WEBVTT

00:00:00.000 --> 00:00:07.920
-  Let me call this meeting of the new county redevelopment commission to order on march 26 2025

00:00:07.920 --> 00:00:17.600
-  Commissioner martin yes commissioner cassidy president commissioner mccarty yes commissioner

00:00:17.600 --> 00:00:25.840
-  talker present we have three voting members and one non-voting member present so we have a quorum

00:00:25.840 --> 00:00:37.920
-  all right how you do you want to proceed with these reports do you want to present them

00:00:37.920 --> 00:00:47.680
-  i think we will let uh present the financial solutions group group present them i would ask

00:00:47.680 --> 00:00:54.560
-  tsc if you could i'm trying to log into this so if you could log me into the meeting and then give

00:00:54.560 --> 00:01:00.720
-  me the ability to share that way i can try to keep up with him as he moves along so the

00:01:00.720 --> 00:01:24.800
-  people at home can follow you promote charlie as well

00:01:24.800 --> 00:01:28.880
-  uh

00:01:28.880 --> 00:01:42.880
-  you've been made a presenter

00:01:42.880 --> 00:01:49.840
-  good afternoon this is charlie can you guys hear me

00:01:52.880 --> 00:02:00.960
-  just fine all right can i share my screen is that possible or or jeff will you

00:02:00.960 --> 00:02:06.640
-  do that um if you if they can give you the ability i seem to be having trouble getting

00:02:07.440 --> 00:02:29.200
-  in all right how about that can you see my screen it should show the curry profile tiff district

00:02:29.200 --> 00:02:37.280
-  report yes okay perfect i'll start with that one if that's okay and we'll just go through

00:02:37.280 --> 00:02:45.360
-  these um alphabetically and i'll kind of hit the highlights and if um anybody has a question or

00:02:45.360 --> 00:02:57.680
-  wants to go into more detail uh we can do that okay so um curry profile we did on the old ge

00:02:57.680 --> 00:03:06.000
-  property um is basically what that area entails um and if we go to page three we've got a little

00:03:06.000 --> 00:03:14.080
-  bit of a summary here um we authorized six million one hundred and seventy five thousand of tiff

00:03:14.080 --> 00:03:14.560
-  bonds

00:03:14.560 --> 00:03:22.880
-  um to help finance the project there um this unfortunately kind of got caught up in the time

00:03:22.880 --> 00:03:28.400
-  of covid and there were some other delays there and really there hasn't been a lot of new

00:03:28.400 --> 00:03:29.040
-  development

00:03:29.040 --> 00:03:36.480
-  there and the developer has only drawn a hundred and three thousand two hundred dollars on that tiff

00:03:36.480 --> 00:03:43.920
-  bond so we authorized over six million they they didn't draw that um we've started to pay that back

00:03:43.920 --> 00:03:51.200
-  because there has been some tiff revenue there and we have about fifty two thousand dollars

00:03:51.920 --> 00:04:01.360
-  left to pay on the bonds so if we um i'll go to that um here's our debt service schedule

00:04:01.360 --> 00:04:09.520
-  it's two and a half percent the bonds were issued in 2018 um fifty two thousand is what's remaining

00:04:09.520 --> 00:04:16.640
-  we'll we pay that as much pay that down as much as we can um with the tiff revenue that does come

00:04:16.640 --> 00:04:16.800
-  in

00:04:18.320 --> 00:04:26.400
-  and we do pay interest on those bonds and i'll skip to this page this is our cash flow

00:04:26.400 --> 00:04:33.840
-  all the tiff revenue goes into the county fund 4934 so we've gotten about twenty five thousand

00:04:33.840 --> 00:04:41.520
-  dollars um in 23 and 24 for tiff revenue and then the the claims there the majority of that

00:04:42.080 --> 00:04:49.200
-  is for debt service on the bonds so we've got a five thousand dollar balance we've kind of said

00:04:49.200 --> 00:04:54.800
-  that's our minimum that we want to keep in there just in case we have some expenses we don't expect

00:04:54.800 --> 00:05:03.760
-  and then i'll go down you can see the assessed value in 22 it was a million 480 that we captured

00:05:03.760 --> 00:05:10.960
-  just about the same in 23 and 24 and we've had a little bit of growth in 25 so almost three million

00:05:10.960 --> 00:05:19.520
-  dollars of assessed value um captured for 25 that's going to bring in based on the 25 tax rate

00:05:19.520 --> 00:05:19.760
-  about

00:05:19.760 --> 00:05:26.400
-  forty six thousand dollars so probably not enough to pay the bonds off totally but we're going to

00:05:26.400 --> 00:05:36.560
-  be real close to getting those paid off if not in 25 then in 26 so that's kind of the highlights on

00:05:36.560 --> 00:05:45.920
-  curry profile are there any questions on that report yes once we pay off this bond

00:05:45.920 --> 00:05:56.080
-  there is nothing else planned in terms of improvements so any collections we would

00:05:56.080 --> 00:06:04.480
-  get would then become excess probably because there's no plan for them so does it make sense

00:06:04.480 --> 00:06:13.840
-  to pay off this bond or keep this bond open for a while give us some options for using the accumulating

00:06:13.840 --> 00:06:25.840
-  tiff revenue on other projects like curry pike that is a great question um and part of it would

00:06:25.840 --> 00:06:33.920
-  be up to the developer so they they own the bond and they could draw on it if there was something

00:06:33.920 --> 00:06:40.800
-  going on out there but i i do think what you said makes the most sense to pay this off and then

00:06:40.800 --> 00:06:48.400
-  the rdc could decide if you would keep it open and we would have to make sure that the

00:06:48.400 --> 00:06:55.600
-  authorizing documents allow for the money to be spent on those other projects so you know that

00:06:55.600 --> 00:07:02.080
-  that would be the the discussion there and i think the developer we would want to include in those

00:07:02.080 --> 00:07:07.920
-  discussions to make sure what their project you know are they truly gone as far as they can go

00:07:07.920 --> 00:07:14.320
-  or want to go on that or you know what is their plan going forward i would say that unlike our

00:07:14.320 --> 00:07:20.800
-  west the west side tiff this this tiff would not end with when that bonds paid off right so in the

00:07:20.800 --> 00:07:27.040
-  west side tiff if we pay off the 2015 bond that kind of and if all the bonds are paid off then

00:07:27.040 --> 00:07:31.580
-  that tiff district would end and that's because it when it was established and then the rules

00:07:31.580 --> 00:07:32.080
-  changed

00:07:32.080 --> 00:07:39.760
-  prior to 2015 and then we had we issued a bond to to kind of set the life of that and that life is

00:07:39.760 --> 00:07:47.040
-  set with the same time period as that bond this one we could get rid of the bond and i would say

00:07:47.040 --> 00:07:52.800
-  i know the developer and i and this is no way trying to disparage the developer but in a

00:07:52.800 --> 00:07:58.800
-  hypothetical situation if you closed out the bond then there would be no ability to get the rest of

00:07:58.800 --> 00:08:05.200
-  that six million dollars out and in terms of projects and then you could add i'd have to

00:08:05.200 --> 00:08:10.000
-  relook at what's currently in that tiff but you could add certainly add that part of that curry

00:08:10.000 --> 00:08:15.600
-  pike project because it's right alongside of it to the tiff plan for the curry profile and

00:08:15.600 --> 00:08:21.440
-  then you could use the money for that i mean we could i guess my feeling is that if we're going

00:08:21.440 --> 00:08:25.920
-  we're going to get close to paying it off next year maybe we should look at you know the tiff

00:08:25.920 --> 00:08:33.040
-  plan and then maybe adding the curry profile to it to help fund that project is that a boundary

00:08:33.040 --> 00:08:39.840
-  extension or just a document extension as far as it would just be adding projects to to the current

00:08:39.840 --> 00:08:45.520
-  geographically it's surrounded by the by the website tiff so i don't think you could expand

00:08:45.520 --> 00:08:51.280
-  the boundaries of it but it would be adding projects to the to the list essentially that would have

00:08:51.280 --> 00:08:51.440
-  an

00:08:51.440 --> 00:09:00.480
-  overlapping ability to pay from two particular tips if necessary i think that i think for the most

00:09:00.480 --> 00:09:01.200
-  part

00:09:01.200 --> 00:09:06.400
-  most a lot of the curry pike you can say is physically connected or serves that property

