- 3 PM. So, let me welcome all of you and call to order the meeting of the Monroe County Capital Improvement

00:00:07.845 --> 00:00:14.467
- Board for October 21st, 2026 at 3 PM here in the cookroom. So, we will begin with a call to order and

00:00:14.467 --> 00:00:21.284
- we'll take into the role. So, Mr. Whitledge, if you'd please take the role. Yes. John Weickart. Present.

00:00:21.284 --> 00:00:27.906
- Doug Bruce. Here. Jim Silberstein. Here. Jay Baer. Here. Joyce Poling. Here. Galen Cassidy. Here. And

00:00:27.906 --> 00:00:29.854
- Kyle Hannon. Here. Thank you.

00:00:30.114 --> 00:00:35.874
- Item number two, approval of the consent agenda. You've received the minutes of the board meeting of

00:00:35.874 --> 00:00:42.090
- September 16th, claims and a financial report. And before I ask for a motion, I'm going to ask Mr. Underwood

00:00:42.090 --> 00:00:47.964
- to explain something that's new to your packet. So this month, you'll notice that we had two different

00:00:47.964 --> 00:00:48.990
- claims registers.

00:00:49.090 --> 00:00:54.565
- the normal one for the construction side of things. But as we've begun to take over operations of the

00:00:54.565 --> 00:01:00.039
- existing facility, we now have a claims register for the operations side. So it'll be labeled for the

00:01:00.039 --> 00:01:05.675
- Bloomington Convention Center operations side. So you'll start seeing those two separate claims register

00:01:05.675 --> 00:01:11.042
- paid out of different sources of funds each month. And then down the road, we'll also have a second

00:01:11.042 --> 00:01:15.390
- financial report, which will also be for the operational side of things as well.

00:01:17.666 --> 00:01:24.706
- So may I have a motion to approve the Consent Agenda? Second. Moved and seconded. Is there any further

00:01:24.706 --> 00:01:31.542
- discussion or questions about the Consent Agenda? Seeing none, Mr. Whitlatch, if you would take the

00:01:31.542 --> 00:01:38.377
- roll. John Weichart? Yes. Doug Bruce? Yes. Jim Silverstein? Yes. Jay Baer? Yes. Joyce Polling? Yes.

00:01:38.377 --> 00:01:41.726
- Galen Cassidy? Yes. Kyle Hannon? Yes. Thank you.

00:01:42.082 --> 00:01:48.935
- Item number 3, Treasurer's Report, Mr. Silberstein. Yes, the good news is that our 2027 budget request

00:01:48.935 --> 00:01:55.722
- for construction was approved by City Council last week and that will be our last construction budget

00:01:55.722 --> 00:02:02.576
- on this project. Okay, thank you. Item number 4, President's Report, and we have change authorizations

00:02:02.576 --> 00:02:06.302
- that I've approved since our last meeting of $25,000 or

00:02:06.402 --> 00:02:13.451
- or under, I sent those out to you with the explanations for them, but you'll see them again in this

00:02:13.451 --> 00:02:20.501
- report, as well as the category under which they fall. And then you may want to call your attention

00:02:20.501 --> 00:02:28.044
- to where we are with the total contingency sum used to date and what percentage that is of the contingency

00:02:28.044 --> 00:02:32.062
- budget and the remaining contingency of over $1 million.

00:02:32.194 --> 00:02:40.078
- I'd be happy to answer any questions about the ones that I've approved that I sent out to you earlier.

00:02:40.078 --> 00:02:47.502
- If there are no questions, we'll move to item number five, the construction update from Weddell.

00:02:47.502 --> 00:02:54.238
- Thank you, John. Andrew Sherry, project manager at Weddell Brothers. Share screen here.

00:03:06.178 --> 00:03:12.378
- Okay so starting off with the construction progress update and then upcoming activities for the expansion

00:03:12.378 --> 00:03:18.227
- center project. This photo here is the southwest corner of the exhibit hall as you can see a lot of

00:03:18.227 --> 00:03:24.134
- overheads in place overhead painting and then actually this is the ceiling grid so preparing to drop

00:03:24.134 --> 00:03:30.334
- some tiles so this is a neat picture to see the bulkheads the paint and then the ceiling clouds in place.

00:03:31.714 --> 00:03:36.989
- Starting off on exterior concrete. So on the north side, the sidewalks and curves are completed. On

00:03:36.989 --> 00:03:42.686
- the west side, the curves are completed near the two near the connector location. Sidewalks are in progress

00:03:42.686 --> 00:03:47.962
- at the northwest entrance and progressing south. So this was this morning pouring the entrance here

00:03:47.962 --> 00:03:53.290
- at the northwest entrance. So on this side, we'll see a lot of the tree grates and accessories being

00:03:53.290 --> 00:03:58.618
- placed with our sidewalk pours. And then we're progressing into the paper bands, light poles, things

00:03:58.618 --> 00:03:59.198
- like that.

