:45:58.782
- have been on the site with their vehicles.

02:46:00.994 --> 02:46:11.094
- We've got a video. We've got our camera. The question is, is it approved use or are they just? Well,

02:46:11.094 --> 02:46:21.994
- unless, did they never execute? We passed by a resolution to allow them to use that site. It also terminates

02:46:21.994 --> 02:46:29.694
- December 31st of 2026. The resolution to utilize that area was with Calumet.

02:46:29.794 --> 02:46:38.632
- because they were supposed to contain it and re-establish it. So I understand we're going to close our

02:46:38.632 --> 02:46:44.638
- permit out. I just want to make sure from a responsibility cost-wise.

02:47:01.410 --> 02:47:10.291
- My memory serves me correct. What it was is they would not sign the agreement. And so because they found

02:47:10.291 --> 02:47:18.918
- another place to go. They're on Madison Street at the old high speed. OK, so they wouldn't sign it so

02:47:18.918 --> 02:47:27.038
- we don't have an agreement with Calumet. Which is why you're running them off every time. Yeah.

02:47:27.362 --> 02:47:36.844
- Dana's correct. I've found an email. They've decided to put their staging area elsewhere. They will

02:47:36.844 --> 02:47:46.990
- not be signing the agreement. OK. Appreciate all that. I've got a question, much like a couple resolutions

02:47:46.990 --> 02:47:55.998
- prior. Where in these documents does it give a completion date for Mother Nature? It does not.

02:47:57.282 --> 02:48:04.415
- I know there's no I didn't see a completion date, but I did see a an immediate start date. OK, well.

02:48:04.415 --> 02:48:11.689
- And then the funding authorization terminates May 31st, right? I know that, but we certainly not going

02:48:11.689 --> 02:48:18.822
- to wait that long to have the. So no, this is the right time to see it is right now. So I think with

02:48:18.822 --> 02:48:26.590
- all these performance contracts we had to have completion date, so it's a word for the future. Good. So what?

02:48:29.474 --> 02:48:43.649
- What do you recommend? Pardon me? What do you recommend as a completion date? March 1st. Those last

02:48:43.649 --> 02:48:52.862
- two months would only be if it was damaged. That should be done.

02:48:53.442 --> 02:48:58.708
- should be all done. They should be done in the next couple weeks if they're given a go and then process

02:48:58.708 --> 02:49:03.873
- coming soon. I was thinking it'd be by the end of the year because it's germinate erosion control. We

02:49:03.873 --> 02:49:08.987
- don't want to run it. We don't want to run into next year. So yeah, I mean germination if it's going

02:49:08.987 --> 02:49:14.202
- to happen this year, it's going to happen the next six weeks. So yeah, and so their work, I mean, they

02:49:14.202 --> 02:49:19.266
- don't have, they're not, we're not gonna wait around for germination, but their work should be done

02:49:19.266 --> 02:49:20.734
- by the end of December. Yes.

02:49:21.570 --> 02:49:29.507
- Will that satisfy and get us our MS board finished? It depends how dense it comes up, how dense it terminates

02:49:29.507 --> 02:49:36.795
- and how. I don't know. I'm just asking the question to try to get through, because this is being put

02:49:36.795 --> 02:49:44.443
- in for a so we can close out a project. I think I think sodding is just my perception. Lack of experience

02:49:44.443 --> 02:49:49.566
- here in Bloomington, but sodding has its own challenges because of the

02:49:49.954 --> 02:49:58.630
- the mixture that we have in the UDO for. For the bluegrass. For the bluegrass. Instead of fascia. Yeah.

02:49:58.630 --> 02:50:07.056
- Which, if you can get that changed. Bluegrass isn't native. Okay, so are we getting an amendment for

02:50:07.056 --> 02:50:14.814
- our December 31st closing of this project? Yeah, I was going to do the resolution with that.

02:50:19.650 --> 02:50:30.568
- Yeah I'm ready for a motion I just wanted to clarify the amendment and where it was going and what we're

02:50:30.568 --> 02:50:41.591
- saying. I'll move approval of resolution 2688 with a revision that completion date for the work by Mother

02:50:41.591 --> 02:50:47.934
- Nature's Landscaping to be completed by December 31st, 2026.

02:50:50.466 --> 02:50:58.927
- We've got a first and a second. All in favor say aye. Aye. Any opposed? Passes unanimously. Thank you.