00:09:06.400 --> 00:09:12.590
-  and so that's kind of the the benchmark i think if you get if you get south of third street that

00:09:12.590 --> 00:09:12.800
-  may

00:09:12.800 --> 00:09:18.720
-  become more of an issue or north and there's geographics where you it's it becomes harder

00:09:18.720 --> 00:09:24.640
-  to make that discussion but i think at least for that part that's close to that i think it's easily

00:09:24.640 --> 00:09:30.640
-  said to be connected to that project that's discussions needs to be had with the developer

00:09:30.640 --> 00:09:37.680
-  accordingly to how once we pay it off here a year and a half from paying i think once one i want

00:09:37.680 --> 00:09:37.680
-  and

00:09:37.680 --> 00:09:41.760
-  i think we can't have it with the developer but i think once the bond's paid off you don't have to

00:09:41.760 --> 00:09:46.560
-  right i mean given that they're the sole property owner for this tiff district it makes a lot of

00:09:46.560 --> 00:09:49.920
-  sense to keep them in the loop and make sure that they're comfortable with what we're doing

00:09:49.920 --> 00:09:56.000
-  so i'm not saying you shouldn't i'm just saying it's not necessarily a requirement it's a good idea

00:09:56.000 --> 00:10:01.600
-  is that good something of that nature if we look at it in the next

00:10:01.600 --> 00:10:05.680
-  two to five years does that assist the highway department in their budgeting for that

00:10:10.960 --> 00:10:17.280
-  that's that's basically we broke it into three segments to be able to afford it not put so much

00:10:17.280 --> 00:10:25.840
-  strength allocated it definitely helps everybody yeah because they're also alongside it and a

00:10:25.840 --> 00:10:32.960
-  beneficiary of in a way of those improvements right even though they're included in it i mean

00:10:32.960 --> 00:10:40.080
-  it's twofold i guess right they're they're part of it and there'd be the a beneficiary of of the

00:10:40.080 --> 00:10:46.720
-  improvements yeah at this present moment moving forward on that we know based on the financial

00:10:46.720 --> 00:10:53.040
-  analysis here we're a year around a year year and a half to get it paid off but that gives time to

00:10:53.040 --> 00:10:59.680
-  have discussions with the developer and then add projects in if need be so we can move forward

00:10:59.680 --> 00:11:06.240
-  move forward allocate right yeah and our highway department can determine if there's anything else

00:11:06.240 --> 00:11:14.160
-  that would serve this property as well that i can't think of any but you know it's you'd ever know

00:11:14.160 --> 00:11:20.800
-  and we don't have to worry about sun setting if it's paid correct okay we still yeah

00:11:20.800 --> 00:11:23.860
-  thank you

00:11:23.860 --> 00:11:29.680
-  all right any other questions on curry profile

00:11:32.720 --> 00:11:38.800
-  oh yeah one quick question on that when we say we only they've only drawn about 103 000 on that

00:11:38.800 --> 00:11:45.680
-  that's just the amount that we have that once we pay back the 103 that bond is closed well we in

00:11:45.680 --> 00:11:51.440
-  discussions with the with the property owner that that that is their desire is to get that paid off

00:11:51.440 --> 00:11:57.600
-  and then close out that bond that is what what they have requested from us and that 103 dollars

00:11:57.600 --> 00:12:06.000
-  or 103 000 essentially was the closing cost of the bond itself so none of that or if any of that it's

00:12:06.000 --> 00:12:11.200
-  very little went into actual projects and they did do quite a bit of work on the site

00:12:11.200 --> 00:12:17.680
-  well i mean legally assessed value increase yeah yeah increase shows that

00:12:20.800 --> 00:12:32.320
-  okay that sounds good let's move on to fullerton pike um same kind of thing you guys are familiar

00:12:32.320 --> 00:12:39.760
-  with our reports um there's a lot of information here i won't go through every page of that um

00:12:39.760 --> 00:12:48.640
-  this um this situation uh with our tax rate i do want to point that out that

00:12:49.200 --> 00:12:56.400
-  the tax rate has been declining for the last several years um and also point out that this

00:12:56.400 --> 00:13:03.680
-  particular area is in the Monroe county school district they've got two referendum tax rates

00:13:03.680 --> 00:13:12.640
-  that are included in the total but we do not get to capture those so um very steady decrease

00:13:12.640 --> 00:13:22.160
-  in in tax rate um which impacts our tiff revenue the second page here is our cash that we've got

00:13:22.160 --> 00:13:31.920
-  at the county level um it's fund 4922 um we've had a pretty consistent cash balance year to year

00:13:31.920 --> 00:13:40.480
-  on this one at the end of 24 we had just over 566 thousand dollars of tiff revenue in there

00:13:42.160 --> 00:13:47.520
-  we don't produce a lot of tiff out there right now it's been pretty steady at about 150 thousand

00:13:47.520 --> 00:13:57.040
-  but we do have a large bridge project um going on uh that we've funded some from our tiff

00:13:57.040 --> 00:14:03.280
-  but it's also you know the bulk of the funding has come from the county major bridge fund

00:14:03.280 --> 00:14:11.760
-  and then the county did a bond issue to to pay for um the remainder that we couldn't pay from cash

00:14:12.640 --> 00:14:21.520
-  so we would expect this 566 thousand plus whatever tiff revenue we bring in this year

00:14:21.520 --> 00:14:25.120
-  to go towards completing that big bridge project

00:14:25.120 --> 00:14:36.560
-  here's our assessed value that we've captured um like i said it's been pretty consistent

00:14:37.120 --> 00:14:43.680
-  and you can see that tax rate going down and um when we remove those referendum rates it's a it's

00:14:43.680 --> 00:14:50.720
-  really a very low tax rate that we capture out there so with that i'll wrap fullerton

00:14:50.720 --> 00:15:03.600
-  pike up and ask for any questions on that area okay um when i look at the analysis of cash and

00:15:03.600 --> 00:15:17.760
-  investments i look at mounted if settlement that grow across and i look at the historical assessed

00:15:17.760 --> 00:15:26.880
-  value and annual tax increment how come the tiff numbers don't match up sometimes they're close

00:15:28.000 --> 00:15:35.680
-  yeah and that's a great question we we get yeah we get some things we get some reimbursements back

00:15:35.680 --> 00:15:46.080
-  sometimes um and i think in that line um you can see for 24 we've got 16 000 reimbursements in

00:15:46.080 --> 00:15:46.320
-  there

00:15:46.320 --> 00:15:54.480
-  and i think we probably need to review 2023 and see if we didn't have something put into the wrong

00:15:54.480 --> 00:16:02.160
-  fund at the county level that we got create uh fixed in 2024 so we we need to pull the detail

00:16:02.160 --> 00:16:10.720
-  out because you're right that 23 to 24 doesn't look um normal on the tiff revenue and i'm

00:16:10.720 --> 00:16:19.280
-  wondering if because 24 is considerably higher whether we ended up with part of the 23 tax

00:16:19.280 --> 00:16:26.400
-  actually being deposited in the 24 calendar year yeah that's definitely what it looks like

00:16:26.400 --> 00:16:34.320
-  um and we'll look at that and make an amendment to this page as needed to to try to clarify that

00:16:34.320 --> 00:16:43.760
-  better okay all right yep that was my big question there

00:16:43.760 --> 00:16:50.240
-  there

00:16:50.240 --> 00:17:04.240
-  where is my list of

00:17:04.240 --> 00:17:08.720
-  uh

00:17:08.720 --> 00:17:24.960
-  i thought this i don't think this map is correct

00:17:29.600 --> 00:17:36.400
-  app is showing property north of fullerton pike is in this tiff and i didn't think this

00:17:36.400 --> 00:17:39.920
-  tiff had any property north of fullerton pike

00:17:39.920 --> 00:17:49.120
-  i think the answer to that is when it was initially conceived it did and then the city annexed the

00:17:49.120 --> 00:17:55.120
-  properties that are north of fullerton pike right so they're kind of in a limbo area where they are

00:17:55.120 --> 00:18:01.280
-  low area where they we can't collect from them i'll have to check the statute whether that removes

00:18:01.280 --> 00:18:08.800
-  them from the tiff or not and if it does we'll we'll mend the map but that that is those areas