00:04:00.322 --> 00:04:05.844
- Also, we have metal panels. Metal panels are progressing on the parapet walls from the low roof to high

00:04:05.844 --> 00:04:11.153
- roof. The metal panels for the canopy will be progressing by the end of this month, starting on the

00:04:11.153 --> 00:04:16.568
- east elevation, starting to wrap up the canopy elevation. Our limestone feature walls, as you can see

00:04:16.568 --> 00:04:21.931
- here in this photo, this is the north feature wall. This is one of the change orders we talked about

00:04:21.931 --> 00:04:27.293
- a month or so ago, where we changed to the CMU wall. The CMU wall has been topped out, so now we are

00:04:27.293 --> 00:04:29.470
- preparing to start the limestone itself.

00:04:29.570 --> 00:04:35.675
- Again, it'll be a neat feature to see. And then the west limestone feature wall, we're planning to start

00:04:35.675 --> 00:04:41.897
- next week. Masonry work. So the last area for exterior brick is nearing completion, which is the southwest

00:04:41.897 --> 00:04:47.769
- elevation shown in this picture. So this is looking south on college. Masonry workers are working on

00:04:47.769 --> 00:04:53.758
- washing the exterior brick. And then on the column wraps, we'll be starting in the existing courtyard.

00:04:53.890 --> 00:05:00.629
- The glazing systems, the last curtain wall frame has been set on the project, which is the southwest

00:05:00.629 --> 00:05:07.634
- elevation here in the photo. The glazing is currently being installed, and then we're preparing to start

00:05:07.634 --> 00:05:14.506
- doors on the east entrance off of Walnut, the northeast entrance, and the northwest entrance. Also for

00:05:14.506 --> 00:05:15.774
- exterior progress,

00:05:15.874 --> 00:05:21.960
- We have the exterior equipment set on the back of house roof. So the dedicated outdoor air system,

00:05:21.960 --> 00:05:28.170
- the DOAS, as we call it, has been started and is supplying air into the building. This is one of the

00:05:28.170 --> 00:05:34.317
- three equipment locations shown in this photo on the right-hand side. Here are some exterior photos

00:05:34.317 --> 00:05:40.650
- on the left-hand side. You can see the northwest entrance. A photo on the top right of the patio area.

00:05:40.650 --> 00:05:44.830
- Bottom right would be the equipment and the roof tied in, dried in.

00:05:46.146 --> 00:05:52.349
- Again, patio photo here on the left coming into the main meeting space and then the doorway on the right

00:05:52.349 --> 00:05:58.375
- would take you to the grand stairs and the photo on the right hand side is the northeast entrance and

00:05:58.375 --> 00:06:04.520
- we are preparing to get metal panels here on site. We are procuring the canopy system, the glass canopy

00:06:04.520 --> 00:06:10.427
- to start to see that to get buttoned up. Interior progress for those that don't get to drive by and

00:06:10.427 --> 00:06:12.318
- see the inside drywall framing.

00:06:12.450 --> 00:06:17.654
- Drywall is nearing completion in all areas. Wall infills are completed in the exhibit hall. So what

00:06:17.654 --> 00:06:23.014
- we did is we left a few areas out to shoot the equipment up onto the mechanical mezzanines. Those have

00:06:23.014 --> 00:06:28.270
- been buttoned up or are getting buttoned up right now. And then second floor drywall is completed so

00:06:28.270 --> 00:06:33.474
- that our painters can start on Monday on the second floor. Rough ends, so termination points to the

00:06:33.474 --> 00:06:34.046
- equipment.

00:06:34.978 --> 00:06:39.560
- are being completed for the equipment startup to take place next week. So we actually have a meeting

00:06:39.560 --> 00:06:44.052
- tomorrow to start our phasing plan, starting each piece of equipment up. That includes electrical,

00:06:44.052 --> 00:06:48.816
- mechanical, and plumbing. And this photo right here on the right side is the north mechanical mezzanine.

00:06:48.816 --> 00:06:53.534
- So as you can see, the tie-in points are taking place, the equipment is set, the walls are buttoned up.

00:06:56.450 --> 00:07:01.534
- Interior progress. Painting is progressing throughout the building. Overhead paint is in progress above

00:07:01.534 --> 00:07:06.617
- ceilings in the exhibit hall. And then painting is starting on the second floor. The photo on the right

00:07:06.617 --> 00:07:11.896
- hand side is the North restroom. So we have our toilets being set, toilet partitions and toilet accessories

00:07:11.896 --> 00:07:16.980
- to be starting. Tile, the restroom tile is completed in the North restrooms. Corridor tile has started,

00:07:16.980 --> 00:07:22.112
- which we'll see in another photo. And then restrooms are in progress throughout the building. So there's

00:07:22.112 --> 00:07:25.534
- a lot of tile work on the project in the corridors, in the restrooms.

00:07:25.698 --> 00:07:31.058
- The water fountain areas, things like that. And again, we're progressing in all areas. Ceilings, so

00:07:31.058 --> 00:07:36.419
- the ceiling grid is progressing the exhibit halls we saw in the first photo I explained. The linear

00:07:36.419 --> 00:07:41.887
- ceilings are being installed in the corridors, which you can see on the right-hand side here. So this

00:07:41.887 --> 00:07:47.408
- is the east corridor looking north towards the northeast entrance. The ceilings up top, painted walls.

