00:00:00.226 --> 00:00:07.317
- Here. Jim Silberstein, I believe, is absent. Joyce Poling? Here. Jay Baer? Here. Galen Cassidy? Here.

00:00:07.317 --> 00:00:14.618
- Kyle Hannon? Here. Thank you. Item number two is approval of the consent agenda. You would have received

00:00:14.618 --> 00:00:21.779
- the minutes of the board meeting of October 21st, the claims and financial report. And if I could have

00:00:21.779 --> 00:00:25.950
- a motion to approve the consent agenda. So moved. It's been

00:00:26.050 --> 00:00:32.708
- Moved by member polling, seconded by member Bruce. Any questions or discussion? All right, seeing and

00:00:32.708 --> 00:00:39.431
- hearing none, would you take the roll, please? John Wyckart? Yes. Doug Bruce? Yes. Joyce Polling? Yes.

00:00:39.431 --> 00:00:45.959
- Jay Baer? Yes. Galen Cassidy? Yes. Kyle Hannon? Yes. Item number three, the Treasurer's Report. The

00:00:45.959 --> 00:00:52.682
- Treasurer is not with us today, so we'll skip to item number four, the President's Report. And we will

00:00:52.682 --> 00:00:55.358
- begin with the change orders this month.

00:00:55.618 --> 00:01:02.867
- We can have those up. All right. The first, you're going to see two pages of listings of change orders.

00:01:02.867 --> 00:01:09.838
- The first one are the change orders of under $25,000 that I've already circulated to all of you. So

00:01:09.838 --> 00:01:17.087
- I will ask at this point, if you have any questions about those that I've already approved, that you've

00:01:17.087 --> 00:01:19.806
- already had an opportunity to look at.

00:01:22.242 --> 00:01:30.619
- Okay, if not, we'll move to the request for over $25,000. And Mary, did you want to handle this? Sure,

00:01:30.619 --> 00:01:38.997
- I can explain a bit about this. CA-69 is for the West Limestone Future Wall. This is actually a credit

00:01:38.997 --> 00:01:47.618
- coming back from the full change that we had approved in a previous meeting. So this is the credit coming

00:01:47.618 --> 00:01:50.302
- back to the CIB for that effort.

00:01:51.042 --> 00:01:59.648
- CA 72 is the existing building window remediation. They've done some prep work to review the conditions

00:01:59.648 --> 00:02:08.172
- of the existing windows and what they might get into as we go into the spring with that work. And this

00:02:08.172 --> 00:02:15.454
- is some remediation work that is anticipated throughout the window replacement process.

00:02:15.618 --> 00:02:23.143
- That work in itself is funded through the CVC, so it's not actually coming directly out of the CIB budget.

00:02:23.143 --> 00:02:30.528
- Yes, so that's the, as Mary just said, that's the money that came to us from the Convention and Visitors

00:02:30.528 --> 00:02:37.772
- Commission for the alternates that they have funded on our behalf. So may we take these in one motion,

00:02:37.772 --> 00:02:39.038
- Mr. Whittle? Yes.

00:02:39.298 --> 00:02:46.731
- Okay, do we have a motion then to approve the Change Authorization 69 and 72? So moved. So moved. Is

00:02:46.731 --> 00:02:54.310
- there a second? It's been seconded. Any questions or discussion? All right, seeing none, hearing none,

00:02:54.310 --> 00:03:01.964
- would you please take the roll? John Weickart? Yes. Doug Bruce? Yes. Joyce Pauling? Yes. Jay Baer? Yes.

00:03:01.964 --> 00:03:07.998
- Galen Cassidy? Yes. Kyle Hannon? Yes. Okay, thank you. And then we have a second.

00:03:08.098 --> 00:03:15.265
- page as well. And Mary, I'll let you explain why we're doing this in a sort of a two-page system here.

00:03:15.265 --> 00:03:22.293
- Right. This is for the wayfinding project of which Schmidt Associates is leading. This is for adding

00:03:22.293 --> 00:03:29.321
- bronze plaques to the project as well as for new electrical monument sign. This comes out of, again,

00:03:29.321 --> 00:03:36.766
- a different budget. This comes out of the food and beverage budget, so it's separated from the hard costs.