02:50:58.927 --> 02:51:07.553
- Thank you. Next item on our agenda is resolution 2689, approval of the second amendment to the agreement

02:51:07.553 --> 02:51:15.768
- for public art in Hopewell East. Ms. Dragovich. Hi, thank you. These last two resolutions overlap a

02:51:15.768 --> 02:51:20.286
- little bit, so would it be okay if I talked about them

02:51:20.450 --> 02:51:31.295
- currently. So these last two resolutions are for undulate artwork in Hopewell East. You, I can't remember

02:51:31.295 --> 02:51:42.038
- which date you approved ENB paving to come in and install footers, concrete footers at the site. They've

02:51:42.038 --> 02:51:48.382
- now completed that work as of early last week and now, sorry,

02:51:50.850 --> 02:51:58.881
- It's eight o'clock, my brain's fried. So this second amendment, we've had to do a lot of site prep work

02:51:58.881 --> 02:52:06.834
- for this project and we did not want to do it in July or August or even early September to accommodate

02:52:06.834 --> 02:52:14.711
- all of the plants that are in the park currently. We wanted to wait until the fall to wait for plants

02:52:14.711 --> 02:52:20.734
- in essence. And so that has extended the project and thus it's time to update

02:52:20.962 --> 02:52:28.946
- the agreement that we have with the artist, John Reisak Bunyama. And so his project, his installation

02:52:28.946 --> 02:52:36.774
- is on track to be installed the first week of December. That's what we're still targeting. But this

02:52:36.774 --> 02:52:44.758
- will be to accommodate any work or any potential, hopefully none, but any potential weather delays in

02:52:44.758 --> 02:52:50.942
- that installation. And so we're asking for an extension to March 31st of 2027.

02:52:53.890 --> 02:53:03.048
- And do you want to distinguish anything in terms of 2690 since you had offered to talk about both of

02:53:03.048 --> 02:53:12.478
- them? And so as part of site prep, we also need to run electrical conduit, bore for electrical conduit.

02:53:12.478 --> 02:53:22.814
- There is a lighting feature on the sculpture. And so this would accommodate for that. That work is with Snedeker.

02:53:23.074 --> 02:53:31.971
- I solicited quotes, and Snedeker submitted a quote for $19,000 to do that work. And there's a lag currently

02:53:31.971 --> 02:53:40.291
- because the concrete footers need to cure for 30 days before we can install the sculpture. And so if

02:53:40.291 --> 02:53:48.611
- we have this window right now, that will keep us on target for that December installation date. Yes?

02:53:48.611 --> 02:53:52.318
- Any questions or comments from commissioners

02:53:53.026 --> 02:54:00.659
- these resolutions because I'm going to, since it was presented jointly, welcome questions on both jointly

02:54:00.659 --> 02:54:08.004
- and we can do a motion jointly as long as there's no other ways. I've got a kind of a question, maybe

02:54:08.004 --> 02:54:15.349
- a little more general, but it's more pertaining to 90 than 89. So we have, we've made a commitment to

02:54:15.349 --> 02:54:21.182
- spending 1% of some number. I'm not really sure what that number ended up being.

02:54:22.658 --> 02:54:31.020
- So the foundation work and the electrical work and everything that the artist is doing, that all is

02:54:31.020 --> 02:54:39.633
- within that 1%? So the contract that we have with the artist says that the RDC will pay for site prep.

02:54:39.633 --> 02:54:48.246
- So it is beyond that initial commitment that you made. But it seems to me that 1%, which you're making

02:54:48.246 --> 02:54:51.006
- a commitment for an art project,

02:54:51.746 --> 02:55:01.965
- All of the work that goes into the art project ought to be part of that 1%. So I don't understand why

02:55:01.965 --> 02:55:11.984
- there's add-ons. 1% is the entire project. I see what you're saying, and it makes complete sense. I

02:55:11.984 --> 02:55:21.502
- don't really have an answer for you. I do not know what the total project cost was for the 1%.

02:55:21.730 --> 02:55:31.819
- off the cuff sorry we've come you've committed to a hundred thousand for the art for the sculpture and

02:55:31.819 --> 02:55:42.300
- that's broken down by with the artist and then you approved funding for EMB paving which was about $48,000

02:55:42.300 --> 02:55:50.430
- I believe and then this is an additional and I didn't think about it in that first

02:55:50.626 --> 02:55:58.874
- Resolution or the second resolution or I would have run it up then but I guess Maybe the ship is sailed

02:55:58.874 --> 02:56:07.519
- in this case, but I'll be looking at this differently And we say it's 1% and the numbers a hundred thousand.