00:07:47.408 --> 00:07:52.286
- It's hard to see, but this little cubby here is the water fountain areas the tiles placed.

00:07:52.418 --> 00:07:58.524
- And then ceiling tiles are starting installation for the fixture trim-outs. Again, we're moving towards

00:07:58.524 --> 00:08:04.454
- the testing and balancing as we fire up the equipment. Also to note here, the kitchen build-out, the

00:08:04.454 --> 00:08:10.326
- walk-in cooler has started installation this week. And then kitchen equipment is starting to be set

00:08:10.326 --> 00:08:16.374
- also. We'll see a lot of that take place in the November timeframe. Here are some interior photos. The

00:08:16.374 --> 00:08:20.190
- photo on the left is from the window view from the second floor.

00:08:20.610 --> 00:08:28.101
- The photo on the right is all the mechanical and electrical terminations on the south mezzanine. Photo

00:08:28.101 --> 00:08:35.375
- on the left-hand side here is the south mezzanine and then a connector photo here on the right-hand

00:08:35.375 --> 00:08:42.793
- side. Thought this photo, these photos were showing the corridor, or I'm sorry, the restroom tile. So

00:08:42.793 --> 00:08:48.830
- the restroom tile is progressing very well. Upcoming activities, so interior work.

00:08:49.026 --> 00:08:55.156
- Floor coatings are starting in the back of house area. Floor carpet is starting in the corridors. Casework

00:08:55.156 --> 00:09:01.000
- and solid surfaces to be delivered next week for installation. Terrazzo stairs are being poured to be

00:09:01.000 --> 00:09:06.901
- procured to the project for the grand stair. Decorative railing is in fabrication for installation and

00:09:06.901 --> 00:09:12.802
- then toilet accessories and partitions to start in all the restrooms. This is a short list of the many

00:09:12.802 --> 00:09:14.750
- things that's going on right now.

00:09:15.586 --> 00:09:20.641
- Upcoming activities on the exterior side is sidewalks and curbs are to be completed. Site landscaping

00:09:20.641 --> 00:09:25.646
- is going to start taking place this month. The green roof is going to start installation this month.

00:09:25.646 --> 00:09:30.700
- South parking lot concrete pavement is going to start at the end of this month beginning in November.

00:09:30.700 --> 00:09:36.102
- The remainder of the asphalt patch along college will be completed and then metal panels will be progressing

00:09:36.102 --> 00:09:37.886
- around the entirety of the project.

00:09:40.642 --> 00:09:46.182
- Small notes here in the renovation, again, as we're starting to come into the last two to three months

00:09:46.182 --> 00:09:51.722
- here on the expansion side, we're starting to prep for the schedule on the existing convention center.

00:09:51.722 --> 00:09:57.154
- We have created all the renovation scope and logistics in our schedule. We're working on procurement

00:09:57.154 --> 00:10:02.533
- of equipment and materials for installation currently. And then one note we wanted to make is we've

00:10:02.533 --> 00:10:08.288
- worked with the owner here, the group, Delicious Team, to improve our end date to June 16th to accommodate

00:10:08.288 --> 00:10:09.310
- an upcoming event.

00:10:09.506 --> 00:10:17.891
- kudos to our team, everybody involved to see what we can do there and tie that together. And that's

00:10:17.891 --> 00:10:26.780
- the construction update. Yeah, let me place greater emphasis on that last bullet point about the improved

00:10:26.780 --> 00:10:35.333
- end date of the project. I was contacted a couple of weeks ago, Mike McAfee contacted me to say there

00:10:35.333 --> 00:10:36.926
- was an opportunity

00:10:37.282 --> 00:10:45.631
- to land a large conference in late June of 2027, but we had to be able to guarantee both buildings to

00:10:45.631 --> 00:10:53.981
- this large conference, and they had to be available to them by June 20th. And we're talking about 900

00:10:53.981 --> 00:11:02.494
- people. So I approached Weddle and asked them, is there any way we can move up the completion date from

00:11:02.494 --> 00:11:06.750
- June 28th to accommodate a conference on June 20th?

00:11:07.458 --> 00:11:14.950
- I met with all the parties they would need to meet with and came back to us and had a schedule to have

00:11:14.950 --> 00:11:22.733
- the completion of the renovation done by June 16th to accommodate that conference. Mike Mackey's estimated

00:11:22.733 --> 00:11:30.443
- that conference has a $500,000 economic impact to our community. And I just want to thank Weddle Brothers

00:11:30.443 --> 00:11:36.990
- for that effort. Mike's here and they signed the contract yesterday. So it's a done deal.

00:11:37.474 --> 00:11:45.202
- We've landed 900 people for June 20th of 2027 with that kind of an economic impact. And it's because

00:11:45.202 --> 00:11:52.931
- we work with our local partners and Weddle Brothers who take as much pride in making sure we can get

00:11:52.931 --> 00:12:00.889
- things done as all of us do. And I just want to thank them for that effort. So appreciate it very much.

00:12:00.889 --> 00:12:02.878
- Any questions for Andrew?