00:03:36.866 --> 00:03:43.219
- that we were just looking at. So the first one for plaques is one that I'm authorized to sign with the

00:03:43.219 --> 00:03:49.511
- authority you've given me. We have two plaques that will go on the building I've shared with you. One

00:03:49.511 --> 00:03:55.987
- of them is the plaque that recognizes the county's contribution to the history of the convention center.

00:03:55.987 --> 00:04:02.340
- The second one is the dedication plaque. I haven't shared that one with you yet because as a surprise,

00:04:02.340 --> 00:04:05.918
- your names are on it. So I didn't want you to see it yet.

00:04:06.754 --> 00:04:13.275
- So I guess what we need is a motion for the oh, and I'm sorry, so I can approve that. So let's move

00:04:13.275 --> 00:04:19.796
- then to the second one, which does require board authorization. Correct. And if there's any detail,

00:04:19.796 --> 00:04:26.382
- Eddie could speak to that. Yeah, I was actually going to say that there is a electrical for monument

00:04:26.382 --> 00:04:33.033
- sign authorization coming probably next month. There's three. That total, that amount actually is for

00:04:33.033 --> 00:04:34.142
- the foundations.

00:04:35.266 --> 00:04:42.848
- the form, there was an error on the form. So they just got translated to the slide. That amount is for

00:04:42.848 --> 00:04:50.283
- some modifications to the directional signage exterior foundations to match field conditions. I just

00:04:50.283 --> 00:04:57.645
- want to clarify that. That's correct in the paperwork. It's just on the slide. It got mixed up. OK.

00:04:57.645 --> 00:05:03.902
- OK. So this needs to be correctly identified as foundations for the monumental sign.

00:05:04.514 --> 00:05:11.167
- directional signs for the directional signs throughout okay and that's so there's multiples yes and

00:05:11.167 --> 00:05:18.021
- then that's and that's the uh double a dash zero one correct okay the dollar correct the dollar amount

00:05:18.021 --> 00:05:24.807
- is correct it's the description that's incorrect okay so the description will will be changed to read

00:05:24.807 --> 00:05:32.126
- what um it's for um modified foundations for directional signage okay so modified foundations for directional

00:05:33.346 --> 00:05:44.740
- Signage is what we will amend, AA-01. So it still has the same cost, $38,242. A rose is still a suite.

00:05:44.740 --> 00:05:56.797
- So is there a motion to approve that change? Is there a second? Second. OK, so it's been moved and seconded.

00:05:56.797 --> 00:06:03.102
- Any questions? Just one. So we had a $60,000 contingency

00:06:03.266 --> 00:06:10.091
- And so remaining is eighty eight hundred. How do we feel about other issues that might come up? Yeah,

00:06:10.091 --> 00:06:16.916
- so the electrical, the one that's labeled there, but it's coming is going to be after this decide how

00:06:16.916 --> 00:06:23.808
- we handle that, because it's going to probably put us over the sixty thousand total. Just with the way

00:06:23.808 --> 00:06:30.366
- the things worked out, the. Those foundations, I guess you might ask, what's the reason for that?

00:06:30.498 --> 00:06:36.671
- Why are we getting, why are we seeing that? And that's just the change in the way the scheduling has

00:06:36.671 --> 00:06:42.782
- worked out on them, getting them onsite and what they need to do to get those foundations installed

00:06:42.782 --> 00:06:49.138
- compared to what they had assumed during the bid process. Working with VITO to make sure that the whole

00:06:49.138 --> 00:06:55.371
- projects they don't schedule and things are moving without holding up the overall progress. Does that

00:06:55.371 --> 00:06:58.366
- answer your question? Okay, any other questions?

00:07:00.162 --> 00:07:08.197
- Okay. So we have a motion and a second. If you would take the role, please. John Whitehart. Yes.

00:07:08.197 --> 00:07:16.730
- Doug Bruce. Yes. Joyce Pauling. Jay Bear. Gailen Cassidy. Yes. Kyle Hannon. Yes. Okay. Thank you. Item

00:07:16.730 --> 00:07:25.345
- number five, construction update. Weddell. Mr. Sharon. Thank you, John. Yes. Andrew Sharon with Weddell

00:07:25.345 --> 00:07:27.582
- Brothers. Share my screen.