00:18:08.800 --> 00:18:13.920
-  i know have been annexed yes that's what i thought they've been annexed is that the bill c brown

00:18:13.920 --> 00:18:24.800
-  property yeah that's what i thought just to clarify that we're not collecting revenues from that

00:18:24.800 --> 00:18:31.120
-  particular parcel at the present moment we need we're gonna have to check it could be no we

00:18:31.120 --> 00:18:36.480
-  shouldn't be okay the question is whether just because you're not whether that that means it's

00:18:36.480 --> 00:18:42.000
-  totally removed from the tiff area in which case we could remove it from our map or whether by some

00:18:42.000 --> 00:18:49.600
-  reason it's still in that tiff area in a tiff but it's no good to us non-revenue producing my

00:18:49.600 --> 00:18:54.560
-  assumption is that it gets removed and that we should take that off the map okay is that the the

00:18:54.560 --> 00:19:02.480
-  parcel under the bill c brown trustee okay so we're showing it right payable but it should not

00:19:02.480 --> 00:19:11.360
-  reflect next year right is that that property was annexed years ago okay okay so it's just a matter

00:19:11.360 --> 00:19:16.880
-  when we update we need to update the map assuming that it is excluded and i'll confirm that we just

00:19:16.880 --> 00:19:23.760
-  need to update that that's okay because we've got some parcels in our real estate name that are

00:19:23.760 --> 00:19:24.080
-  saved

00:19:24.080 --> 00:19:31.760
-  bill c brown and so the value of those is actually included in our assessed value so i think he

00:19:31.760 --> 00:19:32.080
-  does

00:19:32.080 --> 00:19:39.680
-  own some south of 46 as well or of fullerton pike as well so he is some of the i think some of this

00:19:39.680 --> 00:19:47.520
-  area he owns there must be the smaller properties given the kind of relatively small number

00:19:47.520 --> 00:19:53.440
-  that's right because they discussed putting the jail on that site one time yeah that's right that's

00:19:53.440 --> 00:20:02.640
-  right i just think this ought to get cleared up because we've got we have what two four six eight

00:20:02.640 --> 00:20:09.440
-  there are 12 properties listed but if i count the number of parcels that are below fullerton pipe

00:20:09.680 --> 00:20:10.800
-  i don't get that many

00:20:10.800 --> 00:20:16.400
-  you'd look at the two coincide

00:20:16.400 --> 00:20:24.560
-  okay which is exactly what their report says we ought to do yeah

00:20:24.560 --> 00:20:35.280
-  okay so we'll work with jeff and the auditor's office to make sure we get the parcel list

00:20:35.280 --> 00:20:44.640
-  updated and the map updated so that we reflect the current situation okay uh that's two down

00:20:44.640 --> 00:20:52.640
-  you want to do which one next one question just to make sure the revenue that's going in that'll go

00:20:52.640 --> 00:20:58.480
-  to the bridge project and that will be funded completely by the end of this year or will we

00:20:58.480 --> 00:21:08.000
-  have additional revenues that'll be having to be paid out in the future out of we will use

00:21:08.000 --> 00:21:18.560
-  and lisa can talk about the project but we will use revenue to pay some portion of the debt service

00:21:18.560 --> 00:21:25.280
-  on the bonds the county issued for the project so there there will be a commitment for future tiff

00:21:25.280 --> 00:21:32.480
-  revenue to some extent not for the full payment on the bonds but to to help satisfy those debt

00:21:32.480 --> 00:21:38.960
-  service payments annually and i would the bond documents indicate that the we would make sure

00:21:38.960 --> 00:21:47.440
-  that at least 50 percent of the tiff revenue is available for payment of that those we did a

00:21:47.440 --> 00:21:58.240
-  resolution to that account yeah and i think and yeah yeah yes at least 50 but the resolution that

00:21:58.240 --> 00:22:03.520
-  allows that means you could actually pay more if necessary or if you if the revenue increased

00:22:03.520 --> 00:22:10.240
-  and that way that would retire that cost and free up additional revenue in the future

00:22:11.040 --> 00:22:18.320
-  and i would just say that the the the tiff's portion of that bond payment is minuscule

00:22:18.320 --> 00:22:29.600
-  compared to with me i mean it's a pretty expensive bridge we're being helpful but in a minor way

00:22:32.400 --> 00:22:40.320
-  everything helps yeah so i don't i don't think you're you could end it early even if we gave 100 i

00:22:40.320 --> 00:22:51.840
-  guess yeah yeah okay what's next all right state road 46 and we'll go through this kind of the same

00:22:51.840 --> 00:23:01.920
-  way this is very similar to curry profile where we authorized a 4.5 million dollar bond but the

00:23:01.920 --> 00:23:10.240
-  developer has only drawn in this case 61 500 so again there's an idea there's a project out there

00:23:10.240 --> 00:23:19.360
-  the county wanted to assist the developer with that we've we've done so and since that time we've

00:23:19.360 --> 00:23:27.680
-  we've been in a holding pattern so we we're ready to go that there's also a large project out there

00:23:29.440 --> 00:23:35.760
-  we've built and here's our we're paying four percent on that so a thousand two thirty is

00:23:35.760 --> 00:23:43.440
-  interest every six months that we pay on the bonds our cash balance at the county level

00:23:43.440 --> 00:23:51.920
-  we've continued to grow that so we're up to almost 1.8 million at the end of 2024

00:23:53.200 --> 00:24:00.320
-  and that's to help pay for that big project that lisa has been planning out there

00:24:00.320 --> 00:24:09.440
-  well and maybe add a little more maybe add a little more context we had a conversation with

00:24:09.440 --> 00:24:15.520
-  steve krater today who is the developer they are planning they're still planning on doing the

00:24:15.520 --> 00:24:22.240
-  the roadway this year they are waiting for and they've been waiting for like nine to ten months

00:24:22.240 --> 00:24:27.840
-  on a what are called a lomar permit land of map revision

00:24:27.840 --> 00:24:35.040
-  oh he still anticipates getting that road with hunter valley completed this year

00:24:35.040 --> 00:24:43.120
-  okay but cannot move forward until he has a permit is a long process it's new in the

00:24:43.120 --> 00:24:51.360
-  last couple years um for fullerton pike phase three it took probably over a year to get that permit

00:24:51.360 --> 00:25:02.880
-  through idem so here is my question this says we've got a million seven hundred and eighty four

00:25:02.880 --> 00:25:18.800
-  thousand in the bank and if i look at estimated annual tax increment for this year through twenty

00:25:18.800 --> 00:25:33.120
-  twenty nine added to that one seven million seven i end up with three million roughly three million

00:25:33.120 --> 00:25:45.200
-  five hundred thousand dollars so where does how do we end up paying back four and a half million if

00:25:45.200 --> 00:25:55.920
-  we've only got three and a half million to work with so we if if we do put that money in or the

00:25:55.920 --> 00:26:02.960
-  developer puts that money in for the road the assumption is that new assess value new development

00:26:02.960 --> 00:26:12.800
-  will occur and that will increase the tif revenue so this we have not made any projections at this

00:26:12.800 --> 00:26:19.920
-  point in time on what those increases in assess value might be just because we we're not sure what

00:26:19.920 --> 00:26:25.920
-  the developer's plan was or how soon that that might happen because it'll take some time to get

00:26:25.920 --> 00:26:32.000
-  the road done and then it'll take even you know more time to get buildings built and then more

00:26:32.000 --> 00:26:37.760
-  time to get them assessed and and finally pay tax on on the new building so there there it is a

00:26:37.760 --> 00:26:38.080
-  long

00:26:40.000 --> 00:26:47.040
-  cycle to to increase those tif revenues so that that's the key and that the the bonds if i go back

00:26:47.040 --> 00:26:59.520
-  to that schedule the bonds were are outstanding see all the way to 2033 so that was the original we

00:26:59.520 --> 00:27:05.840
-  we would have to go back and maybe that's a discussion with the developer when we look at

00:27:05.840 --> 00:27:14.080
-  their build out that that may not be enough time to pay the bonds back and i i think jeff correct

00:27:14.080 --> 00:27:19.920
-  me if i'm wrong i think that is the end date on the on the area as of now yeah i think that's how

00:27:19.920 --> 00:27:29.120
-  we structured it and and i guess my my my response would be twofold one is the end of this tif is