00:12:04.450 --> 00:12:10.533
- Yes, Mr. Bayer. Just one, because it's been a while. Maybe next month, if we have time, we could have

00:12:10.533 --> 00:12:16.557
- Andrew give us a little presentation on the scope and scale of the renovations over here. Yeah, that

00:12:16.557 --> 00:12:22.521
- would be no problem. Thanks. Absolutely. Item without, I didn't see any other questions. Let's move

00:12:22.521 --> 00:12:25.086
- to item number six, working group reports.

00:12:25.378 --> 00:12:31.098
- I don't believe we have a wayfinding report, is that correct? I have a presentation, just as an update.

00:12:31.098 --> 00:12:36.653
- Graphic House, the wayfinding science vendors have been working with Little Brothers on coordinating

00:12:36.653 --> 00:12:42.207
- install schedule. They submitted their shop drawings to us for review to make sure that what they're

00:12:42.207 --> 00:12:47.707
- proposing matches the design and then working with City of Bloomington on the science permitting so

00:12:47.707 --> 00:12:53.317
- that all can be here in time to reopen. Yes, thank you. And other things we've been working on behind

00:12:53.317 --> 00:12:54.142
- the scenes are

00:12:54.594 --> 00:13:00.369
- dedication plaques and things that go with the building. And we're already to that stage, which is very

00:13:00.369 --> 00:13:05.978
- exciting that we're working on those things now. Furniture, fixtures, and equipment, I don't believe

00:13:05.978 --> 00:13:11.586
- we have anything this month. We don't have anything this month. OK, thank you. And art installation,

00:13:11.586 --> 00:13:17.139
- the Beat Advisory Group. Gail, I think you have something for us. Just a quick update. We are close

00:13:17.139 --> 00:13:23.026
- to finalizing the call for artists for this next stage. Hope to release that in the next couple of weeks,

00:13:23.026 --> 00:13:24.414
- by the end of the month.

00:13:24.514 --> 00:13:33.352
- That call for artists will be open until kind of the second half of November. We will review the applicants

00:13:33.352 --> 00:13:41.536
- at that time and then present in December to the CIB the recommended selections that we have there.

00:13:41.536 --> 00:13:49.310
- So that call for artists will be available on MonroeCIB.com as well as the application portal.

00:13:49.634 --> 00:13:56.961
- There will be a FAQ on there for any questions and contact information if artists do have questions

00:13:56.961 --> 00:14:04.288
- about that call. Okay, thank you. Any questions for Galen? All right, thank you. Item number seven,

00:14:04.288 --> 00:14:11.908
- demolition on South Parcels update. Weddle, and I know there's a sequence of bullet points you're going

00:14:11.908 --> 00:14:16.158
- to go through with us. So, Andrew, are you starting that?

00:14:17.218 --> 00:14:22.982
- Yes, I'll be starting. I'll go through the environmental testing and the schedule and then hand it off

00:14:22.982 --> 00:14:29.082
- to Josh Nagle for the bid process and the recommendation. Starting off here with the south parcel demolition

00:14:29.082 --> 00:14:34.678
- again, just going to talk about the environmental testing update and the schedule update. So as far

00:14:34.678 --> 00:14:40.386
- as environmental testing, all the testing has been completed for both the site and the buildings. The

00:14:40.386 --> 00:14:47.102
- site testing, the site testing included soil and groundwater sampling. We'll note here that with coordination with VET,

00:14:47.234 --> 00:14:54.521
- They noted that this is one of the cleanest areas that they've ever observed in the downtown area. Very

00:14:54.521 --> 00:15:01.597
- surprising there with their testing, but great topic there. The boring samples noted a few locations

00:15:01.597 --> 00:15:09.374
- of elevated arsenic results. The arsenic is a natural occurring material and is very common in the local area.

00:15:09.474 --> 00:15:15.629
- If required, these can be disposed of at approved landfills. And then the current demolition scope is

00:15:15.629 --> 00:15:22.086
- not expected to have any soil removal. So don't expect this to affect the project. So again, great things.

00:15:22.086 --> 00:15:28.120
- As far as the building testing, the buildings were tested for lead paint and asbestos. So currently

00:15:28.120 --> 00:15:34.154
- we're waiting on the final analytical results for all structures, which we expect to have that this

00:15:34.154 --> 00:15:39.102
- week. Based on current evaluations, we have environmental exposures and structure

00:15:39.362 --> 00:15:44.446
- four and structure five, which is the Seminary Point apartment building and the Friendly Beast. So again,

00:15:44.446 --> 00:15:49.243
- with that, we'll wait on the final results, see what they are, the recommendation for abatement and

00:15:49.243 --> 00:15:54.087
- how we move forward. Remediation requirements, again, will be determined with the final results, and

00:15:54.087 --> 00:15:58.980
- then we'll just add that into our schedule. You know, if there's three out of the five buildings that

00:15:58.980 --> 00:16:04.016
- we can start on, we will. We'll identify those. Our schedule will be broke out into the five structures,

00:16:04.016 --> 00:16:06.558
- and then we will put an abatement activity in there.