00:07:36.770 --> 00:07:42.447
- Okay, so in today's presentation, we'll talk about the construction progress currently, the upcoming

00:07:42.447 --> 00:07:48.461
- activities, the details of the renovation that we discussed last month, and then the south parcels update.

00:07:48.461 --> 00:07:54.082
- For exterior concrete, so our north sidewalks are completed along with the east. The west sidewalks

00:07:54.082 --> 00:07:59.422
- are in progress. We're actually south of the connector with our curb works nearing completion.

00:07:59.650 --> 00:08:05.736
- We're just prepping for the paving on the east side of college to take place at the end of this month,

00:08:05.736 --> 00:08:11.703
- beginning of December. And then our south lot is going to be started following our west sidewalk, so

00:08:11.703 --> 00:08:18.084
- flowing straight into there. We have bollards on site, our accessories and everything prepped for subgrade.

00:08:18.084 --> 00:08:24.170
- Again, just prepping for our concrete pavement down there. Our exterior progress, our metal panels are

00:08:24.170 --> 00:08:26.238
- on the north side of the building.

00:08:26.370 --> 00:08:31.769
- On the east elevation, this picture here is the northeast entrance. So it shows the point where all

00:08:31.769 --> 00:08:37.437
- the panels come together from the two elevations. Pretty neat photo. And then we actually had a delivery

00:08:37.437 --> 00:08:42.943
- today that gets us to the patio area and then we will be heading south on college in the next week or

00:08:42.943 --> 00:08:48.342
- so. The masonry work, our exterior brick work is completed on the building, excluding the limestone

00:08:48.342 --> 00:08:53.794
- and feature walls. And then the extra brick column wraps are in progress at the connector. So button

00:08:53.794 --> 00:08:55.198
- up some loose ends there.

00:08:55.330 --> 00:09:01.209
- Again, we tied our last window in. All the masonry work has topped out around the facade. Again, the

00:09:01.209 --> 00:09:07.145
- limestone feature walls are in progress, which actually look very good. They're making great progress

00:09:07.145 --> 00:09:13.198
- on those on the north side right now. Here's a photo as of this morning. I wanted to include this. It's

00:09:13.198 --> 00:09:19.019
- hard to see, but it just shows the textured stone that we've been talking about. They're actually a

00:09:19.019 --> 00:09:23.966
- course or two higher than this as of right now, but the north limestone feature wall

00:09:24.066 --> 00:09:29.384
- has limestone in progress. The west feature wall has the CMU laid to the second floor level. We have

00:09:29.384 --> 00:09:34.649
- added some supplemental steel, which we discussed has been approved. That is actually starting this

00:09:34.649 --> 00:09:40.125
- week. It will be delivered to start with crews on Monday. The glazing systems, all glazing is completed

00:09:40.125 --> 00:09:45.548
- at the window locations. Areas remaining include miscellaneous glazing at the entrances along with the

00:09:45.548 --> 00:09:50.919
- connector. These pieces we expect to button up by the end of this week. Again, the side lights around

00:09:50.919 --> 00:09:52.446
- the doors, things like that.

00:09:54.274 --> 00:09:59.544
- Other exterior improvements, our landscaping material is going to be delivered to the site next week.

00:09:59.544 --> 00:10:04.866
- Bike shelters to start installation. Exterior pavers will be starting by the end of the month, working

00:10:04.866 --> 00:10:10.136
- east towards west. And then our limestone benches are going to be delivered in December. Again, those

00:10:10.136 --> 00:10:15.613
- sit underneath the connector at the existing convention center courtyard and on the east side of college.

00:10:15.613 --> 00:10:20.883
- So to kind of help with the column wraps there. Here's some exterior photos. Photo on the left is the

00:10:20.883 --> 00:10:24.190
- southwest window, the last window that we were set on the site.

00:10:24.386 --> 00:10:30.381
- The middle photo is the patio looking towards the east. And then the photo on the right are the metal

00:10:30.381 --> 00:10:36.612
- panels on the east elevation. They are buttoned up all the way to the registers lot. We have been working

00:10:36.612 --> 00:10:42.489
- on Sundays with discussions and coordinations with Jim himself to get access in there and button up

00:10:42.489 --> 00:10:48.778
- the south side of the building. Here are some neat photos on the interior side of the project. So interior

00:10:48.778 --> 00:10:53.598
- progress drywall completed throughout the building other than the elevator shaft.