00:27:29.120 --> 00:27:29.280
-  not

00:27:29.280 --> 00:27:35.600
-  in 2029 but my other would be you know that that was the deal going into it is that we would use

00:27:35.600 --> 00:27:40.640
-  the tiff we had available to make payments and if we could not make the payments and the developer

00:27:40.640 --> 00:27:46.720
-  was on the hook for any extra payments necessary so what's the motivation for steve to actually

00:27:46.720 --> 00:27:50.000
-  do this project if he's going to get stuck for a million dollar bill

00:27:50.000 --> 00:27:59.600
-  but one i think he's required to under the the pud that's in the area so he's required this road

00:27:59.600 --> 00:28:06.560
-  is a required build for him under that so even if he got reimbursed you know three out of the

00:28:06.560 --> 00:28:14.080
-  four million he still got three more million than he would if he if he didn't do it and the second

00:28:14.080 --> 00:28:21.920
-  is i i think there's ample time for there to be development that would push us from three million

00:28:21.920 --> 00:28:29.600
-  to four and a half um if and if the when when did you say the bond ended i'm sorry

00:28:29.600 --> 00:28:40.080
-  february of 23 33 sorry so yeah take another three years on this then you're up another million so

00:28:40.080 --> 00:28:48.720
-  you're at four and so that half a million dollar difference is is where you're really at because i

00:28:48.720 --> 00:28:58.080
-  think the repayment schedule goes until but i'm trying what i mean so we we put a jail on the new

00:28:58.080 --> 00:29:05.360
-  road we're building right but since that's a municipal thing it doesn't give us any money

00:29:05.360 --> 00:29:16.480
-  right and the question is where else he's been doing building on the south side we got a new one

00:29:16.480 --> 00:29:26.960
-  coming online soon for um yeah right um but he has shown really no interest in developing

00:29:26.960 --> 00:29:33.680
-  anything on the north side of there and i'm trying to figure out how we provide sufficient

00:29:33.680 --> 00:29:34.400
-  incentive

00:29:34.400 --> 00:29:42.960
-  for to actually do something there which would give us a considerable increase in assessed value

00:29:43.520 --> 00:29:50.160
-  particularly since this is going to end in 33 and that would effectively give us

00:29:50.160 --> 00:29:57.840
-  nine years of tiff money which is not very much for a big bond that would put in a lot of roads

00:29:57.840 --> 00:30:05.840
-  for example or a sewer system in that big open area part that he's got so i'm having trouble

00:30:05.840 --> 00:30:10.800
-  figuring out how this becomes a viable thing for him to really put his teeth into

00:30:13.040 --> 00:30:17.520
-  and i'm not steve i'm not him so i can't answer it but i think i would say that

00:30:17.520 --> 00:30:24.640
-  the roadway that's there currently has a sewer underneath it from the plant and so

00:30:24.640 --> 00:30:33.360
-  you know a lot of that infrastructure is there he has a lot of sunk costs into this area already

00:30:33.360 --> 00:30:39.040
-  because the this is the second time we've done a bond with him and the first one we didn't

00:30:39.600 --> 00:30:46.560
-  we couldn't he's currently going through amending the pud to make it more amenable

00:30:46.560 --> 00:30:53.200
-  develop and so i think there's a lot of other factors going on in there i also think that

00:30:53.200 --> 00:31:01.840
-  developing the land with or without now or in the future is always going to be his best

00:31:01.840 --> 00:31:10.000
-  it is going to be in his interest that's available to him

00:31:10.000 --> 00:31:20.800
-  why is the amount of tiff money we can put into the development of that area and i see us just

00:31:20.800 --> 00:31:26.320
-  losing opportunities as we go on here just as we have in the past and that's

00:31:28.960 --> 00:31:32.320
-  there's no way to incentivize accordingly because he's already bought the bonds and

00:31:32.320 --> 00:31:38.640
-  we're required to make the payments accordingly we just may not be able to and it's his

00:31:38.640 --> 00:31:45.280
-  at his at steve's jeopardy in regards to if it's unable then it's responsibility to take care of

00:31:45.280 --> 00:31:48.560
-  we've done everything well pretty much everything we can

00:31:48.640 --> 00:31:50.640
-  uh

00:31:50.640 --> 00:32:03.920
-  oh the the revenues that this tiff would typically have that would have had you know i think logan

00:32:03.920 --> 00:32:07.760
-  land development in there what kind of revenues are being lost in this now that we're under

00:32:07.760 --> 00:32:15.520
-  municipal ownership i don't i don't know off the top of my head i don't think it's undeveloped

00:32:15.520 --> 00:32:22.080
-  so it would be at a it wouldn't be at a huge success value yeah it will be a decrease in our

00:32:22.080 --> 00:32:28.480
-  overall revenues that have been produced over the period over the past periods oh yeah especially

00:32:28.480 --> 00:32:37.360
-  given the price which is now you know that's it that's the value of the land without improvement

00:32:43.600 --> 00:32:49.680
-  da that's going in is that going to be into a non-taxable situation or is that a taxable

00:32:49.680 --> 00:32:59.520
-  property itself my understanding and i i got i got this information from talking to one of the

00:32:59.520 --> 00:33:06.160
-  people who are also bidding on the project and apparent and according to him and i can't remember

00:33:06.160 --> 00:33:14.640
-  if it's him a kind of requires it to be taxable right so i i understand i think it would private

00:33:14.640 --> 00:33:23.120
-  owner leasing it to the va okay is that true is that actually true i didn't know that

00:33:23.120 --> 00:33:31.440
-  the private owner is leasing it back to the va that is my to the best of my knowledge yes

00:33:31.440 --> 00:33:37.840
-  kind of like pain enterprise has released it back to heavy tech and now they heavy tech owns it i

00:33:37.840 --> 00:33:45.760
-  the nursing training facility for the license ranch building for their own curry right that's

00:33:45.760 --> 00:33:53.120
-  yeah privately held yeah i think so the question we're trying to identify or try to identify as a

00:33:53.120 --> 00:33:58.960
-  matter of as we look in two years down the road from a assessed value situation we're trying to

00:33:58.960 --> 00:34:05.840
-  capture in the tiff prior to the sun setting that we have those revenues and will it be a non-taxable

00:34:05.840 --> 00:34:13.200
-  situation or not based upon the parcels that we have there approximately what between the

00:34:13.200 --> 00:34:20.320
-  arc and the new jail site were 100 plus acres right

00:34:20.320 --> 00:34:25.280
-  we're on the hook

00:34:25.360 --> 00:34:35.890
-  yeah thank you i would just say you're probably at more of 60 to 70 developer acres because a lot

00:34:35.890 --> 00:34:36.240
-  of

00:34:36.240 --> 00:34:43.520
-  that quarry park area is not developed yeah yeah i'm just looking at the aggregate amount yeah what

00:34:43.520 --> 00:34:50.960
-  what what revenue will we losing that will have that could have been put in it's i think the

00:34:50.960 --> 00:34:56.640
-  increment yeah jeff you got a good point but i think the increment on the improvements would be

00:34:56.640 --> 00:35:03.600
-  considerable if they were commercial properties i think that's what oh yes yeah and and that's

00:35:03.600 --> 00:35:11.680
-  where the question comes in okay how much are we losing out of that and you know if we go by the

00:35:11.680 --> 00:35:19.440
-  the schedule of the jail then you're looking on four years maybe maybe five things happen

00:35:19.440 --> 00:35:31.120
-  um that um would be kind of in my mind questionable in terms of um have a revenue successfully

00:35:31.120 --> 00:35:31.440
-  closing

00:35:31.440 --> 00:35:42.480
-  out the bond so the call we talked about splitting this district creating another tiff district

00:35:43.920 --> 00:35:51.600
-  which would be be able to extend that tiff district's life beyond

00:35:51.600 --> 00:36:00.560
-  what we would do what we did and charlie chime in wherever i'm mistaken but i think we would do the

00:36:00.560 --> 00:36:05.300
-  same process we did with the curry profile where we would carve it out of one tiff district and

00:36:05.300 --> 00:36:05.440
-  then

00:36:05.440 --> 00:36:12.640
-  create a new tiff's district um you would and when you do that it would have the the standard and i

00:36:12.640 --> 00:36:19.520
-  think of residential tiffs or 20 years maximum so that you'd have a 20 year tiff district for that