00:16:08.130 --> 00:16:13.576
- but good news overall. In regards to the schedule, so the demolition schedule update permitting and

00:16:13.576 --> 00:16:19.240
- utility termination efforts are in progress. Those have been ongoing for a while now. The current goals

00:16:19.240 --> 00:16:24.741
- include mobilization, implementing the maintenance of traffic plans in November, again, to start our

00:16:24.741 --> 00:16:30.514
- mobilization. This will include fencing, barricades, and pedestrian diversions as we prep for demolition.

00:16:30.514 --> 00:16:35.525
- Demolition of the structures will start in November, starting at the structures that do not

00:16:35.525 --> 00:16:37.758
- have environmental remediation concerns.

00:16:38.114 --> 00:16:44.115
- or requirements. Again, the idea right now is the northern most buildings and our project team is still

00:16:44.115 --> 00:16:50.347
- progressing to have demolitions of the structures completed by the end of the year, which will be evaluated

00:16:50.347 --> 00:16:56.406
- further based on the environmental results that we get this week. So could be a pretty quick turnaround.

00:16:56.406 --> 00:17:02.234
- We're just going to show in our schedule of flow. So good things on the schedule. With that, I think

00:17:02.234 --> 00:17:07.774
- that we'll hand it to Josh Naga with Weddle Brothers for the bid process and the recommendation

00:17:12.290 --> 00:17:19.487
- Good afternoon, everyone. I'm Josh Nagel, Assistant Vice President of Pre-Instruction with Weddle Brothers.

00:17:19.487 --> 00:17:26.350
- As Andrew mentioned, I'm going to talk about the bidding process that we followed for the South Parcel

00:17:26.350 --> 00:17:33.147
- Demolition Project, go through the bid results, and then ultimately present a recommendation. So just

00:17:33.147 --> 00:17:38.878
- high-level bidding process. We released the documents on September 29th of this year.

00:17:39.074 --> 00:17:47.340
- These documents were posted publicly in the Herald Times on the Weddell Plain Room and Construct Connect,

00:17:47.340 --> 00:17:55.216
- which is an industry plan distribution service that covers the nation. We posted to adhere to public

00:17:55.216 --> 00:18:03.014
- bidding laws in the Herald Times on September 28th and on October 5th. We held a pre-bid meeting at

00:18:03.014 --> 00:18:08.862
- the job site on October 6th, and we received bids and opened them publicly

00:18:08.994 --> 00:18:18.559
- on October 13th. Bids were reviewed per Indiana code 202636-1-12-4A. And those are the bidding procedures

00:18:18.559 --> 00:18:27.852
- for public projects over $300,000. There was a prequalification element to the project beyond just the

00:18:27.852 --> 00:18:36.966
- pricing, which was conducted via Form 96, which is a standard bidding form for public works projects

00:18:36.966 --> 00:18:38.590
- within the state.

00:18:38.690 --> 00:18:47.531
- We also had a supplemental Weddle Brothers pre-qualification. We primarily use that information to collect

00:18:47.531 --> 00:18:55.876
- safety information and manpower information from bidders. We did not use that pre-qualification as a

00:18:55.876 --> 00:19:04.303
- sole method to qualify or disqualify any bidders, but we use that as a supplement there. That was the

00:19:04.303 --> 00:19:06.782
- process that we went through.

00:19:07.266 --> 00:19:14.950
- And then we received six bids. And there was a range of bids here. I have Denny excavating highlighted

00:19:14.950 --> 00:19:22.410
- in green. I will get to that on the next slide. But just showing the green demo, they were a bidder

00:19:22.410 --> 00:19:30.392
- from La Porte, Indiana. Dor was from Michigan. And then the rest of the bidders were from central Indiana.

00:19:30.392 --> 00:19:36.062
- There's no local bidders from the city of Bloomington that presented there.

00:19:36.194 --> 00:19:43.549
- So there's a range of numbers. If we go to the next slide. So our bid analysis of the four bidders.

00:19:43.549 --> 00:19:51.051
- So we went through a scope review to make sure that the project requirements were understood, that no

00:19:51.051 --> 00:19:58.406
- gaps in coverage. And what we found with green demos, the low bidder, they were missing significant

00:19:58.406 --> 00:20:05.982
- amounts of scope. They were unfamiliar with local requirements, whether it be with CBU or coordinating

00:20:06.146 --> 00:20:12.849
- city of Bloomington requirements, and they also had no on-site supervision. So that was a concerning

00:20:12.849 --> 00:20:19.551
- point for us in evaluating their proposal. The next two bidders, Dorr and Renescent, did not include

00:20:19.551 --> 00:20:26.320
- their financial statement, which according to the Form 96, it is an automatic disqualification. So we

00:20:26.320 --> 00:20:30.302
- were then moving on to the fourth bidder, Denny Excavating.

00:20:30.434 --> 00:20:38.313
- They had complete bid documents, they had complete scope, complete supervision, everything that we expected

00:20:38.313 --> 00:20:45.754
- to see in the bid. So with that, on the next slide here, so we are coming today with a recommendation

00:20:45.754 --> 00:20:51.006
- to award to Denny Excavating for a total of $660,000, utilizing the AIA

00:20:51.170 --> 00:21:00.321
- A132 agreement between owner and contractor. And this is the CMA edition, which brings Weddle Brothers

00:21:00.321 --> 00:21:09.738
- in as the manager to oversee the transfer of information between the CIB and Denny excavating. All right.