00:10:53.762 --> 00:10:59.945
- This is frame, we have shaft liner up. They're buttoning up the drywall now. The rough ends termination

00:10:59.945 --> 00:11:06.187
- points to equipment are nearing completion. We will be completed this week on the remaining items. Fluid

00:11:06.187 --> 00:11:12.310
- cooler, the chiller, things like that. Heat pumps and everything are hooked up. The photo on the right

00:11:12.310 --> 00:11:18.018
- hand side is what it looks like inside at the Northeast entrance. So you can see the wall tile,

00:11:18.018 --> 00:11:20.574
- the paint, the six foot light fixtures and

00:11:20.738 --> 00:11:26.118
- The carpet, that's a big feat for the project. The flooring and base is ongoing. Continuing with the

00:11:26.118 --> 00:11:31.498
- interior progress, so painting. Painting is nearing completion throughout the building. Again, we're

00:11:31.498 --> 00:11:37.038
- falling back and doing final coats as areas button up. Overhead paint is completed in the exhibit hall,

00:11:37.038 --> 00:11:42.578
- and then we are prepping to start the wall coverings. The tile, as you can see here on the right photo,

00:11:42.578 --> 00:11:48.385
- this is the west corridor looking north. The north restrooms are completed. The north corridor is completed.

00:11:48.385 --> 00:11:50.462
- West restrooms are nearing completion.

00:11:50.562 --> 00:11:55.516
- West corridor is in progress as you can see here. And then the second floor restrooms are in progress.

00:11:55.516 --> 00:12:00.326
- Ceilings, the ceiling grid is nearing completion in the exhibit hall. Linear ceilings are completed

00:12:00.326 --> 00:12:05.280
- in the east and north corridors with the west corridor and second floor currently in progress. Ceiling

00:12:05.280 --> 00:12:10.427
- tiles continue to drop in the exhibit hall. I think we have another photo of that. And then light fixtures

00:12:10.427 --> 00:12:15.670
- continue behind the ceiling installation. So throughout the building, the can lights, the six foot fixtures,

00:12:15.670 --> 00:12:19.518
- the wall lighting, recess lighting everywhere. As far as the kitchen build out,

00:12:20.354 --> 00:12:25.570
- Slides are going faster than I can read. As far as the kitchen build out, the freezer, the cooler, the

00:12:25.570 --> 00:12:30.787
- dish machine, and other equipment has been set. We plan to have all kitchen equipment in the building,

00:12:30.787 --> 00:12:35.851
- in the room, in place by this Friday. So we're getting deliveries all day, every day this week. The

00:12:35.851 --> 00:12:40.915
- photo on the right-hand side is the dish room. So as you can see, the ceiling grid is in. They need

00:12:40.915 --> 00:12:46.334
- to drop tiles in there. Flooring is down, base is down, the epoxy flooring back there. It looks very good.

00:12:49.026 --> 00:12:54.090
- Additional interior progress. So casework has been set in the restrooms with the tile completed. Solid

00:12:54.090 --> 00:12:59.055
- surface underneath all the windows is in progress. It's actually completed in the east and the north

00:12:59.055 --> 00:13:04.069
- corridors. Carpet is completed in the east corridor and continues in the north corridor about halfway

00:13:04.069 --> 00:13:08.985
- down. Flooring is completed in the kitchen and the dish room. Toilet partitions and accessories are

00:13:08.985 --> 00:13:14.098
- in progress in all restrooms with tile completed and we are actually prepping for all door and hardware

00:13:14.098 --> 00:13:15.966
- to be placed throughout the building.

00:13:17.346 --> 00:13:23.624
- Here are some interior photos. The photo on the left is looking north out of the main entrance of the

00:13:23.624 --> 00:13:30.086
- exhibit hall. So the six-foot fixtures are there. As you can see, the floor prep is underway with carpet

00:13:30.086 --> 00:13:36.302
- being laid. The photo on the right-hand side is the north corridor looking east, or I'm sorry, west.

00:13:36.302 --> 00:13:42.764
- Again, halfway down the corridor currently with carpet. Photo on the left-hand side is the exhibit hall.