00:36:19.520 --> 00:36:28.080
-  right so i mean this point and you'd also want to do it for areas that hadn't been developed yet

00:36:28.080 --> 00:36:35.520
-  right because once the building's there you don't get increment on it if it's already existing

00:36:35.520 --> 00:36:41.280
-  so you would look at that and you could still carve that out and give it the whole new 20 year

00:36:42.480 --> 00:36:48.000
-  cycle i think commercial you can go up to 25 but but residential is a 20 year cycle

00:36:48.000 --> 00:36:54.890
-  add land that was not well i think we broached that before we could then add property so that one

00:36:54.890 --> 00:36:55.200
-  chunk

00:36:55.200 --> 00:36:58.960
-  which is uh

00:36:58.960 --> 00:37:09.760
-  originally could be added into a residential tiff correct at that point that's another

00:37:11.440 --> 00:37:14.640
-  yes

00:37:14.640 --> 00:37:17.840
-  questions about

00:37:17.840 --> 00:37:28.000
-  okay on to the biggie all right biggest for last we'll go to the west side

00:37:28.000 --> 00:37:32.880
-  and again i'll kind of skip through this

00:37:35.760 --> 00:37:42.560
-  we have this the same situation here we've had nice decreases in tax rates

00:37:42.560 --> 00:37:51.440
-  we do have a few parcels in this area that the city annexed that we do still get to capture our

00:37:51.440 --> 00:38:00.240
-  non-city part of the tax rate and that was we get to do that because we had bonds outstanding

00:38:00.240 --> 00:38:07.120
-  when the city did that annexation so we've we've got that we've got two bonds left 2020

00:38:07.120 --> 00:38:16.080
-  bonds that go out to 2039 and then we've got some 2015 bonds that also go out to 2039 so

00:38:16.080 --> 00:38:24.080
-  at that point that's when this west side tiff district will expire on those final

00:38:24.080 --> 00:38:32.960
-  payment dates for each of those bonds here's our combined debt service and in 2025 we're paying

00:38:32.960 --> 00:38:42.480
-  about almost 700,000 between the two bonds almost 2.4 million a tiff revenue so excellent coverage

00:38:42.480 --> 00:38:49.600
-  debt service coverage these bonds are backed by the county so that if there were to be a

00:38:50.160 --> 00:38:54.720
-  deficiency in the tiff revenue and we didn't have any other revenue to use for debt service

00:38:54.720 --> 00:39:03.520
-  we would levy a property tax to make up the difference so we want to make sure we we have

00:39:03.520 --> 00:39:13.840
-  cash to make our our bond payments we've got a lot of historical information here we have debt

00:39:13.840 --> 00:39:19.680
-  service reserves for both bond issues that are held by old national bank they're the trustee

00:39:19.680 --> 00:39:26.640
-  for the bonds so i've got some details there and then we've got the big county level tiff fund

00:39:26.640 --> 00:39:35.760
-  just like we looked at the the first three and historically we we've had a good cash balance here

00:39:35.760 --> 00:39:44.560
-  when we get to 2024 we really because we've got some large projects that we've been working on out

00:39:44.560 --> 00:39:54.080
-  there that balance went down to 347,000 at the end of 24 and we've spent some money primarily for

00:39:54.080 --> 00:39:54.400
-  the

00:39:54.400 --> 00:40:01.600
-  the lease payment on the new fire truck that's dropped that balance down in 25 to to 83,000 and

00:40:01.600 --> 00:40:08.470
-  we're really in a holding pattern there on spending until we get our june settlement of tiff

00:40:08.470 --> 00:40:09.040
-  revenue

00:40:12.320 --> 00:40:19.440
-  and then probably the other page to focus on is the cash flow page

00:40:19.440 --> 00:40:26.560
-  it's on page 26 and this has gotten to be very critical now because the cash balance has dipped

00:40:26.560 --> 00:40:33.760
-  down so we've got a 25 column here with our cash balance we've got our estimated tiff revenue we're

00:40:33.760 --> 00:40:39.760
-  going to get some federal funding in for part of the project we're finishing then we've got our

00:40:39.760 --> 00:40:47.840
-  expenses our two bond payments our stem payment fire truck lease and then the the projects that

00:40:47.840 --> 00:40:56.160
-  lease is working on and i think that the discussion we had after we sent this draft report out and

00:40:56.160 --> 00:40:56.240
-  i

00:40:56.240 --> 00:41:03.120
-  think lisa referenced this earlier would be we we would move back the starting point for curry pike

00:41:03.920 --> 00:41:12.000
-  and not started in 25 move that back to 26 so that we can make sure we've got a comfortable

00:41:12.000 --> 00:41:18.560
-  cash balance at the end of 25 so if we take that 650 out we should be over a million dollars

00:41:18.560 --> 00:41:26.160
-  of cash balance at the end of 25 which would be much better in the overall scheme of things

00:41:26.160 --> 00:41:32.720
-  because you you don't know what expenses might come up or a big taxpayer doesn't make their

00:41:32.720 --> 00:41:40.800
-  property tax payment we have a delay in tiff revenues so we're glad that that lisa has been

00:41:40.800 --> 00:41:50.340
-  able to accommodate that so those are the highlights i think on west side so any questions on that

00:41:50.340 --> 00:41:50.400
-  on

00:41:50.400 --> 00:41:57.760
-  those items what i'm hearing is we're trying to build back up our reserves in order to make sure

00:41:57.760 --> 00:42:02.880
-  that we have the cover debt service coverage that's necessary in order to meet the financial

00:42:02.880 --> 00:42:10.960
-  requirements of the and you know that's that's right um we we have a fully funded debt service

00:42:10.960 --> 00:42:17.040
-  reserve for each one of those that are i don't show those in the county fund balance so we do have

00:42:17.040 --> 00:42:24.640
-  an additional um one year of debt and we would not ever want to hit that reserve but we have that

00:42:24.640 --> 00:42:29.920
-  there and the way the bond documents are set up is when we bring our tiff revenue in

00:42:29.920 --> 00:42:39.120
-  the first set aside goes to those bond payments so um realistically i think we you know if we had a

00:42:39.120 --> 00:42:46.880
-  problem we would probably be back to um lisa and say what else is there anything else we can delay

00:42:46.880 --> 00:42:57.360
-  or um not do if if we if we came down to that but by moving curry pike back at least that helps us

00:42:57.360 --> 00:43:01.840
-  bring back the cash balance just so we have a little more cushion if if there is something that

00:43:01.840 --> 00:43:06.720
-  happens um you know i think the the biggest thing would be if a big taxpayer

00:43:06.720 --> 00:43:11.840
-  delayed their payment or um you know we've seen that happen where they

00:43:12.960 --> 00:43:17.360
-  well you know a lot of these big companies have tax departments somewhere else in the u.s and so

00:43:17.360 --> 00:43:17.840
-  the

00:43:17.840 --> 00:43:23.120
-  they mail their payment and we don't get it for 30 days late or something like that so

00:43:23.120 --> 00:43:27.520
-  it's more of a timing delay than anything

00:43:27.520 --> 00:43:35.840
-  anyway it goes we're not in any jeopardy by the balance being down to where it is

00:43:35.840 --> 00:43:42.400
-  correct reserve situation that's sitting there okay correct that's that's good point yes

00:43:43.120 --> 00:43:46.080
-  and i would say that that's not to be comfortable with where we're at

00:43:46.080 --> 00:43:53.280
-  no it's just if we've got the backstop so if someone fails to follow through in the timely

00:43:53.280 --> 00:44:07.200
-  manner we're still okay yeah for now yeah and i guess not to be too doom and gloom but our

00:44:07.200 --> 00:44:13.360
-  agreements with ellisville for the fire truck and for the stem payments all have provisions in it

00:44:13.360 --> 00:44:19.760
-  that says if we are unable to meet our bond payments and this the bond payments have priorities so

00:44:19.760 --> 00:44:28.240
-  yeah i want to avoid exercising those clauses and and our complete backstop is an additional

00:44:28.240 --> 00:44:44.320
-  property tax levy correct okay so we're moving the 650 000 to 26 750 000 to 27

00:44:44.320 --> 00:44:49.440
-  which by then will be considerably more

00:44:52.080 --> 00:44:59.440
-  problem with delaying is it cost more it is it is but that also helps us that curry pike has