02:56:07.519 --> 02:56:14.974
- That's a completion of at a hundred thousand and not Just the artist piece and then we've got

02:56:15.586 --> 02:56:23.912
- six other vendors that we gotta pay, and suddenly now we're up to 150,000. That's not what we signed

02:56:23.912 --> 02:56:32.569
- up for. I think that's wise, and I see that as well. In line with that, I would suggest and ask if there

02:56:32.569 --> 02:56:41.142
- would be a way for any 1% for the art project where there would be an addendum with any resolution that

02:56:41.142 --> 02:56:45.182
- has what the 1% is, how it's getting spent down,

02:56:45.506 --> 02:56:51.722
- And so just that it's not kind of buried in the whereas is that it's an actual, you know, budget that

02:56:51.722 --> 02:56:57.998
- would be an addendum to any of these because I think that would just be much more transparent in terms

02:56:57.998 --> 02:57:03.422
- of understanding how the money is being allocated and spent. Thank you for raising that.

02:57:15.138 --> 02:57:23.766
- That's a good question. I know our Assistant Director for the Arts in ESD is looking into maintenance

02:57:23.766 --> 02:57:32.394
- of all pieces that we have. One of our interns just over the summer went out to every piece of public

02:57:32.394 --> 02:57:41.022
- art that we have and did a conditions assessment. It's definitely something that's catching up to us.

02:57:41.346 --> 02:57:49.454
- The maintenance fund has historically been underfunded, so I know she's looking for ways to bolster

02:57:49.454 --> 02:57:57.644
- that. And our 1% for the arts doesn't mandate that we construct physical pieces of art. It just goes

02:57:57.644 --> 02:58:02.590
- to 1% of the arts. And so there's lots of ways you can fund.

02:58:02.754 --> 02:58:09.160
- the arts, not necessarily just physical capital infrastructure. No, I'm just looking at what we have

02:58:09.160 --> 02:58:15.565
- at the present moment in our community. I'm digressing. Excuse me, that's exactly what she's saying,

02:58:15.565 --> 02:58:21.971
- is that there's opportunities potentially in the future to use the 1% for the arts, not to build new

02:58:21.971 --> 02:58:28.440
- art, but to sustain existing. For any allocation for a given project, that some of it be dedicated to

02:58:28.440 --> 02:58:31.294
- a maintenance fund. A maintenance fund, yes.

02:58:31.778 --> 02:58:39.176
- dance performances, anything. I think we've traditionally gone towards capital projects. But you're

02:58:39.176 --> 02:58:46.575
- saying we can use that 1% for maintenance of existing projects. Yes. All right. So the next project

02:58:46.575 --> 02:58:54.491
- comes up. We can say, I'm sorry, your 1% for your building will now go to maintenance of the pre-existing.

02:58:54.491 --> 02:58:59.966
- It will come up during the police station discussion. OK. That works. OK.

02:59:00.930 --> 02:59:10.920
- got a collar on in our community and it has to be maintained and those things are achieved so thank

02:59:10.920 --> 02:59:21.410
- you. Okay so we have now heard for both resolution 2689 and 2690 I will ask for a motion for both unless

02:59:21.410 --> 02:59:29.502
- you choose to separate them. Move approval for resolution 2689 and 2690. Second.

02:59:29.858 --> 02:59:40.136
- We have a first and a second. All in favor say aye. Aye. Any opposed? Passes unanimously for both 2689

02:59:40.136 --> 02:59:50.613
- and 2690. Thank you. Okay, that is the end of new business on our agenda this evening. Is there anything

02:59:50.613 --> 02:59:57.598
- further for general discussion? Dinner. You're thinking of something?

02:59:57.730 --> 03:00:05.505
- I'll yield. I'll yield at the given the hour. I'll yield to the next meeting. Oh, we can't wait. Okay,

03:00:05.505 --> 03:00:13.053
- I'll take a motion to adjourn, please. So moved. Okay. Thank you all. We're trying to figure out if

03:00:13.053 --> 03:00:18.110
- this was it's not a record, but it's probably up there. So anyway.