00:13:42.764 --> 00:13:45.534
- So dropping tiles, ceiling grid buttoned up.

00:13:45.730 --> 00:13:52.009
- We are actually looking the far side there is the west side of the exhibit hall first area that we finished

00:13:52.009 --> 00:13:57.997
- with overhead tiles being completed and then running the center bay and the easternmost bay. The photo

00:13:57.997 --> 00:14:03.986
- on the right hand side is the east corridor looking south so that corridor is basically complete other

00:14:03.986 --> 00:14:09.858
- than the wall coverings. Other interior photos photo on the left hand side again is the exhibit hall

00:14:09.858 --> 00:14:14.974
- just showing the cloud ceiling structure. The photo in the middle is the north corridor

00:14:15.714 --> 00:14:22.273
- And then on the right hand side, this is the North mezzanine. So again, we have the DOAS running. We're

00:14:22.273 --> 00:14:29.083
- firing up heat pumps for testing, functional testing, things like that. And all terminations, duct hookups,

00:14:29.083 --> 00:14:35.516
- electrical and everything. Upcoming activities. So mill work to be set at the entrance desk and under

00:14:35.516 --> 00:14:41.885
- the stairs at the seating area. Decorative railing to be delivered and installed. Terrazzo stairs to

00:14:41.885 --> 00:14:43.966
- be set at the monumental stairs.

00:14:44.162 --> 00:14:50.152
- flooring to start in the exhibit hall, trim out to be in progress. So this will be the covers, the grills,

00:14:50.152 --> 00:14:55.917
- fire alarm, controls, everything like that. And then this week we actually have all the overhead doors

00:14:55.917 --> 00:15:01.683
- being placed on the exterior part of the building. On the right hand side here, it's hard to see, it's

00:15:01.683 --> 00:15:07.393
- a little dark in there, but these are the toilet partitions in the restrooms with the tile completed,

00:15:07.393 --> 00:15:13.046
- ceilings in place. Again, just waiting to drop tile in there. Upcoming activities for exterior work,

00:15:13.046 --> 00:15:13.662
- sidewalks,

00:15:13.794 --> 00:15:18.832
- to be completed on the west side, including the tree grates, landscaping material to be delivered next

00:15:18.832 --> 00:15:23.771
- week, bike shelters to start installation, exterior pavers will be starting by the end of the month,

00:15:23.771 --> 00:15:28.809
- working east towards west, limestone benches being delivered again in December, paving to be completed

00:15:28.809 --> 00:15:33.700
- along the east curbs, College Avenue, and then the overhead doors. The photo on the right-hand side

00:15:33.700 --> 00:15:38.640
- is the patio, which actually has the roof prep in progress right now. They're buttoning that up. And

00:15:38.640 --> 00:15:42.846
- then decorative railing has been field measured and is currently in fabrication here.

00:15:45.666 --> 00:15:51.877
- So we had talked kind of switching gears here to the renovation. So after we get done at the expansion,

00:15:51.877 --> 00:15:58.028
- the renovation work, again, we plan on starting that in January to be done by June. The original scope

00:15:58.028 --> 00:16:04.179
- had selective demolition, flooring, ceilings, walls, et cetera, ceiling rework, removing and reworking

00:16:04.179 --> 00:16:10.271
- flooring in certain areas, new walls, floorings, and lights at the connector area, and then reworking

00:16:10.271 --> 00:16:13.854
- and replacing finishes. So the photo on the right-hand side

00:16:14.178 --> 00:16:19.826
- coming into the left-hand side of the photo is the connector. I actually had to spin this to fit the

00:16:19.826 --> 00:16:25.529
- slide. But we actually build a little corridor there. Whenever you walk off the connector, you'll hit

00:16:25.529 --> 00:16:31.121
- the corridor wall and then come into the main meeting space up here, upstairs here. Furthermore, we

00:16:31.121 --> 00:16:36.880
- actually wanted to mention the approved alternates. So in increase from the base bid, we had alternate

00:16:36.880 --> 00:16:42.695
- three, which was replacing the existing building HVAC units and replacing original heat pump that we're

00:16:42.695 --> 00:16:43.422
- going to do.