00:44:59.440 --> 00:45:06.080
-  drainage structures has sidewalks it has curbs it has a lot of infrastructure that needs replaced

00:45:06.080 --> 00:45:15.600
-  gives us time to develop to develop a good project and helps get the cash back

00:45:18.560 --> 00:45:28.160
-  we eliminated that we worked with the railroad and we doubt the price on that was extreme

00:45:28.160 --> 00:45:46.720
-  and we also um i want to throw out there if there is an emergency or anything i still have funds

00:45:46.720 --> 00:45:53.120
-  that i'm holding back in the local rodent street they'll have that as a backup so

00:45:53.120 --> 00:46:01.120
-  other projects to get the ones we got going get completed then there will always be a little extra

00:46:01.120 --> 00:46:09.440
-  cost um correct right now knock on wood we do not have any change orders for the rental pipe

00:46:12.080 --> 00:46:17.760
-  um intermediate completion date is july and liberty drive trail we're getting ready to do

00:46:17.760 --> 00:46:24.720
-  the punch list and walk through for that and that would have impact on the tiff

00:46:24.720 --> 00:46:34.000
-  we said do you have a sense of where we are cost-wise on material let's say at the uh the

00:46:34.000 --> 00:46:43.280
-  cross railroad crossing at vernal the new one and what's coming up with curry you know obviously

00:46:43.280 --> 00:46:48.080
-  don't have numbers but do you have a rough estimate from what you see on price of material and

00:46:48.080 --> 00:46:59.280
-  we usually get our benefit around here is we have to pay so we get good prices because they're

00:46:59.280 --> 00:47:06.800
-  competitive against each other not everybody has that luxury so what we usually estimate comes out

00:47:06.800 --> 00:47:15.760
-  really close to what the price that a lot of a lot of work i'm anxious to see how it comes out but

00:47:15.760 --> 00:47:24.480
-  again the last few years right on and the price that we get for hiring out some of our paving and

00:47:24.480 --> 00:47:35.360
-  everything super beneficial to Monroe County because five dollars a ton if we did it in-house

00:47:35.360 --> 00:47:43.200
-  and that's saving our equipment that's saving our labor to keep other projects going as mowing

00:47:43.200 --> 00:47:51.680
-  tree trimming everything else outside of paving because when we pave it's everyone paves everything

00:47:51.680 --> 00:48:00.640
-  else stops but being able to be that close to what the fob price is and hiring it out you can't

00:48:00.640 --> 00:48:00.880
-  beat

00:48:00.880 --> 00:48:09.200
-  it it's it's very like i said we have two great paving contractors that provide good quotes and

00:48:09.200 --> 00:48:15.280
-  bids and keep us in tact with our budget but that's great okay

00:48:18.560 --> 00:48:24.080
-  okay do we have anything else for charlie i guess the question i always asked

00:48:24.080 --> 00:48:33.360
-  ask ssg at this point is after reviewing all four of the of the tiff districts and looking through

00:48:33.360 --> 00:48:39.760
-  the reports do you see what would your recommendation be for the you know kind of june

00:48:39.760 --> 00:48:46.160
-  decision of the rdc as to whether there is any excess assessed value in any of the tiff districts

00:48:47.920 --> 00:48:55.280
-  we believe there is no excess assessed value we've we've got the cash committed and the

00:48:55.280 --> 00:48:58.800
-  the revenues for this year and then beyond and the west side's a

00:48:58.800 --> 00:49:05.440
-  good example we need every dollar we can get you know we've got plenty of projects we need to do

00:49:05.440 --> 00:49:16.880
-  i understand it this report has to go to the state is that correct we have to turn these in

00:49:17.600 --> 00:49:21.760
-  we give it to the county council and and then we and then the county council

00:49:21.760 --> 00:49:29.360
-  auditor puts it in the state system could we amend the west side

00:49:29.360 --> 00:49:39.680
-  page 26 to move the funds for the curry pike construction to the right by one year

00:49:39.680 --> 00:49:45.360
-  yes we can definitely do that and then i've got a couple of other

00:49:46.000 --> 00:49:52.880
-  corrections that we talked about earlier so we'll get a revised set of reports down to jeff

00:49:52.880 --> 00:50:01.040
-  this week still because we'd like to get those to the county council for their april meeting

00:50:01.040 --> 00:50:18.720
-  so last minute none oh charlie thank you very much all right thank you all have a good rest

00:50:18.720 --> 00:50:26.880
-  of the day thank you charlie could you guys give a motion that to submit these at as after the

00:50:26.880 --> 00:50:34.240
-  amendments to the county council i will move that we submit these reports as amended

00:50:34.240 --> 00:50:38.160
-  to the county council at its april meeting second

00:50:38.160 --> 00:50:49.680
-  you want me to call the roll yep call the roll please commissioner martin yes commissioner

00:50:49.680 --> 00:50:59.600
-  mccarty yes commissioner cassidy motion is approved three to zero next item on the agenda

00:50:59.600 --> 00:51:08.480
-  are the minutes for our february 19th meeting uh them in the packet of information

00:51:08.480 --> 00:51:14.640
-  actions or additions

00:51:14.640 --> 00:51:22.880
-  to approve is present

00:51:22.880 --> 00:51:31.760
-  there was second second i watched on cat since i wasn't here

00:51:31.760 --> 00:51:40.160
-  jeff would you call the roll i will but i will just note that lisa rich actually prepared these

00:51:40.160 --> 00:51:45.040
-  because i was at the late that's why they're that's why they look so good

00:51:45.040 --> 00:51:51.440
-  you want to do the ones for this month too i was just looking at his scribbles i can't do that

00:51:51.440 --> 00:51:59.280
-  commissioner martin yes commissioner mccarty yes commissioner cassidy yes motion is approved

00:51:59.280 --> 00:52:04.320
-  three oh and i will include that the future minutes should always be done by the highway

00:52:04.320 --> 00:52:14.160
-  department and next month's minutes just add that to our list okay claims uh we have claims this we

00:52:14.160 --> 00:52:22.320
-  have two claims this month uh one from terracon consultants for 868 dollars and 95 cents and the

00:52:22.320 --> 00:52:32.560
-  other one is our rbb csc stem payment for the fall of 2024 of 123,850 dollars and 61 cents

00:52:33.520 --> 00:52:43.280
-  for a total of 124 cents the um we're a little bit late on getting the rbb one done because

00:52:43.280 --> 00:52:51.520
-  we had to go back and adjust it for the spring payment that had been made and some

00:52:51.520 --> 00:52:58.720
-  finagling we had to do to get our money squared away last fall this is now correct

00:53:00.160 --> 00:53:04.880
-  and i would just note that this is actually being paid out of the general fund um through one of

00:53:04.880 --> 00:53:10.240
-  the auditor's office's lines and then the we're having you approve it for when settlement comes

00:53:10.240 --> 00:53:18.160
-  in we'll do a correction to put it into the 4920 west side tiff fund that will clean up the balance

00:53:18.160 --> 00:53:29.920
-  in all funds correct to correct one about the terracon it just looked like this was inspection

00:53:29.920 --> 00:53:35.920
-  for it it is it's for the msc wall that was constructed for the bernal pike

00:53:35.920 --> 00:53:46.080
-  uh do i have a motion for approval i'll make a motion to approve as presented

00:53:46.720 --> 00:53:58.240
-  second second for approval of the claims of uh terracon consultants for $868 and

00:53:58.240 --> 00:54:03.840
-  sc stem payment for the fall of 2024

00:54:08.320 --> 00:54:20.080
-  of 124 719 dollars and 56 cents commissioner martin yes commissioner mccarty yes commissioner

00:54:20.080 --> 00:54:38.640
-  cassidy yes motion is approved three to zero

00:54:39.360 --> 00:55:04.480
-  okay do we have any staff comments lisa um i don't i'm happy to answer any questions

00:55:04.480 --> 00:55:08.480
-  construction kind of slows down in the winter april 1st is the contractor's date that

00:55:09.440 --> 00:55:19.600
-  their time time uh the clock good i'm ready to uh i was driving through there the other day

00:55:19.600 --> 00:55:26.080
-  and i recalled hey we were here a few years ago and we had a opening of that part of the profile

00:55:26.080 --> 00:55:32.640
-  parkway and at the time i commented i wanted to get back to open up the bridge across the track