00:21:09.738 --> 00:21:18.622
- So we have that recommendation and that review from Weddle Brothers. I'm going to ask Mr. Whitlatch

00:21:19.618 --> 00:21:27.428
- what he proposes we do as a recommendation. There's an action by the board now, and then if we have

00:21:27.428 --> 00:21:35.629
- a motion and a second to that effect, then we can discuss that. Thank you. It would be my recommendation

00:21:35.629 --> 00:21:43.829
- that the board consider this recommendation with a motion and a second, obviously, and that if the board

00:21:43.829 --> 00:21:47.422
- does approve the recommended Denny excavating

00:21:47.682 --> 00:21:54.882
- a contract has been included. Obviously, the contract has not been signed. It would be my recommendation

00:21:54.882 --> 00:22:02.014
- with approval of the bid that the board also give approval to John Weichart to work with me to get that

00:22:02.014 --> 00:22:09.145
- contract in final form. We will certainly bring the contract back next month for final or for the board

00:22:09.145 --> 00:22:16.003
- to review, but we would like to keep the project moving forward and give John the authority to sign

00:22:16.003 --> 00:22:17.374
- the contract, which

00:22:17.474 --> 00:22:25.891
- which was provided by Weddle Brothers as part of the project. So the recommendation or the process would

00:22:25.891 --> 00:22:33.988
- be to approve the bid and to approve John signing the contract once we get it in acceptable form. So

00:22:33.988 --> 00:22:42.565
- that's the recommendation. Do we have a motion to accept that recommendation? So moved. Is there a second?

00:22:42.565 --> 00:22:46.814
- Second. So is there discussion? Are there questions?

00:22:48.674 --> 00:22:55.387
- Mr. Baird. This budget comes out of contingency, is that correct? Or construction? Yeah, Mr. Underwood.

00:22:55.387 --> 00:23:02.101
- This will come out of contingency on the soft cost side. Because we didn't necessarily know at the very

00:23:02.101 --> 00:23:08.620
- beginning that we were going to, the demolition was part of this project at the beginning. So that's

00:23:08.620 --> 00:23:14.430
- why it's contingency, not a budget. Correct. So it's not a part of the construction bond.

00:23:15.010 --> 00:23:22.810
- or the contingency for the construction bond. It's on the food and beverage side. Any other questions?

00:23:22.810 --> 00:23:30.535
- Okay, seeing none, Mr. Whitlatch, so we have a recommendation. It's been moved and seconded, and I'll

00:23:30.535 --> 00:23:38.259
- ask you to please take the roll. John Weichart? Yes. Doug Bruce? Yes. Jim Silverstein? Yes. Jay Baer?

00:23:38.259 --> 00:23:44.318
- Yes. Joyce Polling? Yes. Galen Cassidy? Yes. Kyle Hannon? Yes. Okay, thank you.

00:23:45.634 --> 00:23:56.335
- All right. So we move then on to item number eight, Anticipated Site Map for the South Parcels.

00:23:56.335 --> 00:24:08.151
- And again, we're back to Mr. Sherry from Weddle Brothers. Thank you, John. See if I can. I'm just second.

00:24:08.151 --> 00:24:10.046
- I want to share.

00:24:15.074 --> 00:24:22.078
- And is there any way that you can share that logistics plan I sent over? Thank you. Oh, there it is.

00:24:22.078 --> 00:24:29.152
- Apologize. It's working now. OK, so our team got together and just wanted to kind of show a logistics

00:24:29.152 --> 00:24:36.641
- plan of what we were thinking and how all this ties together with the demolition and the hotel development.

00:24:36.641 --> 00:24:43.923
- So on the logistics plan here, you can see the hotel footprint. And then we sat down and tried to really

00:24:43.923 --> 00:24:44.894
- think through

00:24:45.122 --> 00:24:51.493
- What do we need and what do we have as far as utilizing the property? So some things to think about

00:24:51.493 --> 00:24:57.992
- on our end was parking, the office setup, the lay down, which is slightly larger because this project

00:24:57.992 --> 00:25:04.363
- is slightly larger. Also the two way egress for construction traffic deliveries and coordination to

00:25:04.363 --> 00:25:10.989
- try to limit staying off of College or Second Street. Equipment and staging area due to larger concrete

00:25:10.989 --> 00:25:14.430
- structures. So thinking about concrete pumps, cranes,

00:25:14.594 --> 00:25:21.479
- things like that, and then porta pots, dumpsters, and other accessories. So on this site, again, we

00:25:21.479 --> 00:25:28.778
- tried to draw this as close as possible to scale, but in here you can see how we would propose to utilize

00:25:28.778 --> 00:25:35.663
- the site. Again, this is very early stages. We would finalize this plan, but two gates coming in to

00:25:35.663 --> 00:25:40.414
- show egress. We would have lay down over here on the left-hand side.