00:16:43.554 --> 00:16:48.831
- Alternate four was the existing kitchen improvements. This includes removing and replacing flooring

00:16:48.831 --> 00:16:54.424
- and mechanical, electrical and plumbing work and additional architectural improvements as far as painting

00:16:54.424 --> 00:16:59.806
- and finishes. Alternate five was the masonry repairs at the exterior, which includes retuck pointing,

00:16:59.806 --> 00:17:05.399
- which is again, just reworking the masonry joints on 25% of the building, which we're working to identify

00:17:05.399 --> 00:17:10.939
- what areas need the improvement the most. Alternate six is replacing all the existing windows throughout

00:17:10.939 --> 00:17:11.678
- the building.

00:17:12.386 --> 00:17:18.597
- Alternate 7 is replacing the dedicated outside air system. And then Alternate 13 is removing and replacing

00:17:18.597 --> 00:17:24.401
- the surveillance system, reworking the structured data cabling, which is new racks and data cabling

00:17:24.401 --> 00:17:30.264
- itself, and enhancing the audio video to integrate the existing building with the new expansion into

00:17:30.264 --> 00:17:36.300
- one system. So again, these are all things that we were doing on top of the base bid. Andrew, if I may,

00:17:36.300 --> 00:17:41.118
- Alternate 3 and Alternate 13 were the alternates we approved in September of 2025.

00:17:41.506 --> 00:17:47.484
- and then the remaining alternates were the ones that have been funded by the Convention and Visitors

00:17:47.484 --> 00:17:53.759
- Commission. Yes. Thank you. With that, we will note that the renovation logistics, so existing Convention

00:17:53.759 --> 00:17:59.737
- Center will be non-accessible during the renovations, again, with it being an open job site. We will

00:17:59.737 --> 00:18:05.716
- be about everywhere in the building, especially with the window replacement. We are working with the

00:18:05.716 --> 00:18:11.102
- Convention Center team to accommodate signage, access, and other needs during renovations.

00:18:11.202 --> 00:18:16.534
- We'll come up with the final logistics plan, accessibility. I know that shuttles, things like that for

00:18:16.534 --> 00:18:21.815
- events have been discussed. The bus lane at the new expansion helps. These are all details that we're

00:18:21.815 --> 00:18:27.406
- talking about. I do want to note also that the connector will not be utilized until the existing convention

00:18:27.406 --> 00:18:32.583
- center renovations are completed, which we've talked about. So basically upstairs at the expansion,

00:18:32.583 --> 00:18:37.864
- you'll have the double doors. Those will have signage on it and be locked. And then we will button up

00:18:37.864 --> 00:18:41.022
- the connector as we tie into the existing convention center.

00:18:44.546 --> 00:18:50.766
- Switching gears again to the south parcels. So just a small update on the south parcels. Demolition

00:18:50.766 --> 00:18:57.049
- activities did begin yesterday. So if you've drove by buildings, I think the Friendly Beast building

00:18:57.049 --> 00:19:03.581
- is halfway or more down now. We did implement the fencing and maintenance of traffic plan last Wednesday

00:19:03.581 --> 00:19:09.988
- on November 11th. Did all of our pre-demo inspections, our SWIP reviews, things like that. The project

00:19:09.988 --> 00:19:11.294
- is on schedule to be

00:19:11.458 --> 00:19:17.416
- completed by December 31st. That does include all demolition and site stabilization, seed and straw.

00:19:17.416 --> 00:19:23.552
- And I do want to note on here, one thing that we talked about was, you know, what are the environmental

00:19:23.552 --> 00:19:29.628
- requirements and testing and, you know, the answers there as far as the analytical results. We did not

00:19:29.628 --> 00:19:35.763
- have any impacts to the project schedule or the sequence based off the findings. So that was great news

00:19:35.763 --> 00:19:38.654
- for the project schedule. And that should be it.

00:19:39.682 --> 00:19:46.292
- OK, questions for Andrew. He shifted gears on us a couple of times. So whatever questions you may have,

00:19:46.292 --> 00:19:52.775
- Mr. Bear. Just one for Andrew, maybe for Galen. The large exterior art piece, does that install begin

00:19:52.775 --> 00:19:59.131
- after the conclusion of the renovations to this building or contemporaneous with those renovations?