00:55:32.640 --> 00:55:45.440
-  well i am i am ready i think that'll i think it'll also make repair work on curry pike much easier

00:55:45.440 --> 00:55:56.240
-  to do um jeff anything else no i was just if i think i already expressed that we met with

00:55:56.240 --> 00:56:03.680
-  mr krider about hunter valley road and so we're eagerly awaiting for that project to be started

00:56:03.680 --> 00:56:13.690
-  and completed any more information about this jail thing happening not happening any kind of

00:56:13.690 --> 00:56:14.160
-  timeline

00:56:14.160 --> 00:56:22.880
-  idea well the timeline that i've seen has a opening in i think mid 2029 um i think the next

00:56:22.880 --> 00:56:28.000
-  i don't have the timeline off the top of my head but i certainly could email it to you the the

00:56:28.000 --> 00:56:34.000
-  timeline that's been shared with the council and commissioners on steps of when's when do we expect

00:56:34.000 --> 00:56:41.200
-  the next uh i think there are at least two more before they start bid documents

00:56:41.200 --> 00:56:50.960
-  they are currently working with departments and i mean i think the budget needs to be

00:56:52.320 --> 00:56:57.600
-  the project needs to fit the budget and right now it's a little bit over so i think that's

00:56:57.600 --> 00:57:03.040
-  something that needs to be worked out but i can get you the timeline i think 2029 is when it's

00:57:03.040 --> 00:57:11.440
-  anticipated to be done or it's more than a jail it's just as complex it is a justice center yes

00:57:11.440 --> 00:57:15.680
-  that's what i thought i'll make sure i got that terminology right because there's multiple more

00:57:15.680 --> 00:57:19.680
-  than just a jail correct it's going to have the courts and all the court related functions which

00:57:19.680 --> 00:57:24.000
-  would include the the jail okay i just i didn't think the parameters had changed i got nervous

00:57:24.000 --> 00:57:31.040
-  no no parameters have not changed i think a clerk right clerk moving where it's clerk

00:57:31.040 --> 00:57:35.840
-  the clerk of the courts the probation public defender prosecutor

00:57:35.840 --> 00:57:47.120
-  yes i'm sure i'm missing some but essentially anything that's in the justice building which

00:57:47.120 --> 00:57:53.600
-  has what a couple hundred employees i would say anything in the justice building in that block as

00:57:53.600 --> 00:58:04.000
-  well as uh most of the oh community corrections building um and i think we do have some justice

00:58:04.000 --> 00:58:12.320
-  staff and showers building um i 200 is low i would say just the sheriff's department and it's

00:58:13.840 --> 00:58:18.720
-  sheriff's department by itself is probably closer to 150 and then the others i i would say a total

00:58:18.720 --> 00:58:25.120
-  of probably 350 400 employees would be my guess little sheriff's department is planned to be out

00:58:25.120 --> 00:58:41.600
-  there also correct but we just call it the law and order complex

00:58:41.600 --> 00:58:42.560
-  uh

00:58:42.560 --> 00:58:52.640
-  just clarify from a time frame saying you'll email it accordingly but completion in 2029

00:58:52.640 --> 00:59:03.120
-  for everything jail will be prior to that or i i don't know i'm confused now the whole thing

00:59:03.120 --> 00:59:10.880
-  is supposed to be done in 2029 right the the justice i mean it's it's all one building right

00:59:10.880 --> 00:59:15.040
-  at this point with the design it's it's all one building so the whole thing is supposed to be

00:59:15.040 --> 00:59:21.840
-  open in 2029 whether they get the jail done earlier or not i don't know which one i i think

00:59:21.840 --> 00:59:26.880
-  it i think it's anticipated that the jail will take a little bit longer to actually construct

00:59:26.880 --> 00:59:35.600
-  than the rest of it but i don't know i'm i'm not a scheduler of construction so i'm not i'm not

00:59:35.600 --> 00:59:46.000
-  going to venture a guess on how they will manage that 2029 is okay i just assume i said the end of

00:59:46.000 --> 00:59:55.760
-  2029 uh commissioner's comments pucker did you have anything comment thanks

00:59:58.640 --> 01:00:06.400
-  yeah just to latch on to that i've heard uh talk about possible commercial development uh in that

01:00:06.400 --> 01:00:13.440
-  area that would um support all those jobs and um and that came from one of the commissioners

01:00:13.440 --> 01:00:23.760
-  offline and at an event that uh this is um a possibility or it's being discussed i don't know

01:00:24.400 --> 01:00:30.960
-  which would help a little bit you know with what we discussed earlier in that in that district um

01:00:30.960 --> 01:00:37.680
-  i hope to see it because yeah you're basically moving a lot of the county seat into a new area

01:00:37.680 --> 01:00:44.960
-  um a lot of jobs a lot of people in that area so um interesting to see how it turns out

01:00:44.960 --> 01:00:53.840
-  the road extension i guess i mean i when i think about it just to clarify we're looking at

01:00:53.840 --> 01:01:00.400
-  that we're still waiting for the permit for that and then that's a it's a new permit it's a new

01:01:00.400 --> 01:01:08.480
-  permit right but they he still expects to have a complete pie year end is that that's that's pretty

01:01:08.480 --> 01:01:14.960
-  much what his goal what he said today because he uh he stated that he had applied for the permit

01:01:14.960 --> 01:01:22.560
-  it's been at least nine months so the problem with that permit is anytime it comes back to say a

01:01:22.560 --> 01:01:28.480
-  contractor or an engineering firm they make review of it they make comments they get back with idem

01:01:28.480 --> 01:01:37.760
-  idem in their process their their clock starts back at zero they're allotted another 60 or 90 days

01:01:37.760 --> 01:01:44.080
-  to get it back to that so it's a back and forth and that's what seems to take the

01:01:44.080 --> 01:01:50.880
-  the full year to get this permit he said he applied for it like nine months ago so

01:01:50.880 --> 01:01:56.240
-  and and we offer to you know i i'm happy to reach out to my contact at idem that i worked with

01:01:56.240 --> 01:02:01.280
-  with the fullerton pike and maybe he could see where it's at and what stage it's at but um

01:02:01.280 --> 01:02:06.320
-  it's holding up a lot of permits i have some federal aid projects that's going through the

01:02:06.320 --> 01:02:11.680
-  same process okay and it has to do with the floodplain basically and the rise that you do

01:02:11.680 --> 01:02:17.520
-  in a floodplain so if it if you're the way i understand it is if your build is going to

01:02:17.520 --> 01:02:23.600
-  change the rise at all within that floodplain and that would cause a map revision that has to

01:02:23.600 --> 01:02:34.000
-  go through this process okay okay circle back around on our residential tiff just so i can

01:02:34.000 --> 01:02:40.160
-  identify as we're we keep talking about them what is the procedural aspect that we would have to go

01:02:40.160 --> 01:02:47.920
-  through to actually make one is it the legal aspect through the commissioners bring it through

01:02:47.920 --> 01:02:53.760
-  redevelopment because you know we've talked about it but i'm trying to get my head around and just

01:02:53.760 --> 01:02:59.360
-  for the public as a whole how that functionality would actually work where would we start and how

01:02:59.360 --> 01:03:07.120
-  would that progress well i guess the start would we develop a plan right and then the plan would

01:03:07.120 --> 01:03:13.200
-  come to the redevelopment commission and the redevelopment would preliminary approve

01:03:13.200 --> 01:03:19.490
-  preliminarily approve that plan then it would need to be it would go to the county commissioners

01:03:19.490 --> 01:03:19.600
-  and

01:03:19.600 --> 01:03:25.440
-  the county plan commission the plan commission reviews it to determine whether it fits with the

01:03:25.440 --> 01:03:30.880
-  county planning documents the commissioners review it for a kind of a broader scope of whether it's

01:03:30.880 --> 01:03:30.880
-  a

01:03:30.880 --> 01:03:37.600
-  good idea but could also certainly include the interpretation of the the planning ordinance and

01:03:37.600 --> 01:03:42.480
-  then it would come back to the redevelopment commission for a public hearing and then at that

01:03:42.480 --> 01:03:48.720
-  public hearing you have a public or from the the public you would then make a decision whether to

01:03:48.720 --> 01:03:59.200
-  move forward or not so that's kind of the process uh it's uh i think we've done it in two to three

01:03:59.200 --> 01:04:07.280
-  months before um but i think we had a probably a pretty developed plan at that point started the