00:25:40.706 --> 00:25:46.611
- Um, and employee storage, a lot of this would be Connex boxes, trailers, forms, depending on where we

00:25:46.611 --> 00:25:52.226
- were with the project, we would leave this North area open for staging, uh, and equipment again,

00:25:52.226 --> 00:25:58.189
- you know, thinking about cranes, concrete trucks, uh, pump trucks, things like that dumpster location.

00:25:58.189 --> 00:26:03.804
- Again, we, from a logistic standpoint, we want to have that as close to the project as possible.

00:26:03.804 --> 00:26:09.246
- And then, uh, porta pots in the restrooms, we are going to lose, um, uh, significant parking.

00:26:09.474 --> 00:26:16.128
- as far as employee parking. So we're trying to think about that. We showed the employee parking here

00:26:16.128 --> 00:26:23.242
- in blue, and then the construction office and management parking. So the assumption is to have job trailers

00:26:23.242 --> 00:26:29.962
- down there, temporary services as far as electric, things like that. So again, this is just a general

00:26:29.962 --> 00:26:36.286
- overview of the thought currently of how the site would be utilized as the hotel was developed.

00:26:39.554 --> 00:26:47.919
- So once construction of the hotel begins, which is anticipated to be 18 to 22 months, this would be

00:26:47.919 --> 00:26:55.615
- how all the parcels would be used during that construction phase. Yes, sir. So for the next

00:26:55.615 --> 00:27:04.065
- hotels anticipated to open in 2029. So this would be how the parcels would be used up to that point.

00:27:04.065 --> 00:27:09.502
- Yes. OK. Any questions, Mr. Bear? Between now and then, if Denny

00:27:10.242 --> 00:27:16.626
- finish the contract with them, they do the demolition. Do they then put asphalt where it is now so that

00:27:16.626 --> 00:27:22.948
- they can do lay down lot and construction trailers and all that? Or what's the surface of this at that

00:27:22.948 --> 00:27:29.147
- point? The surface at the end of the demolition scope is going to be topsoil and stabilized, so seed

00:27:29.147 --> 00:27:35.838
- and straw. And then, yes, and then it'll be developed. The lot would be put in place when the hotel started.

00:27:39.874 --> 00:27:46.085
- So during the design process, the design stage and all of that, we would be accommodating the

00:27:46.085 --> 00:27:53.286
- city requirements for the lot. Proceed and straw, yeah. Yeah, and then after that, when it's groundbreaking,

00:27:53.286 --> 00:28:00.091
- a movement to construction, then this would be how it would be used, with the adaption of the area for

00:28:00.091 --> 00:28:06.963
- that use. Yeah, I'm just wondering if we have to pave this in order to build the hotel next door. Yeah.

00:28:06.963 --> 00:28:08.350
- Any other questions?

00:28:11.906 --> 00:28:19.147
- Okay, thank you, Mr. Sherry. Thank you. All right, that concludes those items. And now we, item number

00:28:19.147 --> 00:28:26.317
- nine is old business. Is there any old business to be brought before the board? Seeing none, is there

00:28:26.317 --> 00:28:33.699
- any new business to be brought before the board? Again, seeing none, item number 11, comments from board

00:28:33.699 --> 00:28:37.214
- members. Any board member comments at this point?

00:28:39.490 --> 00:28:45.706
- All right, seeing none, move on to number 12, comments from the public. So we set aside a 10-minute

00:28:45.706 --> 00:28:51.922
- period at the end of each meeting. For the public to make comments that are limited to two minutes,

00:28:51.922 --> 00:28:58.324
- we've established some policies and rules on comments. And so at this point, if there are those in the

00:28:58.324 --> 00:29:04.664
- public who would like to make comment, you are welcome to come to the microphone. And please identify

00:29:04.664 --> 00:29:07.710
- yourself, please, for the record when you do so.

00:29:11.394 --> 00:29:25.998
- Amber Core with Bloomington Homes for All. I didn't prepare anything to say. Mostly, I just want to

00:29:25.998 --> 00:29:40.894
- point out that it seems like the plan for the hotel footprint and then what extends beyond it, south,

00:29:43.138 --> 00:29:55.131
- seems like an excuse to demolish affordable housing when you don't really have any other idea with what

00:29:55.131 --> 00:30:06.778
- you want to do with it now. And you already have staging equipment set up for the convention center.

00:30:06.778 --> 00:30:10.238
- I'm sure you have dumped your

00:30:10.402 --> 00:30:22.675
- dumpster locations, employee parking, and construction offices for this project. I understand that that

00:30:22.675 --> 00:30:34.712
- might need to be extended in some way, but to demolish the entire site for this purpose seems absurd.

00:30:34.712 --> 00:30:39.550
- And this land was originally transferred

00:30:39.682 --> 00:30:53.470
- by the Monroe County Council for a land swap. And we need to consider still using it for that land swap

00:30:53.470 --> 00:31:06.064
- to save the affordable housing and get the hotel at the right location at Bunger and Robinson.

00:31:06.064 --> 00:31:09.246
- Thank you. Anyone else?