00:19:59.131 --> 00:20:05.804
- It's after. I think the schedule for the art installation was that would be complete in October of 2027.

00:20:05.804 --> 00:20:07.838
- Any other questions for Andrew?

00:20:09.762 --> 00:20:16.339
- a lot to absorb. Appreciate all of it. Thank you very much. Thank you. I just want to go over and use

00:20:16.339 --> 00:20:23.109
- the bathrooms over there. Pardon me? Just go over and use the bathrooms. Yeah. You can have first flush.

00:20:23.109 --> 00:20:29.556
- Thank you. Got a hard hat though. Oh, I thought we were going to auction that. You're just going to

00:20:29.556 --> 00:20:30.846
- give it away? Okay.

00:20:31.394 --> 00:20:38.093
- All right, item number six, working group reports. I know, Eddie, we have wayfinding on the approval

00:20:38.093 --> 00:20:44.859
- list. Anything else from wayfinding? No, we're just working through final approvals of submittals and

00:20:44.859 --> 00:20:52.022
- samples as they get ready for installation in December. Thank you. Next item under working group, furniture

00:20:52.022 --> 00:20:56.798
- fixtures and equipment JS held. I know you have something for us, Mary.

00:20:57.410 --> 00:21:04.675
- We do just to level set. We've been through the process of bidding items that needed to be bid items

00:21:04.675 --> 00:21:12.084
- that need to be quoted. We are down to detail with items with direct purchase. We have Julie Hutchison

00:21:12.084 --> 00:21:19.925
- from Reload Strategies here who's managing that and she'll report with the next slide. Sure, Julie Hutchison

00:21:19.925 --> 00:21:26.974
- with Relocation Strategies here with the direct purchase items. There were 17 items that we have.

00:21:27.106 --> 00:21:34.743
- And the total amount, seventy six thousand three hundred and seventy six dollars. Did you need me to

00:21:34.743 --> 00:21:42.456
- read through those or no, no. Okay. We would look for approval to move forward with these. We've been

00:21:42.456 --> 00:21:50.169
- working with Jeff on the direct purchases. We'll be back in December for a few more, but otherwise we

00:21:50.169 --> 00:21:52.286
- should be wrapping that up.

00:21:52.450 --> 00:21:58.559
- But we would look for approval for this. And these are all within the budget that we've created? Yes,

00:21:58.559 --> 00:22:04.549
- we've done an excellent job of staying within that FF&E budget. I know you're looking at a list for

00:22:04.549 --> 00:22:10.658
- the first time, but if you have questions, otherwise we have a recommendation for approval. Why don't

00:22:10.658 --> 00:22:16.647
- we do this? Is there a motion to approve the direct purchase items? Let's get a motion and a second

00:22:16.647 --> 00:22:21.918
- and then we can have discussion if we need to. It's been moved. Seconded. And seconded.

00:22:22.498 --> 00:22:36.029
- Uh, is there any discussion or questions? All right. I don't, I don't see any, um, Mr. Whitlatch has

00:22:36.029 --> 00:22:49.828
- wandered off someplace, so I'm wondering. Okay. Okay. Yes. If you please take the role. Yes. Yes. Yes.

00:22:49.828 --> 00:22:51.838
- Yes. Yes. Yes.

00:22:52.226 --> 00:23:00.985
- OK, thank you. Thank you. The next one, Galen, anything on the art installation for this month? Just

00:23:00.985 --> 00:23:09.831
- to update, the Call for Artists is live right now. It's on munrocib.com. A few other places I've seen

00:23:09.831 --> 00:23:18.590
- too online. The deadline for the Call for Artists is November 27th by 5 p.m. So at this point, we've

00:23:18.722 --> 00:23:26.299
- We've heard from nearly 30 artists with some submissions, and it's resulted in over 60 pieces that we

00:23:26.299 --> 00:23:33.950
- have so far. But it is definitely very active still. And again, find that at mirocib.com. You can have

00:23:33.950 --> 00:23:41.973
- questions. My contact is on there for any questions you may have about the application process or anything.

00:23:41.973 --> 00:23:48.510
- OK, any questions for Galen? All right, moving on to contract approvals, Mr. Whitlatch.