01:04:07.280 --> 01:04:13.680
-  meetings themselves take about two to three months because of all the bodies that have to look at

01:04:13.680 --> 01:04:13.840
-  it

01:04:13.840 --> 01:04:20.480
-  starting point of it is a private developer bringing something to us

01:04:22.880 --> 01:04:29.760
-  what body would start that process because this body could start that yeah this body could say

01:04:29.760 --> 01:04:36.960
-  here's the map here's what we want to do here we want to and depending on how detailed you

01:04:36.960 --> 01:04:44.400
-  want it to be we want to include at roads here here and here or we just want to do this initial

01:04:44.400 --> 01:04:50.240
-  road and we'll amend the plan later to include these others the more details the better of course

01:04:51.120 --> 01:04:56.480
-  because then it gives the commissioners and the plan commission more more information on on their

01:04:56.480 --> 01:05:03.680
-  decision process but it would start here whether a developer brings it to you or or this group on

01:05:03.680 --> 01:05:09.680
-  its own does it i don't think we've ever had well i'm pretty sure the folton pike tiff did

01:05:09.680 --> 01:05:14.640
-  not start with the developer the west side tiff did not start with the developer north park might

01:05:14.640 --> 01:05:23.520
-  have or not north park state road 46 corridor might have um curry profile started with a developer

01:05:23.520 --> 01:05:31.840
-  that's where starting as we pick the air an area that needs redeveloped essentially and it would

01:05:31.840 --> 01:05:37.840
-  start at this i'm just trying to identify as we talk about this there has to be some expectation

01:05:38.720 --> 01:05:48.080
-  that its development is actually possible going forward in the time frame of the tiff that we

01:05:48.080 --> 01:05:54.320
-  would be creating 20 year time frame right well and i wish charlie was still on here but i think

01:05:54.320 --> 01:06:00.640
-  there are options and i and i would defer to the people who set up these tips much more regularly

01:06:00.640 --> 01:06:07.360
-  than i do where the clock doesn't start ticking until a bond is issued and i'm guessing there's

01:06:07.360 --> 01:06:11.760
-  probably a time period there where you have to do it and or it starts clipping typically that's

01:06:11.760 --> 01:06:12.000
-  like

01:06:12.000 --> 01:06:16.960
-  a with a bond anticipation note they can only go up to five years so i i mean i guess my gut

01:06:16.960 --> 01:06:17.440
-  reaction

01:06:17.440 --> 01:06:23.040
-  is that you probably would have five years to get somebody to start working and then once you issue

01:06:23.040 --> 01:06:33.280
-  that bond that's when the the district would actually form but we ever got clear we've got

01:06:33.280 --> 01:06:42.160
-  clarification that a multi-family project actually can pay into a residential tiff so that and i

01:06:42.160 --> 01:06:50.000
-  think commercial as well commercial and yes so that would increase the increment amount that

01:06:50.000 --> 01:06:59.360
-  we could collect if a residential tiff was established okay it seems like that's about

01:06:59.360 --> 01:07:05.520
-  the only way you could get that done is if you have a view got to be all of it yeah it's got to

01:07:05.520 --> 01:07:14.560
-  be all of it and make it worthwhile well and it uh the other thing that it can do you can actually

01:07:14.560 --> 01:07:15.520
-  buy land

01:07:15.520 --> 01:07:25.200
-  if money to bond to buy land

01:07:25.200 --> 01:07:32.720
-  and

01:07:32.720 --> 01:07:40.960
-  and i think any tiff district you're allowed to to buy land or buildings and things like that

01:07:40.960 --> 01:07:50.000
-  body bought the nursing school building ironically called the pain building at the time

01:07:51.120 --> 01:07:56.240
-  and and and bought that as the redevelopment commission and then we worked with ivy tech to

01:07:56.240 --> 01:08:03.040
-  get it well yeah french lick has done that if we don't want a real estate yeah we signed that i

01:08:03.040 --> 01:08:17.600
-  signed the deed and it's now the lee mark oddly enough fitting thing to have finally gotten

01:08:17.600 --> 01:08:27.360
-  accomplished on those tiffs though if it's a mixed use area you could cut out the residential side

01:08:27.360 --> 01:08:34.720
-  and not tiff that but just tiff the commercial part of it correct you could that's kind of what

01:08:34.720 --> 01:08:39.440
-  you and i have talked about so in my understanding is commercial could be in there but then the

01:08:39.440 --> 01:08:47.840
-  residential would go back to the schools i think you could do that i i guess my my reaction it

01:08:47.840 --> 01:08:52.720
-  depends what you want to do with the increment right if you want to if you want to have a lot of

01:08:52.720 --> 01:09:00.960
-  maybe much more you know down payment assistance those types of programs you'd really want it all

01:09:00.960 --> 01:09:10.000
-  in one in the same tiff district if you if it's an infrastructure i mean i i would be curious

01:09:10.000 --> 01:09:17.040
-  with that idea what would happen if you tiff the whole thing but you said all the residential was

01:09:17.040 --> 01:09:25.120
-  the excess assessed value and you you did all your payments based upon the the commercial area so

01:09:25.120 --> 01:09:31.360
-  that it would still be in the tiff districts you could expect spend money on that but the the

01:09:31.360 --> 01:09:31.600
-  property

01:09:31.600 --> 01:09:39.600
-  tax would would not go to the the tiff district i think that that is probably a little complicated

01:09:39.600 --> 01:09:45.520
-  for people who haven't dealt with tiffs for a long time but as richard mentioned prior prior to

01:09:45.520 --> 01:09:45.760
-  that

01:09:45.760 --> 01:09:52.720
-  law slipping in at the bottom of another law a year ago the residential tiff was set up for

01:09:52.720 --> 01:09:58.400
-  economically underdeveloped areas correct to try to try to promote residential growth that was the

01:09:58.400 --> 01:10:05.760
-  way the law read uh it had to do the previous law had to do with the number of homes built in the

01:10:05.760 --> 01:10:11.200
-  township single-family residents built in the township for the average over the previous three

01:10:11.200 --> 01:10:18.400
-  years i don't think it really which which may be a correlation with economically depressed probably

01:10:18.400 --> 01:10:25.200
-  is but it but it doesn't it didn't say that on the face i think the the the issue and until the

01:10:25.200 --> 01:10:33.040
-  legislature clarified it was how do you pay for the cost of a tiff district if you if you only have

01:10:33.040 --> 01:10:37.760
-  single-family homes right that was always today because they've got a long lead time before it's

01:10:37.760 --> 01:10:47.680
-  built out and the assessed value is is a lot lower than a multi-family and you know that a 1 cap on

01:10:47.680 --> 01:10:58.480
-  your on your property taxes is a lot different than a 2 or 3 worked hard to give us a residential

01:10:58.480 --> 01:11:08.880
-  tiff and then took all the ability to actually make it work away

01:11:08.880 --> 01:11:22.880
-  where we start where we end and if it's it starts here and it ends here no pressure

01:11:22.880 --> 01:11:38.000
-  all we can do is help a little and i for instance the westside tiff that developer

01:11:38.000 --> 01:11:45.200
-  was ge right i'm not sure developers right word but that business when the westside tiff started

01:11:45.200 --> 01:11:50.720
-  they were redoing all their manufacturing equipment and i think maybe even doing some expansion

01:11:52.000 --> 01:11:58.480
-  so that's that was the the cash flow that started the whole westside tiff is that

01:11:58.480 --> 01:12:04.080
-  i did learn today that the that subdivision

01:12:06.320 --> 01:12:26.720
-  worth of the point has started to see development now it's been been there for 15 years and it's

01:12:26.720 --> 01:12:47.280
-  actually friday morning they're putting in the side path along right now tony fox took that over

01:12:49.040 --> 01:13:01.520
-  yeah we're happy the point right the point across from the point across from the point

01:13:01.520 --> 01:13:10.960
-  housing with the arpa money we looked at that site for affordable housing

01:13:13.600 --> 01:13:20.080
-  which is too far away from transportation and other kinds of infrastructure to make

01:13:20.080 --> 01:13:25.360
-  it make sense for affordable housing oh yeah it's far away yeah yeah

01:13:25.360 --> 01:13:36.560
-  okay uh with that i think we will call this meeting adjourned thank you all for coming thank you