00:31:14.370 --> 00:31:20.607
- Mr. Green, welcome back. Please identify yourself for the record. You are correct. I am Mr. Green and

00:31:20.607 --> 00:31:26.905
- I am back. I'm with Bloomington Homes for All. I'd just like to echo what Amber's saying. I mean, this

00:31:26.905 --> 00:31:33.081
- process is far enough along, but I will recap the fact that this is affordable housing that is being

00:31:33.081 --> 00:31:39.379
- demolished. And it's not only being demolished for a hotel, it's being demolished for a hotel, despite

00:31:39.379 --> 00:31:41.886
- the fact that many members of the county

00:31:42.082 --> 00:31:47.854
- Council and County Commission have spoken out against this idea. Also from the fact that the public

00:31:47.854 --> 00:31:53.683
- has been very unanimous in their voice that they would like to keep affordable housing. And also the

00:31:53.683 --> 00:31:59.397
- City Council has sent a letter saying that they would like affordable housing. And the Bloomington

00:31:59.397 --> 00:32:05.630
- Redevelopment Commission has also said that they were open to talking about ways to preserve the affordable

00:32:05.630 --> 00:32:08.574
- housing. For whatever reason, this body has sought

00:32:09.026 --> 00:32:15.816
- to move forward with the destruction of affordable housing to give it to a private developer for a hotel.

00:32:15.816 --> 00:32:22.543
- Now, I think I can speak for most people when I say that this is not a good way to spend city resources,

00:32:22.543 --> 00:32:29.013
- especially when we're in a housing crisis and there doesn't seem to be any way to get any more units

00:32:29.013 --> 00:32:35.483
- of that cost point into Bloomington. So we're permanently destroying affordable housing. I just want

00:32:35.483 --> 00:32:38.558
- it on the record that this is what is going on.

00:32:38.690 --> 00:32:45.079
- that this is a conscious choice to do so. And a number of members of this body have gone on record saying

00:32:45.079 --> 00:32:51.286
- that they don't believe it's their job to assist in developing Bloomington's affordable housing stock.

00:32:51.286 --> 00:32:57.374
- And that may be true on a technical level, but on a human level, on the level that I think we should

00:32:57.374 --> 00:33:03.461
- be acting on, and that should be the basis of any government sanction action, on a human level, it's

00:33:03.461 --> 00:33:08.222
- just wrong. And it's just bad city policy. And it's very disappointing to see.

00:33:08.962 --> 00:33:16.119
- We'll be continuing to raise our voices and make the details of this issue known to as many people as

00:33:16.119 --> 00:33:23.206
- possible. Thank you. Anyone else for public comment? Mike McAfee from Visit Bloomington. I just want

00:33:23.206 --> 00:33:30.223
- to thank Mr. Weichardt and the board and Mr. Sherry and Weddle for adjusting the schedule for us to

00:33:30.223 --> 00:33:37.310
- help with that group. It's actually a large sporting event that'll be here for about a week in June.

00:33:37.506 --> 00:33:42.973
- It was touch and go there for a little while. We weren't sure we were gonna, even after they rearranged

00:33:42.973 --> 00:33:48.282
- the schedule, I was nervous about being able to meet the hotel block, but we made some calls and the

00:33:48.282 --> 00:33:53.592
- actual reason we were able to do it is because it was in late June. Probably wouldn't have been able

00:33:53.592 --> 00:33:59.006
- to put that hotel block together if it wasn't late June or July. That's why this new hotel is critical

00:33:59.006 --> 00:34:04.263
- for the convention center to meet its potential. We have to have the room block down the road. I've

00:34:04.263 --> 00:34:05.630
- been at this a long time.

00:34:05.730 --> 00:34:12.963
- I remember when these two lots were purchased in 2012 for this purpose within Keepers Tax. There's no

00:34:12.963 --> 00:34:20.055
- surprises here of what's going on. We made it publicly known. We're building a hotel and convention

00:34:20.055 --> 00:34:27.146
- center. That's 15 years ago. And I just thank you for keeping moving forward. Appreciate all you're

00:34:27.146 --> 00:34:34.238
- doing. Any other public comment? Anyone online? All right, that concludes the public comment phase.

00:34:34.754 --> 00:34:41.590
- Item 13, next board meeting is November 18th, 2026 at 3 p.m. And I would note on the agenda that we've

00:34:41.590 --> 00:34:48.492
- announced the, oh, I'm sorry, before we get to that, Mr. Baird, did you want to make a report on, we're

00:34:48.492 --> 00:34:55.328
- back to almost the furniture fixtures and equipment on where we are with the AV process? I don't think

00:34:55.328 --> 00:35:01.964
- there's a report yet, just other than that we are meeting the subgroup on the audio visual provider

00:35:01.964 --> 00:35:03.358
- for both the new and

00:35:03.650 --> 00:35:11.064
- Refashioned Convention Center. We're going to start looking at the proposals for that soon. And so we

00:35:11.064 --> 00:35:18.478
- should have a report in November. Okay, thank you. So back to where I left off. New dedication is set

00:35:18.478 --> 00:35:25.747
- for Tuesday, January 12th at 2 p.m. So by all means, get that on your calendars as well. And we are

00:35:25.747 --> 00:35:31.998
- at item 14. You don't have to go home, but you can't stay here. And we are adjourned.