00:23:48.866 --> 00:23:57.354
- Yes, thank you. We have three contracts that need approval. We are not quite ready for the MCL Convention

00:23:57.354 --> 00:24:05.362
- Center catering, so we're taking that off the list. Ken's Westside Towing for Towing for Convention

00:24:05.362 --> 00:24:13.530
- Center parking lots needs to be approved. The Rigger Engineering Firm, we have a proposal for them to

00:24:13.530 --> 00:24:17.694
- do a subdivision of lot A, which is the parking lot

00:24:17.794 --> 00:24:25.755
- Uh, just to the south of the current convention center, we're subdividing off about 25% of that anticipating

00:24:25.755 --> 00:24:33.790
- that that would then be available as part of the hotel expansion project or part of the hotel project rather.

00:24:33.922 --> 00:24:40.657
- Uh, host hotel project, and then the vet phase two environmental actually was, uh, signed and approved

00:24:40.657 --> 00:24:47.261
- as part of the prior approval that you'd given us on the environmental and that work, but we'll also

00:24:47.261 --> 00:24:53.996
- provide that and approve that. So I would need a motion to approve the Ken's West side towing the BRJC

00:24:53.996 --> 00:25:00.927
- lot subdivision and, uh, ratify or approve the, uh, environmental for phase two related to the demolition

00:25:00.927 --> 00:25:02.366
- of the South parcels.

00:25:03.106 --> 00:25:10.987
- Okay, so is there a motion to approve those three contracts? So moved. Is there a second? I'm going

00:25:10.987 --> 00:25:18.947
- to get Mr. Hannon into the minute. I'll second that. Okay, so we've got a motion. You're not in yet?

00:25:18.947 --> 00:25:27.222
- I'll get you in here. All right, so we have a motion and a second. Are there any questions or discussion

00:25:27.222 --> 00:25:33.054
- about those three contracts? Seeing none, if you'd take the roll, please.

00:25:33.186 --> 00:25:40.507
- John Weichart? Yes. Doug Bruce? Yes. Joyce Pulling? Yes. Jay Baer? Yeah, it's figured out for two and

00:25:40.507 --> 00:25:47.828
- a half years. Yes. Kaelan Cassidy? Yes. Kyle Hannon? Yes. I don't know if this makes anybody nervous,

00:25:47.828 --> 00:25:55.221
- but Mr. Baer is going to be the emcee at the dedication. Okay, thank you. All right. So moving to item

00:25:55.221 --> 00:26:02.398
- eight, old business. Is there any old business to be brought before the board by any board members?

00:26:04.354 --> 00:26:09.655
- Seeing none, any new business to be brought before the board by a board member? Seeing none, item number

00:26:09.655 --> 00:26:14.804
- 10, comments from board members? Any comments from board members? I have a comment as a board member.

00:26:14.804 --> 00:26:20.105
- And now the microphone is working, which is an experience operator error. I don't do this professionally

00:26:20.105 --> 00:26:25.255
- anymore, as you know. Just a quick note, this is my last in-person meeting. I'll be here virtually in

00:26:25.255 --> 00:26:30.505
- December. I'm taking my leave of the board in January. The mayor has a replacement lined up, but I will

00:26:30.505 --> 00:26:33.534
- be delighted as my last official duty to to emcee our grand

00:26:33.762 --> 00:26:41.008
- a grand opening. Thank you. And Mr. Rivera, thank you for your participation as a board member and much,

00:26:41.008 --> 00:26:47.909
- much appreciated. OK, so comments from the public. Item number 11, anyone from the public choose to

00:26:47.909 --> 00:26:55.018
- make a comment. You have two minutes. We've set aside 10 minutes at the end of each meeting for public

00:26:55.018 --> 00:27:02.195
- comments. So anyone care to make a two minute or less public comment? OK, I don't see anyone in person,

00:27:02.195 --> 00:27:03.230
- anyone online.

00:27:04.002 --> 00:27:11.133
- Okay. No one online. So moving to item number 12, the next board meeting is December 16th at 3pm. But

00:27:11.133 --> 00:27:18.335
- as always, I want to note the dedication of the new expansion is Tuesday, January 12th at 2pm. So item

00:27:18.335 --> 00:27:23.998
- number 13, you don't have to go home, but you can't stay here. We are adjourned.